Power plants in California
1,838 operating power projects with 107,415 MW of nameplate capacity, from EIA-860M for August 2026.
Projects
1,838
Nameplate capacity
107,415 MW
Counties with a plant
55
Operators
789
Power markets: CAISO prices
Capacity by fuel
MW is nameplate from operating generators and batteries. Plant counts use each project's primary fuel, so a coal and gas plant counts once.
Largest power plants in California
Top 50 · All 1,838 plants| Plant | Primary fuel | MW | County | Operator |
|---|---|---|---|---|
| Diablo Canyon | Nuclear | 2,323 | San Luis Obispo | Pacific Gas & Electric Co. |
| Dynegy Moss Landing Power Plant Hybrid | Natural gas and battery storage | 1,848 | Monterey | Dynegy -Moss Landing LLC |
| Haynes | Natural gas | 1,739 | Los Angeles | Los Angeles Department of Water & Power |
| Castaic | Pumped storage | 1,682 | Los Angeles | Los Angeles Department of Water & Power |
| Ormond Beach | Natural gas | 1,612 | Ventura | Ormond Beach Power, LLC |
| Geysers Unit 5-20 | Geothermal | 1,236 | Sonoma | Geysers Power Co LLC |
| La Paloma Generating Plant | Natural gas | 1,156 | Kern | CXA La Paloma LLC |
| AES Alamitos LLC | Natural gas | 1,115 | Los Angeles | AES Alamitos LLC |
| Helms Pumped Storage | Pumped storage | 1,053 | Fresno | Pacific Gas & Electric Co. |
| Mountainview Generating Station | Natural gas | 1,037 | San Bernardino | Southern California Edison Co |
California power plants by fuel
Newest plants in California
Ordered by the month the first generator began operating.
Counties with the most capacity
Largest operators in California
Grouped by EIA operator name. Parent companies are not merged.
All 1,838 plants in California, by county
Alameda County 31 plants
- Russell City Energy Center Natural gas · 655 MW
- Mariposa Energy Project Natural gas · 199.6 MW
- Dynegy Oakland Power Plant Oil · 149 MW
- Golden Hills Wind Wind · 85.9 MW
- Summit Winds Wind · 57.5 MW
- Alameda Natural gas · 54.8 MW
- Golden Hills North Wind Energy Center Wind · 46 MW
- PE Berkeley Natural gas · 28.5 MW
- Diablo Winds LLC Wind · 18 MW
- WWTP Power Generation Station Biomass · 6.6 MW
- Altamont Gas Recovery Landfill gas · 6 MW
- Power Generation Station (PGS) 2 Biomass · 4.6 MW
- Ameresco Vasco Road Landfill gas · 4.4 MW
- Whitethorn Solar LLC Solar · 3.3 MW
- Santa Rita Jail Hybrid Solar · 2.9 MW
- City of Hayward WWTP Solar · 2.7 MW
- Thermo Fisher Pleasanton Solar · 2.6 MW
- CA- US Foods- Livermore Solar · 2.4 MW
- Las Positas College Solar · 2.3 MW
- Preferred Freezer San Leandro Solar · 2 MW
- KSR028 Merced Fuel Cell Natural gas · 2 MW
- Union Sanitary District Cogen Biomass · 1.8 MW
- Santa Rita Jail Fuel Cell Natural gas · 1.4 MW
- Fremont - Kato Rd Solar · 1.4 MW
- Life Technologies - Fremont Natural gas · 1.3 MW
- Life Technologies - Pleasanton Natural gas · 1.1 MW
- Pixar - Emeryville Natural gas · 1.1 MW
- Kaiser Owens Dr. Fuel Cell Natural gas · 1 MW
- AT&T - Hayward Natural gas · 1 MW
- Delta Electronics Fremont Solar · 1 MW
- Fremont CA AutoFactory Solar · 0.3 MW
Amador County 5 plants
- Electra Hydro · 102.5 MW
- Tiger Creek Hydro · 52.2 MW
- Salt Springs Hydro · 42 MW
- West Point PH Hydro · 13.6 MW
- Oaks HOA Solar · 1 MW
Butte County 20 plants
- Edward C Hyatt Hydro · 644.1 MW
- Poe Hydro · 142.8 MW
- Thermalito Pumped storage · 115.1 MW
- Woodleaf Hydro · 67.2 MW
- Forbestown Hydro · 41.9 MW
- Cresta Hydro · 36.9 MW
- De Sabla Hydro · 18.4 MW
- Forks of Butte Hydro Project Hydro · 14.5 MW
- Sly Creek Hydro · 12.1 MW
- Kelly Ridge Hydro · 10 MW
- Oroville Cogeneration, LLC Natural gas · 7.7 MW
- Sierra Nevada Brewing Co Hybrid Natural gas · 4.2 MW
- Butte College Main Campus Solar Solar · 3.5 MW
- Thermalito Diverson Dam Hydro · 3.4 MW
- Gridley Main Two Solar · 2.5 MW
- Ameresco Butte County Landfill gas · 2.3 MW
- Toadtown Hydro · 1.8 MW
- Enloe Medical - Chico Natural gas · 1.7 MW
- 2127 Harris Solar Project Solar · 1.3 MW
- Gridley Main Solar · 1 MW
Calaveras County 5 plants
- Collierville Powerhouse Hydro · 253 MW
- Pardee Hydro · 23.6 MW
- Murphys Hydro · 3.6 MW
- New Hogan Power Plant Hydro · 3 MW
- Angels Hydro · 1.4 MW
Colusa County 4 plants
- Colusa Generating Station Natural gas · 712.4 MW
- Wadham Energy Biomass · 29.1 MW
- Abel Road Bioenergy Biomass · 4 MW
- CFF Rice Mill Solar Plant Solar · 3.5 MW
Contra Costa County 40 plants
- Delta Energy Center Natural gas · 943.5 MW
- Marsh Landing Generating Station Natural gas · 828 MW
- Los Medanos Energy Center Natural gas · 678.3 MW
- Gateway Generating Station Natural gas · 619.7 MW
- Crockett Cogen Project Natural gas · 247 MW
- Diablo Energy Storage Battery storage · 200 MW
- Richmond Cogen Natural gas · 173.5 MW
- Marathon Bay Area Cogen Natural gas · 113.5 MW
- Martinez Refining Natural gas · 100 MW
- Vasco Winds Wind · 78.2 MW
- Phillips 66 Rodeo Refinery Natural gas · 54.9 MW
- Riverview Energy Center Natural gas · 47 MW
- Buena Vista Energy LLC Wind · 38 MW
- P66 Rodeo Solar Solar · 30.2 MW
- Columbia Solar Energy, LLC Solar · 19.2 MW
- Marin Clean Energy Solar One Solar · 10.5 MW
- C&H Sugar Plant Other fuels · 8 MW
- Byron Highway Solar Solar · 5 MW
- Bear Creek Solar (Orinda) Solar · 5 MW
- Martinez Sulfuric Acid Regeneration Plt Other fuels · 4 MW
- Ameresco Keller Canyon Landfill gas · 3.8 MW
- CCCSD Wastewater Treatment Plnt Natural gas · 3.5 MW
- Nove Power Plant Landfill gas · 3 MW
- Bishop Ranch - BR 2600 Solar · 2.8 MW
- Bio-Rad Solar · 2.3 MW
- CA Dept of Public Health at Richmond Solar · 2.2 MW
- Central San Solar · 1.8 MW
- Bishop Ranch - BR 1-Y Solar · 1.8 MW
- Oakley Solar Project Solar · 1.5 MW
- Bishop Ranch - BR 8-P Solar · 1.5 MW
- Bishop Ranch - BR 8-O Solar · 1.5 MW
- Kaiser Deer Valley Rd. Fuel Cell Natural gas · 1.4 MW
- Bishop Ranch BR 1-X Solar · 1.4 MW
- CSD 2 - Heritage High Solar · 1.3 MW
- Bishop Ranch - BR 8-Q Solar · 1.2 MW
- Bishop Ranch - BR 15-AA Solar · 1.2 MW
- Bishop Ranch - BR 15-CC Solar · 1.2 MW
- Bishop Ranch - BR 15-DD Solar · 1.1 MW
- California PV Energy at ISD WWTP Solar · 1 MW
- CSD 2- Freedom High Solar · 0.9 MW
El Dorado County 15 plants
- White Rock/Slab Creek Hydro · 268.7 MW
- Jaybird Hydro · 161.6 MW
- Camino Hydro · 157.8 MW
- Loon Lake Hydro · 74.1 MW
- Union Valley Hydro · 38.6 MW
- Robbs Peak Hydro · 25.5 MW
- El Dorado Hydro · 20 MW
- Jones Fork Hydro · 10 MW
- Chili Bar Hydro · 8.3 MW
- Broadridge Cogen Natural gas · 5.2 MW
- Rock Creek LP Hydro · 3 MW
- Blue Shld Of Cal- El Dorado Hlls Mtr B Solar · 1.5 MW
- El Dorado County Solar · 1.5 MW
- El Dorado Solar, LLC Solar · 1.5 MW
- Deer Creek 2 Solar · 1.3 MW
Fresno County 100 plants
- Helms Pumped Storage Pumped storage · 1,053 MW
- Panoche Energy Center Natural gas · 432 MW
- Scarlet II Hybrid Solar · 350 MW
- Fifth Standard Solar PV, LLC (Hybrid) Solar · 287 MW
- RE Tranquillity Solar · 277.3 MW
- Scarlet Solar (CA) Solar · 240 MW
- Great Valley Solar Portfolio Holdings, L Solar · 202.5 MW
- Luna Valley Solar · 200 MW
- J S Eastwood Pumped storage · 199.8 MW
- Big Creek 3 Hydro · 174.5 MW
- Pine Flat Hydro · 165 MW
- Midway Peaking LLC Natural gas · 139.8 MW
- Kerckhoff 2 Hydro · 139.5 MW
- Haas Hydro · 135 MW
- Malaga Power LLC Natural gas · 121 MW
- Balch 2 Hydro · 97.2 MW
- Acid BESS Battery storage · 97 MW
- Big Creek 1 Hydro · 88.4 MW
- Fresno Cogen Partners Natural gas · 86.8 MW
- Big Creek 2 Hydro · 66.6 MW
- North Star Solar Solar · 61.6 MW
- Algonquin Power Sanger LLC Natural gas · 61.5 MW
- CalPeak Power Panoche Peaker Plant Natural gas · 60.5 MW
- Five Points Solar Park Solar · 60 MW
- Wellhead Power Panoche Natural gas · 56.7 MW
- Big Creek 2A Hydro · 55 MW
- Little Bear 4 Solar · 50 MW
- Little Bear 5 Solar · 50 MW
- Kings River PH Hydro · 48.6 MW
- Little Bear Solar 1, LLC Solar · 40 MW
- Friant Hydro Facility Hydro · 37.5 MW
- Kingsburg Cogen Natural gas · 36.2 MW
- Balch 1 Hydro · 31 MW
- Big Creek 8 Hydro · 30 MW
- San Joaquin Solar Solar · 21.3 MW
- Stroud Solar Station Solar · 20 MW
- Cantua Solar Station Solar · 20 MW
- Huron Solar Station Solar · 20 MW
- Gates Solar Station Solar · 20 MW
- Giffen Solar Park Solar · 20 MW
- Oro Loma Solar · 20 MW
- Whitney Point Solar Solar · 20 MW
- NextEra Westside PV Solar · 20 MW
- Little Bear 3 Solar · 20 MW
- RE Adams East, LLC Solar · 19 MW
- Westlands Solar PV Farm Solar · 18 MW
- Fresno-Clovis RWRF Solar · 16.5 MW
- Five Points Solar Station Solar · 15 MW
- Westside Solar Station Solar · 15 MW
- Coalinga 25D Cogen Natural gas · 13.6 MW
- Portal Hydro · 10.8 MW
- Giffen Solar · 10 MW
- West Gates Solar Station Solar · 10 MW
- Fresno Community Solar Solar · 10 MW
