Wood biomassOperatingCAISO

Woodland Biomass Power Ltd

Wood biomass power plant in Yolo County, California. 28 MW of nameplate capacity across 1 generator, operated by DTE Energy Services-Woodland.

Also known as Woodland Biomass Power · EIA plant 10836

Analyst: free account, 1 question a day.

Yolo County Solar ProjectMM Yolo PowerSCDA Solar 1Woodland Biomass Powe…5 km
Open in the map
6 plants within 14 km, from EIA coordinates.

Key facts

Capacity
28 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
September 1989First generator online
Operator
DTE Energy Services-WoodlandEIA operator ID 54806
Grid
CAISOBalancing authority CISO
Price nodes
1 CAISO nodeResource nodes with prices
Location
Yolo County, CA38.6905, −121.7371
EIA plant ID
10836EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Woodland Biomass Power Ltd produces

Free · EIA-923

Net generation, 2025

162 GWh

161,896 MWh, final

Capacity factor, 2025

66.0%

2024: 69.5%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2015 to 2025

31.1–191.4

GWh a year. Low 2020, high 2016

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001149,208Not reported12 of 12
2002170,184Not reported12 of 12
2003143,676Not reported11 of 12
2004173,520Not reported12 of 12
2005159,624Not reported12 of 12
2006146,496Not reported12 of 12
2007148,224Not reported12 of 12
2008165,312Not reported12 of 12
2009159,528Not reported12 of 12
2010175,58471.6%12 of 12
2011179,41273.1%12 of 12
2012183,26474.5%12 of 12
2013188,71276.9%12 of 12
2014183,43274.8%12 of 12
2015191,28078.0%12 of 12
2016191,42477.8%12 of 12
2017183,81974.9%12 of 12
2018187,73676.5%12 of 12
2019184,89475.4%12 of 12
202031,12712.7%12 of 12
202133,52613.7%12 of 12
2022182,44574.4%12 of 12
2023172,18470.2%12 of 12
2024170,88769.5%12 of 12
2025161,89666.0%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account · CAISO

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
GEN1Wood/Wood Waste Biomass28.0September 1989

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists DTE Energy Services-Woodland as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Generation potential vs reported

Monthly potential at seasonal net capability, next to EIA-923 output. Shows how much of the plant's capability was used.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Woodland Biomass Power Ltd and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Woodland Biomass Power Ltd

Questions about Woodland Biomass Power Ltd

How much power does Woodland Biomass Power Ltd produce?

Woodland Biomass Power Ltd reported 161,896 MWh (162 GWh) of net generation in 2025, a 66.0% capacity factor on 28 MW of nameplate capacity.

Where is Woodland Biomass Power Ltd?

Woodland Biomass Power Ltd is in Yolo County, California, at 38.6905, −121.7371. It is in the California Independent System Operator balancing area (CISO).

Who operates Woodland Biomass Power Ltd?

EIA-860M for August 2026 lists DTE Energy Services-Woodland as the operator (EIA operator ID 54806). The operator is not always the owner.

When did Woodland Biomass Power Ltd start operating?

Its first generator began operating in September 1989, according to EIA-860M.

Does InfraMap have power prices for Woodland Biomass Power Ltd?

Yes. InfraMap has CAISO day-ahead and real-time prices at 1 price node linked to Woodland Biomass Power Ltd, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • CAISO day-ahead and real-time prices; node and hub assignments as of 2026-10-05
  • Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)