- Aspiration G Solar · 9 MW
- Saint Agnes Medical Center Natural gas · 7 MW
- Coalinga Cogeneration Facility Natural gas · 6.8 MW
- CalRenew-1 Solar · 5 MW
- Citizen B Solar · 5 MW
- Althea Avenue Solar Solar · 5 MW
- Conflitti Solar Solar · 4.4 MW
- Five Points Pipeline Solar · 4.1 MW
- Crystal Farms Local Solar Solar · 3.5 MW
- Fresno Solar Solar · 3 MW
- CA - Fresno, City of - SE Surface WTP Solar · 3 MW
- National Raisin Solar · 2.9 MW
- CA - Fresno County - Juvenile Hall Solar · 2.8 MW
- Reedley Community College Solar Solar · 2.6 MW
- Gap Pacific Distribution Center Solar · 2.4 MW
- Van der Hoek Solar Array/ Dairy Solar · 2.4 MW
- POM Plant 1 Solar · 2.4 MW
- SCCCD - Fresno Community College Solar · 2.2 MW
- Superior Almond Hulling Solar · 2.1 MW
- DSH (CA) - Coalinga State Hospital Solar · 2 MW
- OK Produce Fresno Carport Solar · 2 MW
- CA-DGS RFP-Pleasant Valley State Prison Solar · 2 MW
- OWC Energy Holdings, LLC Solar · 2 MW
- Fresno Sunnyside High School Hybrid Solar · 1.8 MW
- POM Beverage Solar Solar · 1.8 MW
- Open Sky Ranch Inc Solar · 1.7 MW
- Open Sky Dairy Solar · 1.7 MW
- Fresno Bullard High School Hybrid Solar · 1.6 MW
- POM Plant 2 Solar · 1.6 MW
- La Joya Del Sol Solar · 1.5 MW
- POM Juice Solar Solar · 1.5 MW
- Zonneveld Oak Grove Solar · 1.5 MW
- JD Foods - JD Foods Solar · 1.5 MW
- Fresno Hoover High School Hybrid Solar · 1.4 MW
- Moonlight Packing - Phase 2 Solar · 1.4 MW
- Tranquillity ID Solar · 1.3 MW
- Harris Farms Solar Facility Solar · 1.3 MW
- 2081 Terzian Solar Project Solar · 1.2 MW
- CDCR (CA) - Pleasant Valley State Prison Solar · 1.2 MW
- SCCCD - Clovis Community College Solar · 1.2 MW
- CSU Fresno Solar Project Solar · 1 MW
- Firebaugh-CCS-PV-1 Solar · 1 MW
- Van der Kooi Dairy Solar Array Solar · 1 MW
- Clovis High School Solar · 1 MW
- Clovis East High School Solar · 1 MW
- Clovis North High School Solar · 1 MW
Glenn County 2 plants
- Stony Gorge Hydro · 5 MW
- Adapture CA2, LLC Solar · 1.5 MW
Humboldt County 6 plants
- Humboldt Bay Natural gas · 167 MW
- Humboldt Sawmill Company Wood biomass · 25 MW
- Foster Clean Power B Solar · 5.2 MW
- Redwood Coast Airport Microgrid Solar · 4.4 MW
- Foster Clean Power A Solar · 4.3 MW
- Baker Creek Hydroelectric Hydro · 1.5 MW
Imperial County 71 plants
- El Centro Hybrid Natural gas · 388.3 MW
- Vikings Energy Farm Solar · 286.8 MW
- Ocotillo Express LLC Wind · 265.4 MW
- Mount Signal Solar Farm V Solar · 252.3 MW
- Big Rock Solar Farm Battery storage · 200 MW
- Imperial Valley Solar, LLC Solar · 199.9 MW
- Centinela Solar Energy Solar · 174.8 MW
- Solar Gen 2 Solar Facility Solar · 163.2 MW
- Mount Signal Solar Farm II Solar · 153.5 MW
- Imperial Solar Energy Center West Solar · 148.7 MW
- Campo Verde Solar Solar · 147.4 MW
- CED West Side Canal Battery Storage Battery storage · 131 MW
- Imperial Solar Energy Center South Solar · 128.9 MW
- LeConte Energy Storage Battery storage · 125 MW
- Niland Gas Turbine Plant Natural gas · 121 MW
- Wistaria Ranch Solar Solar · 106.7 MW
- Drew Solar LLC Solar · 100 MW
- Heber Geothermal Geothermal · 91.5 MW
- Arrowleaf Solar and Storage Solar · 77 MW
- Second Imperial Geothermal Geothermal · 74.5 MW
- Titan Solar 1 (CA) Solar · 70 MW
- Salton Sea Power LLC - Unit 5 Geothermal · 58.3 MW
- John L. Featherstone Plant Geothermal · 55 MW
- Salton Sea Power Gen Co - Unit 3 Geothermal · 53.9 MW
- Midway Solar Farm 1 Solar · 50 MW
- Rockwood Natural gas · 49.8 MW
- Salton Sea Power Gen Co - Unit 4 Geothermal · 47.5 MW
- CE Leathers Geothermal · 45.5 MW
- Del Ranch Company Geothermal · 45.5 MW
- Elmore Company Geothermal · 45.5 MW
- Vulcan-BN Geothermal Power Company Geothermal · 39.6 MW
- Pilot Knob Hydro · 33 MW
- Seville 2 Solar · 30 MW
- Midway Solar Farm II Solar · 30 MW
- Citizens Imperial Solar Solar · 30 MW
- Holtville Battery storage · 30 MW
- Ormesa III Geothermal · 24 MW
- Ormesa II Geothermal · 24 MW
- Imperial Valley Solar Company 1 LLC Solar · 23 MW
- Salton Sea Power Gen Co - Unit 2 Geothermal · 20 MW
- Sol Orchard El Centro PV Solar · 20 MW
- Calipatria Solar Farm Solar · 20 MW
- Imperial Valley Solar Co (IVSC) 2, LLC Solar · 20 MW
- Seville 1 Solar · 20 MW
- Midway Solar Farm III Solar · 20 MW
- Wister Solar Solar · 20 MW
- Drop 4 Hydro · 19.6 MW
- Ormesa I Geothermal · 19 MW
- North Brawley Geothermal Plant Geothermal · 16 MW
- CE Turbo LLC Geothermal · 11.5 MW
- Heber Solar Solar · 10.9 MW
- Drop 2 (CA) Hydro · 10 MW
- Salton Sea Power Gen Co - Unit 1 Geothermal · 10 MW
- Drop 3 (CA) Hydro · 9.2 MW
- Spreckels Sugar Company Natural gas · 8.9 MW
- Centinela State Prison Solar · 6 MW
- Calipatria State Prison Solar · 6 MW
- Community Solar 1 Solar · 5.7 MW
- Drop 1 Hydro · 5.7 MW
- Siphon Drop Power Plant Hydro · 4.4 MW
- Drop 5 (CA) Hydro · 4 MW
- SEPV Imperial Dixieland West Solar · 3 MW
- Valencia 1 Solar CA Solar · 3 MW
- IVC Solar Solar · 3 MW
- Valencia 2 Solar · 3 MW
- Valencia 3 Solar · 3 MW
- East Highline Hydro · 2.4 MW
- SEPV Imperial Dixieland East Solar · 2 MW
- Crown Cooling Facility Solar · 1 MW
- USG 1 Solar · 1 MW
- USG 2 Solar · 1 MW
Inyo County 19 plants
- Coso Finance Partners Geothermal · 92.2 MW
- Coso Power Developers Geothermal · 90 MW
- Coso Energy Developers Geothermal · 90 MW
- Coso Battery Storage Battery storage · 60 MW
- Control Gorge Hydro · 37.5 MW
- Mordor ES1 Battery storage · 25 MW
- Mordor ES2 Battery storage · 20 MW
- Bishop Creek 3 Hydro · 8.4 MW
- Bishop Creek 4 Hydro · 8.2 MW
- Bishop Creek 2 Hydro · 7.3 MW
- Haiwee Hydro · 5.6 MW
- Bishop Creek 5 Hydro · 4.5 MW
- Munro Valley Solar Solar · 4 MW
- Big Pine Creek Hydro · 3.2 MW
- Pleasant Valley Hydro Hydro · 3.2 MW
- Trona Solar III Solar · 2 MW
- Bishop Creek 6 Hydro · 1.6 MW
- Cottonwood Hydro · 1.6 MW
- Owens Valley Solar Project 11 Solar · 1 MW
Kern County 257 plants
- La Paloma Generating Plant Natural gas · 1,156 MW
- Bellefield Solar and Energy Storage Farm Solar · 1,000 MW
- Pastoria Energy Facility, LLC Natural gas · 779 MW
- Sunrise Power LLC Natural gas · 685.2 MW
- Elk Hills Power LLC Natural gas · 623 MW
- Eland Solar & Storage Center, Phase 1 Hy Solar · 459.6 MW
- Eland Solar & Storage Center, Phase 2 Hy Solar · 458 MW
- Golden Field Solar III, LLC Solar · 339 MW
- Solar Star 1 Solar · 318 MW
- Kern River Cogeneration Natural gas · 300 MW
- Sycamore Cogeneration Natural gas · 300 MW
- Edwards Sanborn E1A Solar · 293.3 MW
- Edwards Sanborn E1B Solar · 290.4 MW
- Solar Star 2 Solar · 279 MW
- RE Garland Solar · 273.1 MW
- Chaparral Springs Solar · 262 MW
- Edwards Sanborn E2 Solar · 257.8 MW
- Rosamond South 1 Solar · 257 MW
- Edwards Sanborn E4 Solar · 248.9 MW
- Northern Orchard Solar PV, LLC Solar · 242 MW
- Midway Sunset Cogen Natural gas · 234 MW
- Sandrini Solar 200 Solar · 200 MW
- Sandrini Solar 100 Solar · 195.4 MW
- Manzana Wind LLC Wind · 189 MW
- Sanborn BESS 3 Battery storage · 169 MW
- Alta Wind Energy Center V Wind · 168 MW
- Pinyon Pine I Wind · 168 MW
- BigBeau Solar, LLC Solar · 168 MW
- North Sky River Energy LLC Wind · 162 MW
- Springbok Solar Farm 2 Solar · 155 MW
- Pacific Wind LLC Wind · 151.7 MW
- North Rosamond Solar LLC Solar · 151.1 MW
- Alta Wind Energy Center I Wind · 150 MW
- Alta Wind Energy Center II Wind · 150 MW
- Alta Wind Energy Center III Wind · 150 MW
- Mustang Hills LLC Wind · 150 MW
- Alta Wind VIII Wind · 150 MW
- Edwards Sanborn 1C Solar · 148 MW
- Alta Wind X Wind · 138 MW
- Pine Tree Wind Power Project Wind · 135 MW
- Pinyon Pine II Wind · 132 MW
- Voyager Wind I Wind · 131.1 MW
- Voyager Wind II Wind · 128.7 MW
- AVEP BESS Battery storage · 126 MW
- Tumbleweed Energy Storage Battery storage · 125 MW
- Windstar 1 Wind · 120 MW
- Rabbitbrush Solar, LLC Solar · 120 MW
- Edwards Sanborn E5 Solar · 115 MW
- Valentine Solar, LLC Solar · 111.2 MW
- Catalina Solar LLC Solar · 110 MW
- Willow Spring Solar, LLC Solar · 107.9 MW
- Pastoria Solar Solar · 105.2 MW
- Springbok Solar Farm 1 Solar · 105 MW
- Alta Wind Energy Center IV Wind · 102 MW
- Brookfield Tehachapi 1 Wind · 102 MW
- RE Astoria Solar · 100 MW
- Sanborn BESS 1 Battery storage · 100 MW
- Sanborn BESS 2 Battery storage · 100 MW
- Rising Tree Wind Farm III Wind · 99 MW
- SF Azalea, LLC Solar · 98 MW
- South Belridge Cogeneration Facility Natural gas · 94.2 MW
- Springbok 3 Solar Farm Hybrid Solar · 91.5 MW
- Alta Wind XI Wind · 90 MW
- Mojave 16/17/18 Wind · 88.5 MW
- Edwards Sanborn S1 Solar · 84.6 MW
- Sagebrush ESS Battery storage · 80 MW
- Pastoria Power Bank Battery storage · 80 MW
- Rising Tree Wind Farm Wind · 79.2 MW
- Mojave 16/17/18 BESS Battery storage · 77 MW
- Hecate Energy Beacon Solar 1 Solar · 76 MW
- Mojave 3/4/5 Wind · 75 MW
- RE Astoria 2 Solar · 75 MW
- Edwards Sanborn S3 Solar · 70.7 MW
- RE Gaskell West 2 LLC Solar · 65 MW
- Point Wind Wind · 64.5 MW
- Oasis Wind Wind · 60.3 MW
- Sky River Wind Energy Center Wind · 60.2 MW
- Regulus Solar Project Solar · 60 MW
- RE Barren Ridge 1 Solar · 60 MW
- Edwards Sanborn S4 Solar · 60 MW
- Cameron Ridge LLC Wind · 59.6 MW
- Sagebrush Solar 2 ESS 59 Battery storage · 59 MW
- Hecate Energy Beacon Solar 3 Solar · 56 MW
- Golden Fields Solar I, LLC Solar · 54 MW
- Solar Star California, XLI, LLC Solar · 54 MW
- Hecate Energy Beacon Solar 4 Solar · 50 MW
- Double C Generation Limited Partnership Natural gas · 49.8 MW
- Kern Front Limited Natural gas · 49.8 MW
- High Sierra Limited Natural gas · 49.8 MW
- Kern River Eastridge Cogen Natural gas · 48.8 MW
- US Borax Natural gas · 48.2 MW
- Beacon Solar Plant Site 2 Solar · 47.3 MW
- Sanborn BESS 4 Battery storage · 47 MW
- Ridgetop Wind · 46.8 MW
- Bear Mountain Limited Natural gas · 46 MW
- Badger Creek Limited Natural gas · 46 MW
- Chalk Cliff Limited Natural gas · 46 MW
- McKittrick Limited Natural gas · 46 MW
- Live Oak Limited Natural gas · 46 MW
- RE Camelot LLC Solar · 45 MW
- Camino Solar Hybrid Solar · 44 MW
- Voyager Wind III Wind · 43.2 MW
- Kern River 3 Hydro · 40.3 MW
- Sagebrush Solar 2 ESS 40 Battery storage · 40 MW
- Berry Cogen Natural gas · 38.7 MW
- Edwards Sanborn E3 Solar · 38.1 MW
- Beacon Solar Plant Site 5 Solar · 37.8 MW
- Oak Creek Energy Systems I Wind · 34.5 MW
- Lost Hills/Blackwell Solar · 32 MW
- Chevron - Lost Hills Hybrid Solar · 30 MW
- Ridgetop Energy LLC Wind · 29 MW
- TPC Windfarms LLC Wind · 28.7 MW
- Western Power & Steam Inc Natural gas · 27.7 MW
- Difwind Farms Ltd VI Wind · 27.1 MW
- Hayworth Solar Solar · 27 MW
- Kern River 1 Hydro · 26.4 MW
- Victory Garden (Tehachapi) Wind · 26.1 MW
- 85 B Wind · 25.2 MW
- Southeast Kern River Cogen Natural gas · 24 MW
- CalPortland Company Mojave Wind Wind · 23.5 MW
- Voyager Wind IV Wind · 21.6 MW
- 85 A Wind · 21.3 MW
- RE Garland A Solar · 20.2 MW
- Tehachapi Wind Resource II Wind · 20.1 MW
- Adobe Solar Solar · 20 MW
- RE Rosamond One LLC Solar · 20 MW
- RE Rosamond Two LLC Solar · 20 MW
- RE Old River One, LLC Solar · 20 MW
- Rio Bravo Solar 1 LLC Solar · 20 MW
- Rio Bravo Solar II LLC Solar · 20 MW
- Pumpjack Solar I Solar · 20 MW
- Shafter Solar LLC Solar · 20 MW
- Algonquin SKIC20 Solar LLC Solar · 20 MW
- Blackwell Solar Park Solar · 20 MW
- Maricopa West Solar PV, LLC Solar · 20 MW
- Coronal Lost Hills Solar · 20 MW
- SEPV Mojave West Solar · 20 MW
- Kingbird A Solar LLC Solar · 20 MW
- Windhub Solar A LLC Solar · 20 MW
- Kingbird B Solar, LLC Solar · 20 MW
- Redwood 4 Solar Farm Solar · 20 MW
- Gaskell West 1 Solar Facility Solar · 20 MW
- RE Gaskell West 3 LLC Solar · 20 MW
- RE Gaskell West 4 LLC Solar · 20 MW
- RE Gaskell West 5 LLC Solar · 20 MW
- RB Inyokern Solar WDAT 1203 (CSG) Solar · 19.9 MW
- Rising Tree Wind Farm II Wind · 19.8 MW
- Wildwood Solar I, LLC Solar · 19.5 MW
- Berry Cogen Tanne Hills 18 Natural gas · 18 MW
- Catalina Solar 2, LLC Solar · 18 MW
- Wonderful Lost Hills Solar · 17.1 MW
- Redcrest Solar Farm Solar · 16.6 MW
- RE Columbia Two, LLC Solar · 15 MW
- Woodmere Solar Farm Solar · 15 MW
- Wildwood Solar II Solar · 15 MW
- Morelos del Sol Solar · 15 MW
- Oasis Alta Wind · 14.4 MW
- Taft 26C Cogen Natural gas · 12.4 MW
- Cymric 36W Cogen Natural gas · 12.4 MW
- McKittrick Cogen Natural gas · 12 MW
- Orion Solar I Solar · 12 MW
- Cottonwood Solar, LLC (Goose Lake) Solar · 12 MW
- RB Inyokern Solar WDAT 1281 (CSG) Solar · 11.9 MW
- Isabella Hydro Project Hydro · 11.8 MW
- Berry NMW Cogens Natural gas · 11.4 MW
- Naval Air Weapons Station China Lake Solar · 11.1 MW
- RE Columbia 3 LLC Solar · 10 MW
- Algonquin SKIC 10 Solar, LLC Solar · 10 MW
- Tehachapi Wind Resource I Wind · 8.7 MW
- Pine Tree Solar Project Solar · 8.5 MW
- Orion Solar II Solar · 8 MW
- Coram Energy LLC (ECT) Wind · 7.5 MW
- Terra-Gen VG Wind LLC Wind · 7.4 MW
- Lost Hills Cogeneration Plant Natural gas · 7 MW
- Cymric 31X Cogen Natural gas · 6.8 MW
- Cymric 6Z Cogen Natural gas · 6.8 MW
- SunSelect1 Natural gas · 6.6 MW
- Coram Tehachapi Wind · 6.5 MW
- Dome Project Natural gas · 6 MW
- Amazon Bakersfield 1 Solar Project Solar · 5.9 MW
- Bakersfield PV 1 Solar · 5.3 MW
- Lerdo Detention Facility - Solar 2, 3 Solar · 5.2 MW
- Welport Lease Project Natural gas · 5 MW
- RE Rio Grande Solar LLC Solar · 5 MW
- Wonderful Orchards - Westside Solar · 5 MW
- Wonderful Orchards - Belridge Solar · 5 MW
- Wheeler Ridge 2 Solar · 5 MW
- North Kern 3 Solar · 5 MW
- Nachtigall 1836-WD Solar · 4.6 MW
- Terry 1818-WD Solar · 4.6 MW
- Coram Energy LLC (4.5MW) Wind · 4.5 MW
- Kern Oil & Refining Co Natural gas · 4.5 MW
- Wheeler Ridge Solar · 4.5 MW
- North Kern State Prison Phase II Solar · 4 MW
- CA-DGS-California Correctional Inst Solar · 4 MW
- Wonderful Kings Solar · 3.5 MW
- Avalon Dairy Solar · 3.1 MW
- Coram Energy LLC Wind · 3 MW
- Edwards Air Force Base Solar · 3 MW
- CalCity Solar 1 Solar · 3 MW
- Eagle Creek Solar · 3 MW
- Kern Valley SP Solar · 3 MW
- Wonderful Orchards - West Valley Solar · 3 MW
- Flying Goose Solar · 3 MW
- North Kern Water Storage District Solar · 3 MW
- WPR RE Holdings Solar · 2.9 MW
- Sun Pacific - Lerdo Solar · 2.9 MW
- Wonderful Citrus - Delano Solar · 2.8 MW
- Ranch 3461 Solar · 2.8 MW
- Cawelo Water District Solar Solar · 2.5 MW
- North Kern 2 Solar · 2.5 MW
- North Kern 1 Solar · 2.5 MW
- Helzel & Schwarzhoff 86 Wind · 2.4 MW
- Kern Sunset 1886-WD Solar · 2.4 MW
- DGS Wasco State Prison Solar · 2.3 MW
- Wonderful Nursery Solar · 2.3 MW
- Highway 43 1887-WD Solar · 2.3 MW
- AVI Bakersfield Solar · 2.2 MW
- AEDG CA I, LLC Solar · 2.2 MW
- ABEC Bidart-Old River LLC Biomass · 2 MW
- Blackwell?s Corner Storage Facility Battery storage · 2 MW
- Sunny Cow Solar, LLC Solar · 2 MW
- California City Solar · 1.9 MW
- Lost Hills Oilfield Solar · 1.9 MW
- Inland Empire Solar · 1.8 MW
- Rosedale Solar · 1.8 MW
- ZCO Wind · 1.6 MW
- Broadway 4 - Target Shafter Solar · 1.6 MW
- IKEA Tejon 345 Solar · 1.5 MW
- Nickel 1 Solar Facility Solar · 1.5 MW
- CDCR (CA) - Wasco State Prison Solar · 1.5 MW
- Liberty HS Solar Project Solar · 1.5 MW
- Wonderful Huller & Shelling Solar · 1.5 MW
- Wingmaster Solar · 1.5 MW
- Lerdo East Solar · 1.5 MW
- Bakersfield 111 Solar · 1.4 MW
- Frontier HS Solar Project Solar · 1.4 MW
- Vulcan San Emidio Solar Solar · 1.4 MW
- Calibrant Bakersfield LLC Solar · 1.3 MW
- Tejon Castac Water District Solar Solar · 1.3 MW
- Kern Co Sheriff Solar · 1.2 MW
- Lakeview Battery Storage Facility Battery storage · 1.2 MW
- Allied Potato Solar · 1.2 MW
- Kern Del Oro Solar · 1.2 MW
- Improvement Dst No. 4 Solar · 1.1 MW
- EAFB - North Base Solar · 1 MW
- EAFB - South Base Solar · 1 MW
- E&B Resources Solar · 1 MW
- Delano Land 1 Solar · 1 MW
- Bakersfield Industrial PV 1 Solar · 1 MW
- ABEC #2 dba West-Star Dairy Biomass · 1 MW
- ABEC #3 dba Lakeview Dairy Biomass · 1 MW
- ABEC #4 dba CE&S Dairy Biomass · 1 MW
- Blue Skies Solar, LLC Solar · 1 MW
- City of Rosamond (CA) Solar · 1 MW
- Blankenship Solar · 1 MW
- Ranch 4260 Solar · 1 MW
Kings County 52 plants
- Solar Blue Solar · 475 MW
- Slate Hybrid Solar · 440.3 MW
- Chestnut Solar · 285.6 MW
- Aquamarine Solar · 250 MW
- RE Mustang LLC Solar · 175 MW
- Mustang Two Solar · 150 MW
- American Kings Solar, LLC Solar · 128 MW
- Henrietta Solar Project Solar · 102 MW
- Lead BESS 1 Battery storage · 99.4 MW
- Electrolyte BESS Battery storage · 99.4 MW
- Henrietta Peaker Natural gas · 98 MW
- Hanford Energy Park Peaker Natural gas · 92.2 MW
- Cherry Battery storage · 40 MW
- Lead BESS 2 Battery storage · 32 MW
- Sun City Project LLC Solar · 20 MW
- Guernsey Solar Station Solar · 20 MW
- RE Kansas South LLC Solar · 20 MW
- Corcoran Solar Solar · 20 MW
- RE Kansas Solar, LLC Solar · 20 MW
- RE Kent South, LLC Solar · 20 MW
- CID Solar, LLC Solar · 20 MW
- Kettleman Solar -Centaurus Solar · 20 MW
- Corcoran Solar 3 Solar · 20 MW
- Almond Solar · 19.9 MW
- Corcoran Solar 2 Solar · 19.8 MW
- Sand Drag LLC Solar · 19 MW
- CED Avenal Solar · 15.8 MW
- Java Solar, LLC Solar · 13.5 MW
- Cottonwood Solar, LLC (City of Corcoran) Solar · 12 MW
- Henrietta D Energy Storage LLC Battery storage · 10 MW
- Lemoore West Solar · 7.9 MW
- Avenal Park Solar · 6 MW
- CDCR (CA) - Corcoran State Prison Solar · 5 MW
- Canal Energy S23, LLC Solar · 4.1 MW
- Lakeside Pipeline Solar · 4.1 MW
- River Ranch Dairy Solar · 4 MW
- Corcoran Irrigation District Floating So Solar · 3.1 MW
- Hanford 1 and 2 Solar · 3 MW
- Kings CSG 3 LLC Community Solar Solar · 3 MW
- Community Solar Utica 1, LLC Solar · 3 MW
- Lone Oak Solar · 2.9 MW
- Dixie Creek Dairy Solar Solar · 2.9 MW
- Danell Bros Inc Solar · 2.6 MW
- Westside Solar Power PV1 Solar · 2 MW
- Corcoran Irrigation District Solar · 2 MW
- Lemoore 1 Solar · 1.5 MW
- Corcoran Solar · 1.1 MW
- Dover Dairy Solar · 1.1 MW
- Verwey-Hanford Dairy Digester #1 Biomass · 1 MW
- Verwey-Hanford Dairy Digester #2 Biomass · 1 MW
- Verwey-Hanford Dairy Digester #3 Biomass · 1 MW
- Still Water Power Biomass · 1 MW
Lake County 4 plants
- Calistoga Power Plant Geothermal · 176.4 MW
- Sonoma California Geothermal Geothermal · 78 MW
- West Ford Flat Battery storage · 25 MW
- Bear Canyon Battery storage · 13 MW
Lassen County 5 plants
- HL Power Wood biomass · 36.2 MW
- Muck Valley Hydroelectric Hydro · 29.9 MW
- HL Solar (Lassen) Solar · 7.6 MW
- High Sierra Cogeneration Plant Natural gas · 6.2 MW
- PSREC/SIAD Solar Solar · 2.5 MW
Los Angeles County 238 plants
- Haynes Natural gas · 1,739.1 MW
- Castaic Pumped storage · 1,682 MW
- AES Alamitos LLC Natural gas · 1,115 MW
- Scattergood Natural gas · 876 MW
- Valley (CA) Natural gas · 690.5 MW
- AES Alamitos Energy Center Natural gas · 678 MW
- Harbor Natural gas · 548.1 MW
- El Segundo Energy Center LLC Natural gas · 537.4 MW
- Walnut Creek Energy Park Natural gas · 500 MW
- Watson Cogeneration Natural gas · 405 MW
- Magnolia Power Project Natural gas · 387.6 MW
- Glenarm Natural gas · 265.6 MW
- AV Solar Ranch One Solar · 253 MW
- Long Beach Generation Natural gas · 252 MW
- Raceway Solar & Storage Solar · 205 MW
- Cathode (Hinson) BESS Battery storage · 200 MW
- Grayson Natural gas · 188.8 MW
- El Segundo Cogen Natural gas · 180.1 MW
- Malburg Natural gas · 130 MW
- Lancaster Area Battery Battery storage · 127 MW
- Harbor Cogen Natural gas · 107.4 MW
- Antelope Expansion 2 Solar · 105 MW
- AES ES Alamitos, LLC Battery storage · 100 MW
- San Pablo Raceway Solar · 100 MW
- Luna Storage Battery storage · 100 MW
- Cald BESS Battery storage · 100 MW
- Placerita ESS Battery storage · 88 MW
- Solverde 1 Solar · 85 MW
- Estrella Solar & Storage Solar · 84 MW
- AES ES Alamitos 2 LLC Battery storage · 82 MW
- W E Warne Hydro · 74.2 MW
- Alpine Solar Solar · 66 MW
- San Francisquito 1 Hydro · 65.5 MW
- Lake One Natural gas · 60.5 MW
- Center Hybrid Natural gas · 59.8 MW
- THUMS Natural gas · 57.4 MW
- Carson Cogeneration Natural gas · 55.8 MW
- Puente Hills Energy Recovery Landfill gas · 50 MW
- Antelope DSR 1 Solar · 50 MW
- UCLA So Campus Cogen Project Natural gas · 46.8 MW
- Berry Placerita Cogen Natural gas · 42.8 MW
- VESI Pomona Battery storage · 40 MW
- Elevation Solar C Solar · 40 MW
- Total Energy Facilities Biomass · 38.4 MW
- Valero Wilmington Cogeneration Plant Natural gas · 33.5 MW
- Hyperion Treatment Plant CHP Plant Biomass · 33 MW
- San Francisquito 2 Hydro · 32 MW
- Wilmington Hydrogen Plant Other fuels · 31.9 MW
- Torrance Refining Company, LLC Natural gas · 30 MW
- Sunshine Gas Producers Landfill gas · 23 MW
- Lockheed Martin Palmdale Solar PV Solar · 20.9 MW
- TA-High Desert LLC Solar · 20 MW
- Western Antelope Blue Sky Ranch A Solar · 20 MW
- Sierra Solar Greenworks Solar · 20 MW
- TA-Acacia, LLC Solar · 20 MW
- Solar Oasis LLC Solar · 20 MW
- Western Antelope Blue Sky B Solar · 20 MW
- North Lancaster Ranch Solar · 20 MW
- Central Antelope Dry Ranch C Solar · 20 MW
- Antelope Big Sky Ranch Solar · 20 MW
- Summer Solar LLC Solar · 20 MW
- Portal Ridge Solar B, LLC Solar · 20 MW
- Bayshore Solar B, LLC Solar · 20 MW
- Bayshore Solar C, LLC Solar · 20 MW
- Bayshore Solar A, LLC Solar · 20 MW
- Antelope DSR 3 Solar · 20 MW
- Alamo Hydro · 19.6 MW
- Antelope Expansion 1B Solar · 17 MW
- Antelope Expansion 3A Solar · 15 MW
- California Institute of Technology Natural gas · 13 MW
- H. Gonzales Natural gas · 11.8 MW
- Portal Ridge Solar C, LLC Solar · 11.4 MW
- SEPV Sierra Solar · 11.3 MW
- Western Antelope Dry Ranch Solar · 10 MW
- SEPV Palmdale East Solar · 10 MW
- San Dimas Hydro · 9.9 MW
- Pebbly Beach Generating Station Hybrid Oil · 9.7 MW
- Solar Star California, XLIV, LLC Solar · 9.5 MW
- Calabasas Gas to Energy Facility Landfill gas · 9.2 MW
- Central Utilities Plant LAX 2 Natural gas · 9.2 MW
- Foothill Feeder Hydro · 9 MW
- Foothill Hydro · 8.8 MW
- USPS PV Solar · 7.4 MW
- MM West Covina Landfill gas · 6.8 MW
- Summer North Solar Solar · 6.5 MW
- Pacifico Power Lancaster 01 Solar · 6.4 MW
- Signal Hill West Unit Natural gas · 5.7 MW
- Big Bear Solar · 5.5 MW
- Dominguez Plant Other fuels · 5 MW
- San Gabriel Hydro Project Hydro · 5 MW
- Lancaster Dry Farm Ranch B Solar · 5 MW
- Lancaster Little Rock Solar · 5 MW
- Antelope DSR 2 Solar · 5 MW
- Antelope Expansion 3B Solar · 5 MW
- LAX Rental Car Center Solar Power Plant Solar · 4.8 MW
- CSU Long Beach Lots 7 & 14 Solar · 4.5 MW
- SCV Water - Gladbach Water Treatment Plant Phases I and II Solar · 4.5 MW
- Kaiser - LA Natural gas · 4.5 MW
- VA Sepulveda Ambulatory Care Center Solar · 4.4 MW
- Biola University Hybrid Natural gas · 4.3 MW
- Arrache 8083 Solar · 4 MW
- Rutan Solar · 4 MW
- CA- US Foods- La Mirada Solar · 4 MW
- Pacifico Power Palmdale 01 Solar · 3.8 MW
- AVS Lancaster 1 Solar · 3.7 MW
- Yorktown Battery Energy Storage Facility Battery storage · 3.5 MW
- Cadillac Battery Energy Storage Facility Battery storage · 3.5 MW
- 8500 Balboa PV, LLC Solar · 3.2 MW
- Kaiser - Woodland Hills Natural gas · 3.1 MW
- Azusa Hydro · 3 MW
- MM Lopez Energy Landfill gas · 3 MW
- Lancaster WAD B Solar · 3 MW
- Little Rock Pham Solar Solar · 3 MW
- US-TOPCO (Soccer Center) Solar · 3 MW
- Weymouth Solar Plant Solar · 3 MW
- Central Antelope Dry Ranch B LLC Solar · 3 MW
- Westmont 300B Solar · 3 MW
- Green Beanworks C PV Solar · 3 MW
- Green Beanworks D PV Solar · 3 MW
- Green Beanworks B PV Solar · 3 MW
- Lancaster Solar · 3 MW
- Las Virgenes Solar · 3 MW
- Westmont 300A Solar · 2.9 MW
- Westmont 401 Solar · 2.9 MW
- San Fernando Hydro · 2.8 MW
- Toyota Long Beach Trigen Biomass · 2.8 MW
- Gilead Sciences La Verne Rooftop Solar Solar · 2.8 MW
- 20333 Normandie PV, LLC Solar · 2.6 MW
- CSU Long Beach Battery storage · 2.5 MW
- PAC Aviation Solar Solar · 2.5 MW
- Pacific Aviation Solar · 2.5 MW
- Westmont 400A Solar · 2.3 MW
- Walnut Unified School District Walnut HS Solar · 2.3 MW
- CSP Los Angeles Solar · 2.3 MW
- Whittier LFG Power Plant #1 Landfill gas · 2.2 MW
- Westmont 400B Solar · 2.2 MW
- CalTech - Pasadena Wilson Ave Natural gas · 2.2 MW
- Mid Counties DC 45 - sllax345 Solar · 2.2 MW
- Kaiser - Harbor City Natural gas · 2.1 MW
- Maclay Solar Project Solar · 2 MW
- SEPV 1 Solar · 2 MW
- Arrache 4006 Solar · 2 MW
- SEPV 18 Solar · 2 MW
- Freeway Springs Solar · 2 MW
- Glendale Battery Energy Storage System Battery storage · 2 MW
- One Ten Partners PV Solar · 2 MW
- Equinix Douglas St. Fuel Cell Natural gas · 2 MW
- Equinix Maple Ave. Fuel Cell Natural gas · 2 MW
- Downey Battery storage · 2 MW
- Rio Hondo Hydro · 1.9 MW
- Pierce College Solar · 1.9 MW
- Foundation CDCR LAC Wind · 1.9 MW
- Xebec 1 Solar · 1.9 MW
- Lafayette 2 - Internal Services Dept Solar · 1.9 MW
- Santa Fe Springs Rooftop Solar BLDG M Solar · 1.8 MW
- Westmont 301 Solar · 1.8 MW
- Prairie Solar · 1.8 MW
- Alta Sea Solar · 1.8 MW
- CPA Wilmington 1 Solar · 1.8 MW
- City of Long Beach Airport Lot A & B Solar · 1.8 MW
- VS RXI Mason-Chatsworth, LLC Solar · 1.8 MW
- GreenStruxure BBU004, LLC Solar · 1.8 MW
- Lafayette 2 - MLK Jr. Hospital (MLK) Solar · 1.7 MW
- CBS Television City Solar · 1.6 MW
- CFW Solar X LLC - Vaughn Solar · 1.6 MW
- KSR053 Cantara Fuel Cell Natural gas · 1.6 MW
- GreenStruxure REP009, LLC Natural gas · 1.6 MW
- Heliocentric Solar · 1.5 MW
- L-8 Solar Project Solar · 1.5 MW
- Industry MetroLink PV 1 Solar · 1.5 MW
- Radiance Solar 4 Solar · 1.5 MW
- Radiance Solar 5 Solar · 1.5 MW
- Arrache 4013 Solar · 1.5 MW
- Vinam Solar · 1.5 MW
- Ma Solar · 1.5 MW
- Horn Solar · 1.5 MW
- Rodeo Solar C2 Solar · 1.5 MW
- Rodeo Solar D2 Solar · 1.5 MW
- Summer Solar A2 Solar · 1.5 MW
- Summer Solar B2 Solar · 1.5 MW
- Summer Solar C2 Solar · 1.5 MW
- Santa Fe Springs Rooftop Solar BLDG H Solar · 1.5 MW
- Division 1 Solar · 1.5 MW
- Lancaster Solar 1 Solar · 1.5 MW
- Lancaster Solar 2 Solar · 1.5 MW
- Morgan Lancaster 1 Solar · 1.5 MW
- Long Beach Convention Center Battery storage · 1.5 MW
- 20701 Plummer PV, LLC Solar · 1.5 MW
- VS BC Pacific Gateway, LLC Solar · 1.4 MW
- Golden Springs Building D Solar · 1.3 MW
- CSU Northridge Plant Solar · 1.3 MW
- Forever 21 Retail, Inc. Solar · 1.3 MW
- Colon PV Solar · 1.3 MW
- Building F Solar · 1.3 MW
- Aerolease Solar · 1.3 MW
- South Bay Dis Ctr 20-SLLAX512 Solar · 1.3 MW
- East Portal Generator Hydro · 1.2 MW
- Saint Johns Health Center Natural gas · 1.2 MW
- Bolthouse S&P and Rowen Farms Solar Solar · 1.2 MW
- Los Angeles Harbor College Solar · 1.2 MW
- Golden Springs Building C-1 Solar · 1.2 MW
- Building G Solar · 1.2 MW
- Francisco St. Solar Solar · 1.2 MW
- Commerce Distribution Center 4-SLLAX113 Solar · 1.2 MW
- JFC Slauson - SLLAX071 Solar · 1.2 MW
- Toyon Power Station Landfill gas · 1.1 MW
- Metro Support Services Center Solar Solar · 1.1 MW
- Staples La Mirada, CA Solar · 1.1 MW
- ISH Solar Hospital Downey Solar · 1.1 MW
- Port of LA Solar FiT Project Solar · 1.1 MW
- Chatsworth Industrial Center 1-SLLAX601 Solar · 1.1 MW
- Caltech Central Natural gas · 1.1 MW
- ELACC Photovoltaic Power Facility Solar · 1 MW
- Occidental College Solar Project Solar · 1 MW
- 2555 E Olympic Bl Solar · 1 MW
- Kaiser Downey Natural gas · 1 MW
- Lancaster Baptist Church Solar · 1 MW
- Summer Solar D2 Solar · 1 MW
- Las Virgenes Municipal Water District Solar · 1 MW
- Division 2 Solar · 1 MW
- Division 3 Solar · 1 MW
- Kettering Solar 1 Solar · 1 MW
- Kettering Solar 2 Solar · 1 MW
- Buidling L Solar · 1 MW
- Ratkovich Alhambra Natural gas · 1 MW
- Disney Prospect Natural gas · 1 MW
- ATT Van Nyus Natural gas · 1 MW
- ATT Ventura Blvd Natural gas · 1 MW
- Catalina Express Solar · 1 MW
- Marina South Solar · 1 MW
- CalTech - Pasadena (PPA) Natural gas · 1 MW
- DirecTV - Los Angeles Natural gas · 1 MW
- AT&T - Gardena Natural gas · 1 MW
- AT&T - Hawthorne Natural gas · 1 MW
- Comcast - Universal City Natural gas · 1 MW
- CPA 2132 E Dominguez Solar · 1 MW
- Nordhoff Place Solar · 0.9 MW
- Dedeaux Solar · 0.9 MW
Madera County 20 plants
- Mammoth Pool Hydro · 190 MW
- Big Creek 4 Hydro · 100 MW
- Borden Solar Farm Solar · 50 MW
- Chowchilla II Natural gas · 49.6 MW
- Adera Solar Solar · 20 MW
- KDC Solar Madera LLC Solar · 10 MW
- Avenue 26 Solar Solar · 7.6 MW
- Wonderful Firebaugh Solar · 5.4 MW
- Wonderful Orchards - New Columbia Solar · 5 MW
- Costa View Farms Solar · 5 MW
- Pacific Ethanol Madera Solar Array Solar · 4.3 MW
- Sealed Air Madera Solar Project Solar · 3.8 MW
- DGS Valley State Prison Solar · 2.3 MW
- Site 980 65 Hydro · 2.1 MW
- DGS Central California Womens Facility Solar · 2 MW
- Diamond H Dairy Power Biomass · 2 MW
- Madera 1 PV Solar · 1.5 MW
- CA - Madera USD - Madera South HS Solar · 1.2 MW
- City of Madera WWTP Solar · 1 MW
- Madera Community Hospital Solar · 1 MW
Marin County 3 plants
- Waste Mangement Redwood LFGTE Landfill gas · 4 MW
- Silveira Ranch Road Solar Solar · 3 MW
- Cottonwood Solar, LLC Cottonwood Carport Solar · 1 MW
Mendocino County 3 plants
- Redemeyer Road Solar Solar · 8 MW
- Lake Mendocino Hydro · 3.5 MW
- Kama 1 LLC Solar · 2 MW
Merced County 24 plants
- W R Gianelli Pumped storage · 424 MW
- Wright Solar Park Solar · 200 MW
- Quinto Solar PV Project Solar · 108 MW
- ONeill Pumped storage · 25.2 MW
- Vega Solar Solar · 20 MW
- UC Merced Solar Hybrid Solar · 5 MW
- Merced Pipeline Solar · 4.1 MW
- Merced Falls Hydro · 3.4 MW
- Merced 1 PV Solar · 3 MW
- East Cleveland Road Solar Solar · 3 MW
- Dos Palos Clean Power Solar · 3 MW
- Parker Hydro · 2.7 MW
- West Tambo Clean Power II Solar · 2 MW
- Godinho Dairy Digester Biomass · 2 MW
- Lara 2 Hybrid Solar · 1.6 MW
- 2097 Helton Solar Project Solar · 1.5 MW
- Merced Solar LLC Solar · 1.5 MW
- Mission Solar LLC Solar · 1.5 MW
- Sun Harvest Solar NDP1 Solar · 1.5 MW
- Henry Miller RD Solar · 1.5 MW
- City of Atwater NEM Solar · 1.5 MW
- Five H Farms Solar Array Solar · 1 MW
- Broadway 3 - UC Merced 1 Solar · 1 MW
- Dos Palos Cooperative Gin Solar · 1 MW
Mono County 9 plants
- CD4 Geothermal · 44.4 MW
- Middle Gorge Hydro · 37.5 MW
- Upper Gorge Hydro · 37.5 MW
- Mammoth G3 Geothermal · 15 MW
- Mammoth G2 Geothermal · 15 MW
- Rush Creek Hydro · 13.1 MW
- Poole Hydro · 11.3 MW
- Mammoth G1 Geothermal · 10 MW
- Lundy Hydro · 3 MW
Monterey County 23 plants
- Dynegy Moss Landing Power Plant Hybrid Natural gas · 1,848 MW
- King City Power Plant Natural gas · 133.2 MW
- Cal Flats BESS Battery storage · 60 MW
- King City Peaking Natural gas · 47.3 MW
- Salinas River Cogeneration Natural gas · 38.9 MW
- Foundation Dole Fresh Vegetables Wind · 5.6 MW
- Marina Landfill Gas Landfill gas · 5.1 MW
- Blackjack Solar Solar · 4 MW
- CA-DGS RFP-Salinas Valley State Prison Solar · 3.3 MW
- Aera San Ardo Cogen Facility Natural gas · 3.2 MW
- TLR000 Hansen Fuel Cell Natural gas · 3 MW
- D'Arrigo Brothers - Phase 4 Solar · 2.2 MW
- Foundation Scheid Vineyards Wind · 1.9 MW
- Foundation California Training Facility Wind · 1.8 MW
- Foundation Mann Packing Wind · 1.8 MW
- Foundation SaIinas Valley State Prison Wind · 1.8 MW
- Monterey One Water Biomass · 1.8 MW
- CA-DGS- RFP-Correctional Training Fac Solar · 1.6 MW
- Ameresco Johnson Canyon Landfill gas · 1.4 MW
- Monterey Regional Water Pollution Contro Solar · 1 MW
- City of Soledad Water Reclamation Wind · 1 MW
- Taylor Farms Wind · 1 MW
- Taylor Farms - Schilling Place Natural gas · 1 MW
Napa County 6 plants
- Calistoga Resilency Center Other fuels · 19.3 MW
- Kaiser Napa Valley Corporate Dr Fuel Cel Natural gas · 4.8 MW
- American Canyon Solar Solar · 3 MW
- Soscol Ferry Solar Solar · 2 MW
- Sutter Home Winery GIR Solar · 1.1 MW
- Pacific Union College BESS Battery storage · 1 MW
Nevada County 9 plants
- Chicago Park Hydro · 44 MW
- Dutch Flat 2 Hydro · 27.3 MW
- Narrows PH Hydro · 10.2 MW
- Spaulding 1 Hydro · 7 MW
- Spaulding 3 Hydro · 6.6 MW
- Deer Creek PH Hydro · 5.5 MW
- Bowman Hydro · 3.6 MW
- Combie South Hydro · 1.5 MW
- Scott Flat Hydro · 1 MW
Orange County 42 plants
- AES Huntington Beach Energy Project Natural gas · 699.2 MW
- AES Huntington Beach LLC Natural gas · 218 MW
- Stanton Energy Reliability Center Hybrid Natural gas · 161 MW
- Canyon Power Plant Natural gas · 150 MW
- Johanna Energy Center, LLC Battery storage · 80 MW
- Stanton Battery Energy Storage Battery storage · 68.8 MW
- Barre Peaker Natural gas · 49.8 MW
- Brea Expansion Plant Landfill gas · 35.7 MW
- BCE Seal Beach Solar · 28.7 MW
- Bowerman Power LFG, LLC Landfill gas · 23.8 MW
- Hecate Energy Johanna Facility Battery storage · 20 MW
- BCE Los Alamitos 2 Solar · 20 MW
- BCE Los Alamitos 1 Solar · 20 MW
- UCI Facilities Management Central Plant Natural gas · 19 MW
- Plant No 2 Orange County Biomass and other fuels · 16 MW
- Blacksand Generating Facility Natural gas · 9.6 MW
- CSUF Trigeneration Natural gas · 8.9 MW
- Plant No 1 Orange County Biomass · 7.5 MW
- HEBT Irvine 2 Battery storage · 5.8 MW
- Hoag Hospital Cogen Plant Natural gas · 5.5 MW
- HEBT Irvine 1 Battery storage · 5.5 MW
- Orange Coast College PH2 Solar Project Solar · 5.2 MW
- Yorba Linda Hydro · 5.1 MW
- OCSD Battery storage · 4.9 MW
- Valley View Hydro · 4.1 MW
- Coyote Creek Hydro · 3.1 MW
- Kaiser East La Palma Ave. Fuel Cell Natural gas · 2.2 MW
- Anaheim Solar Energy Plant Solar · 2.1 MW
- CSUF Nutwood Solar Solar · 1.9 MW
- Allergan Battery storage · 1.5 MW
- DESI-2 Battery Storage Facility Battery storage · 1.4 MW
- AT&T Anaheim Natural gas · 1.3 MW
- SOCCD Battery storage · 1.3 MW
- Alticor Inc - Solar Project Solar · 1.2 MW
- Baker Battery storage · 1.2 MW
- Kroger La Habra Solar · 1.2 MW
- Ortega Highway Energy Storage Battery storage · 1 MW
- CSUF State College Solar · 1 MW
- Baldwin (CA) Battery storage · 1 MW
- ATT Kelvin Natural gas · 1 MW
- DATS Battery storage · 1 MW
- LAWRP Battery storage · 1 MW
Placer County 20 plants
- Roseville Energy Park Natural gas · 165 MW
- Middle Fork Hydro · 122.4 MW
- Ralston Hydro · 79.2 MW
- Drum 2 Hydro · 53.1 MW
- Drum 1 Hydro · 49.2 MW
- Rio Bravo Rocklin Wood biomass · 27.9 MW
- Dutch Flat Hydro · 22 MW
- Sierra Pacific Lincoln Facility Wood biomass · 19.2 MW
- Wise Hydro · 16.4 MW
- French Meadows Hydro · 15.3 MW
- Kings Beach Oil · 15 MW
- Halsey Hydro · 13.6 MW
- Newcastle Hydro · 12.7 MW
- Rollins Hydro · 12.1 MW
- Sacramento Municipal Util Dist Hydro · 7.2 MW
- Oxbow (CA) Hydro · 6.1 MW
- Lincoln Landfill Landfill gas · 4.8 MW
- Lincoln WWTF Hybrid Solar · 4 MW
- Alta Powerhouse Hydro · 1 MW
- San Francisco Bay Coffee Solar · 1 MW
Plumas County 9 plants
- Rock Creek Hydro · 126 MW
- Belden Hydro · 117.9 MW
- Caribou 2 Hydro · 117.9 MW
- Caribou 1 Hydro · 73.8 MW
- Butt Valley Hydro · 40 MW
- Sierra Pacific Quincy Facility Wood biomass · 35.2 MW
- Bucks Creek Hydro · 33 MW
- Grizzly Hydro · 22 MW
- Collins Pine Project Wood biomass · 5 MW
Riverside County 119 plants
- Sentinel Energy Center, LLC Natural gas · 800 MW
- Menifee Power Bank Battery storage · 680 MW
- Blythe Energy Inc Natural gas · 591 MW
- McCoy Solar Energy Project Hybrid Solar · 500.6 MW
- Desert Quartzite Solar · 450 MW
- Arica Solar Solar · 399 MW
- Oberon Solar Project Solar · 375 MW
- Oberon II Solar Project Solar · 375 MW
- Arlington Energy Center II Solar · 365 MW
- Crimson Battery storage · 350 MW
- Easley Solar Battery storage · 350 MW
- Blythe Mesa Solar II Solar · 335.6 MW
- Desert Peak Energy Storage I Battery storage · 325 MW
- Desert Sunlight 300, LLC Solar · 313.7 MW
- Blythe Solar III, LLC Hybrid Solar · 251.8 MW
- Genesis Solar Energy Project Solar · 250 MW
- Athos Solar Project Solar · 250 MW
- Victory Pass Solar · 250 MW
- Desert Sunlight 250, LLC Solar · 249.7 MW
- Blythe Solar II, LLC Solar · 246.2 MW
- Arlington Energy Center III Solar · 241 MW
- Sunlight Storage Battery storage · 230 MW
- Sunlight Storage II Battery storage · 230 MW
- SE Athos II, LLC Solar · 200 MW
- Riverside Energy Resource Center Natural gas · 196 MW
- Blythe Solar IV, LLC Solar · 184.4 MW
- Blythe Solar 110, LLC Solar · 172.8 MW
- Maverick Solar 6, LLC Solar · 150 MW
- Indigo Energy Facility Natural gas · 149.7 MW
- Maverick Solar 7, LLC Solar · 132 MW
- Maverick Solar, LLC Solar · 125 MW
- Beaumont BESS Battery storage · 116.6 MW
- Desert Harvest II LLC Solar · 105 MW
- Maverick Solar 4, LLC Solar · 100 MW
- Coachella Natural gas · 92.4 MW
- Desert Harvest, LLC Solar · 80 MW
- Desert Peak Energy Storage II Battery storage · 75 MW
- Colgreen North Shore Solar Farm Solar · 74.8 MW
- Mountain View I & II Wind · 70.9 MW
- San Jacinto Grid, LLC Battery storage · 65 MW
- Whitewater Hill Wind Partners Wind · 61.5 MW
- Coachella Hills Wind Wind · 61.2 MW
- San Gorgonio Windplant WPP1993 Wind · 49.5 MW
- Clearwater Power Plant Natural gas · 49 MW
- Mountain View IV Wind · 49 MW
- Painted Hills Wind Park Wind · 46.8 MW
- Dillon Wind LLC Wind · 45 MW
- San Gorgonio Westwinds II LLC Wind · 43.4 MW
- Cabazon Wind Partners Wind · 41 MW
- Springs Generating Station Natural gas · 40 MW
- Salka Cabazon Wind Wind · 38.9 MW
- San Gorgonio Farms Wind Farm Wind · 31 MW
- Mesa Wind Power LLC Wind · 30 MW
- Diamond Valley Lake Hydro · 29.7 MW
- AM Wind Repower Wind · 27 MW
- Mountain View III Wind · 22.4 MW
- Solar Blythe LLC Solar · 21 MW
- Edom Hills Project 1 LLC Wind · 20 MW
- AP North Lake I, LP Solar · 20 MW
- Solar Blythe 2 Solar · 20 MW
- Ortega Grid, LLC Battery storage · 20 MW
- Karen Avenue Wind Farm Wind · 11.7 MW
- Hecate Energy Desert Storage 1 LLC Battery storage · 10 MW
- Carris Storage I Battery storage · 10 MW
- Perris Hydro · 7.9 MW
- SunAnza Solar · 7.8 MW
- Tequesquite Landfill Solar PV Project Solar · 7.3 MW
- Garnet Wind Energy Center Wind · 6.5 MW
- Wagner Wind LLC Wind · 6 MW
- Foundation NWNA Wind · 5.1 MW
- Lake Mathews Hydro · 4.9 MW
- CA Jurupa Valley 3251 De Forest Circle Solar · 4.5 MW
- EMWD - San Jacinto RES BCT Solar · 4.2 MW
- RCWD PV Project Solar · 4.1 MW
- North Palm Springs 4A Solar · 4 MW
- Chuckawalla Solar Solar · 4 MW
- Ironwood Solar LLC Solar · 4 MW
- Garnet Solar Generation Station I LLC Solar · 4 MW
- UC Riverside Lots 30 & 32 Solar · 4 MW
- Amazon PSP1 Solar · 3.8 MW
- EMWD - Perris Valley RWRF Solar · 3.4 MW
- East Winds Project Wind · 3 MW
- Mira Loma Solar · 3 MW
- Wildcat I Energy Storage LLC Battery storage · 3 MW
- Broadway 2 - UC Riverside Solar · 3 MW
- Morongo CRS 1 Solar · 3 MW
- Temescal Hydro · 2.9 MW
- Corona Hydro · 2.9 MW
- Riverside Community College Solar · 2.6 MW
- North Palm Springs 1A Solar · 2.5 MW
- SSI West Riverside Landfill LLC Solar · 2.5 MW
- EMWD - Moreno Valley RWRF Solar · 2.4 MW
- Chambers 4 - Eastvale LGB3 Solar · 2.4 MW
- Chambers 4 - Riverside LGB6 Solar · 2.4 MW
- Desert Hot Springs Solar Solar · 2.3 MW
- Phoenix Wind Power LLC Wind · 2.1 MW
- Foundation RRM Wind · 2 MW
- Dulles Solar · 2 MW
- Soboba Community Solar Project Solar · 2 MW
- Palm Springs DAC PV Solar · 1.9 MW
- EMWD - Sun City RWRF Solar · 1.6 MW
- Temescal Canyon RV, LLC Solar · 1.5 MW
- San Antonio West Solar Rooftop Solar · 1.5 MW
- Venable Solar 1 Solar · 1.5 MW
- Venable Solar 2 Solar · 1.5 MW
- Park Meridian #1 Solar · 1.5 MW
- Chambers 4 - Eastvale DCA2 Solar · 1.5 MW
- Riverside RWQCP Fuel Cell Biomass · 1.4 MW
- Diamond Valley Solar Project Solar · 1.3 MW
- EMWD - San Jacinto RWRF NEM Solar · 1.3 MW
- Municipal Cogen Plant Natural gas · 1.2 MW
- Palo Verde College Solar · 1.2 MW
- SunEdison Walgreens Moreno Valley Solar · 1 MW
- SunEdison Ironwood State Prison Solar · 1 MW
- Chuckawalla Valley State Prison Solar · 1 MW
- Tahquitz High School Solar · 1 MW
- West Valley High School Solar Solar · 1 MW
- Valley Sanitary District WTP Solar Solar · 1 MW
- Lake Elsinore Canopies - Lakeside HS Solar · 1 MW
Sacramento County 62 plants
- Cosumnes Power Plant Natural gas · 556.8 MW
- Folsom Hydro · 198.6 MW
- Procter & Gamble Power Plant Natural gas · 193.4 MW
- Campbell Power Plant Natural gas · 173.9 MW
- Rancho Seco Solar II, LLC Solar · 160 MW
- Carson Power Plant Natural gas · 125.5 MW
- McClellan (CA) Natural gas · 77 MW
- SloughHouse Solar, LLC Solar · 50 MW
- SMUD at Grundman Solar · 17 MW
- Kiefer Landfill Landfill gas · 15.2 MW
- Nimbus Hydro · 13.4 MW
- Wildflower Solar 1 Solar · 13 MW
- Rancho Seco Solar, LLC Solar · 10.8 MW
- SCDA Solar 1 Solar · 7 MW
- Kiefer Landfill Generating Phase II Landfill gas · 6.2 MW
- Intel Folsom Phase 3 Solar · 5.2 MW
- RE Kammerer 1 LLC Solar · 5 MW
- RE Kammerer 2 LLC Solar · 5 MW
- RE Kammerer 3 LLC Solar · 5 MW
- RE Bruceville 1 LLC Solar · 5 MW
- RE Bruceville 2 LLC Solar · 5 MW
- RE Bruceville 3 LLC Solar · 5 MW
- RE McKenzie 1 LLC Solar · 5 MW
- RE McKenzie 2 LLC Solar · 5 MW
- RE McKenzie 3 LLC Solar · 5 MW
- RE McKenzie 4 LLC Solar · 5 MW
- RE McKenzie 5 LLC Solar · 5 MW
- RE McKenzie 6 LLC Solar · 5 MW
- Sacramento Regional County Sanitation PV Solar · 3.5 MW
- Aerojet I Solar · 3 MW
- RE Dillard 1 LLC Solar · 3 MW
- RE Dillard 2 LLC Solar · 3 MW
- RE Dillard 3 LLC Solar · 3 MW
- Green Acres Solar Facility 1 Solar · 3 MW
- Depot Park Solar System Solar · 3 MW
- SMUD at Van Conett Solar · 2.9 MW
- SMUD at Fleshman Solar · 2.9 MW
- Dept of General Services -FTB Solar · 2.7 MW
- Chambers 4 - Sacramento SMF1 Solar · 2.7 MW
- CA - Amazon - SMF6 Solar · 2.6 MW
- Department of Justice Solar · 2.4 MW
- Aerojet II Solar · 2.2 MW
- Solar Star California II LLC Solar · 2 MW
- Renew Solar ABC Sacramento LLC Solar · 1.7 MW
- KP South Sacramento Hospital Solar Solar · 1.7 MW
- Sacramento (SMUD) Solar · 1.4 MW
- Folsom SP and CSP Sacramento Solar · 1.3 MW
- Sacramento Point West Medical Offices Solar · 1.3 MW
- CSU Sacramento I Solar · 1.3 MW
- US GSA - Sacramento Solar · 1.1 MW
- Rancho Cordova Medical Offices Solar · 1.1 MW
- Sacramento Soleil LLC Solar · 1 MW
- FRV SI Transport Solar LP Solar · 1 MW
- SMUD at Lawrence Solar · 1 MW
- Green Acres Solar Facility 2 Solar · 1 MW
- Intel Folsom Solar · 1 MW
- FAA NorCal TRACON Solar · 1 MW
- Sacramento Fairbain Water Treatment Plan Solar · 1 MW
- Intel Folsom Phase 2 Solar · 1 MW
- Strata Roof 1 Solar · 1 MW
- CA- US Foods- Sacramento (McClellan) Solar · 1 MW
- RE Dillard 4 LLC Solar · 0.4 MW
San Benito County 5 plants
- Panoche Valley Solar Farm Solar · 140 MW
- Graniterock Quarry Solar · 4.4 MW
- Enerparc CA1 LLC Solar · 1.5 MW
- Hollister Solar LLC Solar · 1.5 MW
- Hollister Wastewater Facility Solar · 1 MW
San Bernardino County 123 plants
- Mountainview Generating Station Natural gas · 1,036.8 MW
- High Desert Power Plant Natural gas · 960 MW
- Daggett 3 Solar · 449 MW
- Daggett 2 Solar · 313 MW
- Stateline Solar Solar · 299.5 MW
- Mojave Solar Project Solar · 280 MW
- Devil Canyon Hydro · 276.2 MW
- Baldy Mesa Solar & Storage Solar · 225 MW
- Condor Energy Storage LLC Battery storage · 200 MW
- Aratina Solar Center 1A Solar · 195 MW
- Lockhart Solar PV, LLC Solar · 169.4 MW
- Resurgence Solar Solar · 165 MW
- Hudson - High Desert Hybrid Solar · 150 MW
- Lockhart Solar PV II Solar · 144.1 MW
- Ivanpah 2 Solar · 133.4 MW
- Ivanpah 3 Solar · 133.4 MW
- Aratina Solar Center 1B Solar · 130 MW
- Ivanpah 1 Solar · 126 MW
- Desert Breeze Solar, LLC Solar · 125 MW
- Parker Dam Hydro · 120 MW
- Daggett 1 Battery storage · 113.5 MW
- Separator (Etiwanda) BESS Battery storage · 112.5 MW
- Resurgence Solar II Solar · 88 MW
- Lockhart Solar PV IV, LLC Solar · 80 MW
- Baldy Mesa 2_Silver Peak Hybrid Solar · 75 MW
- Inland Empire Energy Storage Battery storage · 70 MW
- Agua Mansa Power Plant Natural gas · 60.5 MW
- Grapeland Hybrid Natural gas · 59.8 MW
- Argus Cogen Plant Coal · 55 MW
- Mira Loma Peaker Natural gas · 49.8 MW
- Lockhart ESS, LLC Battery storage · 45 MW
- Century Generating Facility Natural gas · 44.8 MW
- Drews Generating Facility Natural gas · 44.8 MW
- New-Indy Ontario Mill Natural gas · 33 MW
- Mojave Siphon Hydro · 32.7 MW
- CamChino Leasing LLC Natural gas · 30.8 MW
- Etiwanda Hydro · 23.9 MW
- Sunray 2 Solar · 20 MW
- RE Victor Phelan Solar One LLC Solar · 20 MW
- Lone Valley Solar Park II LLC Solar · 20 MW
- Adelanto Solar, LLC Solar · 20 MW
- Alamo Solar Solar · 20 MW
- Longboat Solar, LLC Solar · 20 MW
- Mira Loma Energy Storage Facility Battery storage · 20 MW
- Cascade Solar Solar · 18.5 MW
- MCAGCC Cogen Plant Natural gas · 16.4 MW
- Sunray 3 Solar · 13.8 MW
- SEPV 8 Solar · 12 MW
- Loma Linda University Cogen Natural gas · 10.4 MW
- Lone Valley Solar Park I LLC Solar · 10 MW
- SEPV9 Power Plant Solar · 9 MW
- Bear Valley Power Plant Natural gas · 8.4 MW
- Adelanto Solar II, LLC Solar · 7 MW
- Adelanto Solar Project Solar · 6.8 MW
- San Manuel Central Plant Cogens Natural gas · 5.4 MW
- Victor Dry Farm Ranch A Solar · 5 MW
- Victor Dry Farm Ranch B Solar · 5 MW
- IGS KSBD Solar · 4.3 MW
- Niagara Bottling - Rialto Solar · 4.2 MW
- Chaffey College Rancho Cucamonga Campus Solar · 4 MW
- IOS II-LAX9 Solar · 4 MW
- Foundation Cemex River Plant Wind · 3.2 MW
- Foundation Cemex BMQ Wind · 3 MW
- PVN Milliken, LLC Solar · 3 MW
- RPUWD Scheuer Well Solar Project Solar · 3 MW
- Sheep Creek Community Solar Farm Solar · 3 MW
- San Antonio Regional Hospital Natural gas · 2.7 MW
- Niagara Bottling Ontario PHI Solar · 2.7 MW
- ESCA-LL-COLTON, LLC Solar · 2.6 MW
- IGS SBD1 Solar · 2.6 MW
- Colton Solar One, LLC Solar · 2.5 MW
- IGS SBD2 Solar · 2.5 MW
- Chambers 4 - Rialto LGB8 Solar · 2.2 MW
- SEPV 2 Solar · 2 MW
- Watts 3115 Solar · 2 MW
- Expressway Solar A Solar · 2 MW
- Expressway Solar B Solar · 2 MW
- CA - DGS RFP - RJ Donovan State Prison Solar · 2 MW
- Chambers 4 - San Bernardino SNA7 Solar · 2 MW
- Chambers 4 - Redland LGB4 Solar · 1.9 MW
- BBARWA Solar · 1.9 MW
- Rancho Cucamonga Dist #1 Solar · 1.8 MW
- KP Ontario Vineyard Solar Solar · 1.7 MW
- Oltmans SCE at Jurupa Solar · 1.5 MW
- Industry Solar Power Generation Station Solar · 1.5 MW
- Navajo Solar Power Generation Station 1 Solar · 1.5 MW
- Powhatan Solar Power Generation Station Solar · 1.5 MW
- Otoe Solar Power Generation Station 1 LL Solar · 1.5 MW
- Expressway Solar C2 Solar · 1.5 MW
- Hesperia Solar · 1.5 MW
- Victor Mesa Linda B2 Solar · 1.5 MW
- Victor Mesa Linda C2 Solar · 1.5 MW
- Victor Mesa Linda D2 Solar · 1.5 MW
- Victor Mesa Linda E2 Solar · 1.5 MW
- SCE-Snowline-Duncan Road (North) Solar · 1.5 MW
- Rudy Solar, LLC Solar · 1.5 MW
- Mitchell Solar, LLC Solar · 1.5 MW
- SCE-Snowline-White Road (South) Solar · 1.5 MW
- SCE-Snowline-White Road (North) Solar · 1.5 MW
- SCE-Snowline-White Rd (Central) Solar · 1.5 MW
- Coronus Adelanto West 1 Solar · 1.5 MW
- Coronus Adelanto West 2 Solar · 1.5 MW
- Terra Francesco Solar · 1.5 MW
- SB Water Reclamation Fuel Cell Biomass · 1.4 MW
- 9150 Hermosa Solar GM Solar · 1.3 MW
- Phelan Pinon Hills CSD Solar Solar · 1.2 MW
- Redlands Community Hospital Natural gas · 1.1 MW
- Mountain View Ind Park 1-sline001 Solar · 1.1 MW
- Kohls San Bernardino Solar Facility Solar · 1 MW
- SunEdison Walmart Apple Valley DC Solar · 1 MW
- Foundation IE Wind · 1 MW
- Kaiser Ontario Natural gas · 1 MW
- Nunn Solar · 1 MW
- Oltmans SCE at Champagne Solar · 1 MW
- SCE-Snowline-Duncan Road (South) Solar · 1 MW
- Madelyn Solar, LLC Solar · 1 MW
- Colton Solar Two, LLC Solar · 1 MW
- SunE- E Philadelphia Ontario Solar · 1 MW
- SunE Rochester Solar · 1 MW
- Waterman Turnout Hydroelectric Hydro · 1 MW
- CA Institute for Women Solar · 1 MW
- Rialto - High School Solar · 0.9 MW
- Energy Center Natural gas · 0.9 MW
San Diego County 103 plants
- Otay Mesa Generating Project Natural gas · 710.7 MW
- Carlsbad Energy Center Natural gas · 659 MW
- Palomar Energy Natural gas · 559 MW
- Pio Pico Energy Center Natural gas · 395.4 MW
- Nighthawk Energy Storage, LLC Battery storage · 300 MW
- Gateway Energy Storage System Battery storage · 250 MW
- Peregrine Energy Storage LLC Battery storage · 200 MW
- Tule Wind LLC Wind · 143 MW
- Orange Grove Peaking Facility Natural gas · 118 MW
- Border Hybrid Energy Center Natural gas · 114.6 MW
- Miramar Energy Facility Natural gas · 106 MW
- Ocotillo Wells Solar · 100 MW
- Pome BESS Battery storage · 100 MW
- Larkspur Energy Facility Natural gas · 99.8 MW
- Valley Center 85 Battery storage · 85 MW
- El Cajon Energy Center Natural gas · 60.5 MW
- CalPeak Power Enterprise Peaker Plant Natural gas · 58.9 MW
- Escondido Energy Center Natural gas · 54 MW
- Valley Center 54 Battery storage · 54 MW
- Goal Line LP Natural gas · 51.4 MW
- Kumeyaay Wind Wind · 50 MW
- Chula Vista Energy Center 2 Battery storage · 50 MW
- Ventasso Energy Storage, LLC Battery storage · 50 MW
- North Johnson Energy Center Battery storage · 50 MW
- Cuyamaca Peak Energy Plant Natural gas · 48.7 MW
- Fallbrook Energy Storage Battery storage · 40 MW
- Vista Energy Storage System Battery storage · 40 MW
- Chula Vista Energy Center Natural gas · 37.2 MW
- University of California San Diego Hybri Natural gas · 33 MW
- Top Gun Energy Storage Battery storage · 30 MW
- Solar Borrego I Solar · 26 MW
- Jacumba Solar Farm Solar · 20 MW
- Melrose BESS Battery storage · 20 MW
- CP Kelco San Diego Plant Natural gas · 19.2 MW
- San Diego State University Natural gas · 15.1 MW
- Kearny North Energy Storage Battery storage · 10 MW
- Kearny South Energy Storage Battery storage · 10 MW
- Paradise Energy Storage Battery storage · 10 MW
- Clairemont Energy Storage Battery storage · 10 MW
- Elliott Energy Storage Battery storage · 10 MW
- Boulevard Energy Storage Battery storage · 10 MW
- Pala Gomez Creek BESS Battery storage · 10 MW
- Santee BESS Battery storage · 10 MW
- El Cajon Energy Storage Battery storage · 7.5 MW
- MM San Diego-Miramar Landfill gas · 7.3 MW
- Dark Sky Energy Center Battery storage · 7.3 MW
- Amazon SAN3 Solar Project Solar · 7 MW
- Genentech-Oceanside Hybrid Solar · 6.5 MW
- Desert Green Solar Farm LLC Solar · 6.3 MW
- EnerSmart Chula Vista Sub Station Battery storage · 6 MW
- Red Mountain Hydro · 5.9 MW
- Sycamore Energy LLC Landfill gas · 5.4 MW
- Naval Hospital Medical Center Natural gas · 5.3 MW
- Valley Center 2 Solar · 5 MW
- Ramona 2 Solar · 5 MW
- Childrens Hospital Natural gas · 4.8 MW
- Gas Utilization Facility Biomass · 4.6 MW
- W Plant Natural gas · 4.6 MW
- Grossmont Hospital Natural gas · 4.5 MW
- Ramona Solar Energy Solar · 4.3 MW
- Illumina Way SD Natural gas · 3.5 MW
- Encina Water Pollution Control Biomass · 3.2 MW
- NLP Granger Solar · 3 MW
- Lindberg FIeld Solar Solar · 2.9 MW
- San Diego - EMDF at San Diego Solar · 2.9 MW
- Amazon - SAN5 Solar · 2.9 MW
- Richard J Donovan Correctional Facility Natural gas · 2.6 MW
- Grossmont College Solar · 2.6 MW
- Valley Center 1 Solar · 2.5 MW
- GEN005 Antibody Fuel Cell Natural gas · 2.5 MW
- Grossmont-Cuyamaca-Cuyamaca Col. Solar & Solar · 2.4 MW
- Valley Center Solar · 2.3 MW
- Gilead Oceanside Solar Project Solar · 2.2 MW
- County of San Diego COC Hybrid Solar · 2.1 MW
- Watkins Manufacturing Co. Natural gas · 2 MW
- Ramona 1 Solar · 2 MW
- Vanadium Redox Flow Battery Plant Battery storage · 2 MW
- San Diego International Airport BESS Battery storage · 2 MW
- Lindberg Field Solar 2 Solar · 1.9 MW
- San Diego - NCRC at Vista Solar · 1.8 MW
- Kyocera International Inc.(San Diego) Natural gas · 1.7 MW
- Borrego Springs Energy Storage Battery storage · 1.5 MW
- Bear Valley Hydro · 1.4 MW
- Grossmont HS Solar Project Solar · 1.4 MW
- Vallecitos Water District Solar · 1.4 MW
- Legoland CA Phase I Solar · 1.4 MW
- County of San Diego SBRC Solar · 1.3 MW
- PFMG Solar Grossmont Helix LLC Solar · 1.2 MW
- ISH Solar Hospital SDMC Solar · 1.1 MW
- Life Technologies Carlsbad Natural gas · 1.1 MW
- Kilroy Solar Solar · 1.1 MW
- SeaWorld Aquatica Solar · 1.1 MW
- San Diego Sockers Solar · 1.1 MW
- Univ of California San Diego Solar Solar · 1 MW
- SDCCD - Miramar Solar · 1 MW
- SDCWA - Twin Oaks Solar · 1 MW
- Golden Acorn Casino Wind · 1 MW
- Pala Energy Storage Yard Battery storage · 1 MW
- Canyon Crest Academy Battery storage · 1 MW
- Kearny Mesa Storage LLC Battery storage · 1 MW
- University of San Diego Natural gas · 1 MW
- AT&T - San Diego Trade Street Natural gas · 1 MW
- San Diego Community College Natural gas · 1 MW
San Francisco County 5 plants
- Parnassus Central Utility Plant Natural gas · 13.4 MW
- Sunset Reservoir North Basin Solar · 4.5 MW
- SF Southeast Cogen Plant Biomass · 2.1 MW
- One Market Plaza Natural gas · 1.5 MW
- Transamerica Pyramid Natural gas · 1 MW
San Joaquin County 37 plants
- Kola Energy Center Battery storage · 400 MW
- Tracy Combined Cycle Power Plant Natural gas · 336.1 MW
- Lodi Energy Center Natural gas · 288.9 MW
- North Central Valley Battery storage · 132 MW
- Ripon Generation Station Natural gas · 121 MW
- Stockton Biomass Wood biomass · 54 MW
- Combustion Turbine Project No 2 Natural gas · 50 MW
- AltaGas Ripon Energy Inc. Natural gas · 49.5 MW
- Enchanted Rock Lodi Natural gas · 48 MW
- Cascade Energy Storage, LLC Battery storage · 25 MW
- Camanche Hydro · 10.8 MW
- University of the Pacific Solar · 5.5 MW
- Regional Wastewater Control Facility Biomass and oil · 5 MW
- Ameresco San Joaquin Landfill gas · 4.4 MW
- Ameresco Forward Landfill gas · 4.4 MW
- Foothill Sanitary Landfill - Solar Array Solar · 3.6 MW
- Lathrop 4 - SLCVA204 Solar · 3.4 MW
- Prologis L.P Solar · 3 MW
- CA Manteca 730 Spreckels Ave Solar · 3 MW
- Tracy 18 - SLCVA418 Solar · 3 MW
- Tracy Linne Solar · 2.7 MW
- Tracy 210 Natural gas · 2.6 MW
- Amazon - Stockton - Roof (SCK1) - (CA) Solar · 2.6 MW
- Tesoro RV & Boat Storage Solar · 2.5 MW
- IPC 25 Solar Solar · 2.4 MW
- Sutter Home Winery Westside Solar · 2.3 MW
- Foundation ST Wind · 2 MW
- IPC 16 - SLCVA516 Solar · 1.7 MW
- Bear Creek Solar (Lodi) Solar · 1.5 MW
- Donaghy-Stockton Solar · 1.1 MW
- Stockton 6 - SLEBA202 Solar · 1.1 MW
- Teichert Materials-Teichert Vernalis Wind · 1 MW
- Kettleman Solar Project Solar · 1 MW
- Manteca Land PV Solar · 1 MW
- Medline Ind. Phase 2 Tracy Solar · 1 MW
- Niagara Bottling Stockton Solar · 1 MW
- Da Silva Dairy Solar · 1 MW
San Luis Obispo County 17 plants
- Diablo Canyon Nuclear · 2,323 MW
- Topaz Solar Farm Solar · 585.9 MW
- California Valley Solar Ranch Solar · 249.8 MW
- CA Flats Solar 150, LLC Solar · 150 MW
- CA Flats Solar 130, LLC Solar · 130 MW
- Caballero Battery storage · 99.7 MW
- Stenner Creek Solar Solar · 4.5 MW
- Nacimiento Hydro Project Hydro · 4.4 MW
- Paso Robles - Municipal Airport Solar · 3 MW
- CA-DGS-California Men's Colony Solar · 2.2 MW
- Firestone Walker Brewery - Phase 1 Solar · 1.6 MW
- Cold Canyon 1 Landfill gas · 1.5 MW
- Vintner Solar Solar · 1.5 MW
- Camp San Luis Obispo Solar · 1.2 MW
- Meridian Vineyards Solar · 1.1 MW
- Atascadero State Hospital Solar · 1.1 MW
- Sutter Home Winery TCC Solar · 1.1 MW
San Mateo County 8 plants
- Ameresco Ox Mountain Landfill gas · 11.4 MW
- SRI International Cogen Project Natural gas · 6 MW
- Google Bayhill Solar PV and Microgrid Solar · 3.8 MW
- Silicon Valley Clean Water Biomass · 2.2 MW
- Shelter Creek Condominiums Solar Solar · 1.9 MW
- Gilead Foster City Solar Project Solar · 1.6 MW
- Franklin Templeton San Mateo Natural gas · 1.1 MW
- AT&T - Redwood City Natural gas · 1 MW
Santa Barbara County 12 plants
- Strauss Wind Farm Wind · 95.3 MW
- Goleta Energy Storage, LLC Battery storage · 60 MW
- Ellwood Natural gas · 58 MW
- Cuyama Solar, LLC Solar · 40 MW
- Vandenberg Solar Project Solar · 25.3 MW
- Painter Energy Storage Battery storage · 10 MW
- Vallecito Battery storage · 10 MW
- Santa Barbara ReSource Center Landfill gas and biomass · 5.8 MW
- SEPV Cuyama Hybrid Solar · 4.6 MW
- Broadway 3 - UCSB Lot 38 Solar · 1.8 MW
- J&A-Santa Maria II LLC Landfill gas · 1.4 MW
- Santa Maria LFG Power Plant Landfill gas · 1.1 MW
Santa Clara County 44 plants
- Metcalf Energy Center Natural gas · 635 MW
- Los Esteros Critical Energy Center Natural gas · 306.1 MW
- Donald Von Raesfeld Power Plant Natural gas · 154 MW
- Gilroy Peaking Energy Center Natural gas · 144 MW
- Gilroy Power Plant Natural gas · 130 MW
- Hummingbird Energy Storage LLC Battery storage · 75 MW
- Gianera Natural gas · 64.6 MW
- Agnews Power Plant Natural gas · 32 MW
- Apple Campus 2 PV Solar · 14.4 MW
- SJ/SC WPCP Natural gas · 14 MW
- San Jose Cogeneration Natural gas · 6 MW
- EQX011 Duane Fuel Cell Natural gas · 5.2 MW
- Mission College Blvd. Fuel Cell Natural gas · 5 MW
- Equinix Lundy Ave. Fuel Cell Natural gas · 4.9 MW
- Equinix Caspian Dr. Fuel Cell Natural gas · 4.8 MW
- Equinix Great Oaks Blvd. Fuel Cell Natural gas · 4.5 MW
- Apple Campus 2 Fuel Cell Landfill gas · 4 MW
- EQX015 Great Oaks Fuel Cell Natural gas · 4 MW
- Stanford Campus Solar Solar · 3.7 MW
- West Valley Mission CCD Solar Project Solar · 3.6 MW
- Malech Solar Farm Solar · 3.1 MW
- Micro Santa Clara Natural gas · 3 MW
- EQX010 Great Oaks Fuel Cell Natural gas · 2.4 MW
- Verizon Comms Garage Top Solar Project Solar · 2.3 MW
- Hellyer Solar Farm Solar · 2.2 MW
- AGT000 Stevens Creek Fuel Cell Natural gas · 2.2 MW
- Google Moffett Park Solar Project Solar · 2.2 MW
- Gavilan Community College Solar Project Solar · 1.9 MW
- Guadalupe Solar Farm Solar · 1.7 MW
- CSU San Jose State University Solar · 1.7 MW
- Sunnyvale City of WPCP Biomass · 1.6 MW
- Zero Waste Energy Development Co LLC Biomass · 1.6 MW
- FLEX Gibraltar Natural gas · 1.5 MW
- SCU000 El Camino Real Fuel Cell Natural gas · 1.5 MW
- AT&T Holger Natural gas · 1.3 MW
- Solar Star Palo Alto I, LLC Solar · 1.3 MW
- CST001 McCarthy Fuel Cell Natural gas · 1.2 MW
- Kellogg's - San Jose Natural gas · 1.1 MW
- Maxim Natural gas · 1.1 MW
- Equinix San Jose Natural gas · 1.1 MW
- Intel Santa Clara Natural gas · 1.1 MW
- JSR000 N Mathilda Fuel Cell Natural gas · 1.1 MW
- Xilinx San Jose Natural gas · 1 MW
- SCC - San Jose Natural gas · 1 MW
Santa Cruz County 4 plants
- University of California Santa Cruz Natural gas · 7.4 MW
- Ameresco Santa Cruz Energy Landfill gas · 3 MW
- Cabrillo College Solar · 2.4 MW
- Santa Cruz Energy Landfill gas · 1.6 MW
Shasta County 37 plants
- Shasta Hydro · 714 MW
- Redding Power Natural gas · 183.1 MW
- Spring Creek Hydro · 180 MW
- James B Black Hydro · 168.6 MW
- Judge F Carr Hydro · 154.4 MW
- Pit 5 Hydro · 141.6 MW
- Keswick Hydro · 117 MW
- Pit 7 Hydro · 109.8 MW
- Pit 4 Hydro · 103.4 MW
- Hatchet Ridge Wind Project Wind · 101.2 MW
- Pit 3 Hydro · 80.1 MW
- Pit 6 Hydro · 79.2 MW
- Pit 1 Hydro · 69.2 MW
- Wheelabrator Shasta Wood biomass · 54.9 MW
- Burney Forest Products Wood biomass · 31 MW
- SPI Anderson 2 Wood biomass · 30.2 MW
- Sierra Pacific Burney Facility Wood biomass · 20 MW
- Coleman PH Hydro · 12.1 MW
- Hat Creek 1 Hydro · 10 MW
- Hat Creek 2 Hydro · 10 MW
- Volta 1 Hydro · 8.5 MW
- Hatchet Creek Project Hydro · 6.8 MW
- Cove Hydroelectric Hydro · 5 MW
- Olsen Hydro · 5 MW
- Slate Creek Hydro · 4.2 MW
- Hat Creek Bioenergy Wood biomass · 3.6 MW
- Whiskeytown Hydro · 3.5 MW
- Bear Creek (CA) Hydro · 3.2 MW
- Burney Creek Hydro · 3 MW
- Shasta Solar Farm Solar · 3 MW
- Montgomery Creek Hydro Hydro · 2.6 MW
- Roaring Creek Water Power Hydro · 2 MW
- Shasta College PH2 Solar Project Solar · 2 MW
- Bidwell Ditch Project Hydro · 1.8 MW
- Nelson Creek Hydro · 1.2 MW
- Lost Creek I Hydro · 1.1 MW
- Volta 2 Hydro · 1 MW
Siskiyou County 3 plants
- Roseburg Forest Products Biomass Wood biomass · 13.4 MW
- Box Canyon Dam Hydro · 5 MW
- Fall Creek Hydro · 2.1 MW
Solano County 34 plants
- Solano Wind Wind · 300.5 MW
- High Winds LLC Wind · 162 MW
- Shiloh I Wind Project Wind · 150 MW
- Shiloh Wind Project 2 LLC Wind · 150 MW
- Shiloh III Wind Project LLC Wind · 102.5 MW
- Shiloh IV Wind Project LLC Wind · 102.5 MW
- Montezuma Wind II Wind · 78.2 MW
- CalPeak Power Vaca Dixon Peaker Plant Natural gas · 60.5 MW
- Valero Refinery Cogeneration Unit 1 Natural gas · 49.9 MW
- Creed Energy Center Natural gas · 48 MW
- Goose Haven Energy Center Natural gas · 48 MW
- Wolfskill Energy Center Natural gas · 48 MW
- Lambie Energy Center Natural gas · 47 MW
- FPL Energy Montezuma Winds LLC Wind · 36.8 MW
- EDF Renewable Windfarm V Inc Wind · 15.5 MW
- Monticello Dam Hydro · 11.5 MW
- Potrero Hills Energy Producers Landfill gas · 8 MW
- SFDK Solar Solar · 6.3 MW
- Genentech Vacaville Meter #1 Solar · 6.1 MW
- Lake Herman Solar · 5 MW
- Solano County Cogen Plant Natural gas · 2.8 MW
- Rio Vista Solar Solar · 2.7 MW
- Anheuser Busch - Fairfield Natural gas · 2.6 MW
- Vaca Dixon Solar Station Solar · 2 MW
- ATT North Watney Natural gas · 2 MW
- G2 Energy Hay Rd Landfill gas · 1.6 MW
- Anheuser-Busch #2 Wind · 1.6 MW
- Foundation AB Wind · 1.5 MW
- Vacaville Hospital Solar · 1.5 MW
- CDCR (CA) - Solano State Prison Solar · 1.1 MW
- Mariani Packing Vacaville Solar Solar · 1 MW
- SunEdison Anheuser Busch Fairfield Solar · 1 MW
- Foundation Superior Farms Wind · 1 MW
- North Bay Solar 1 Solar · 1 MW
Sonoma County 22 plants
- Geysers Unit 5-20 Geothermal · 1,236 MW
- Geothermal 1 Geothermal · 110 MW
- Geothermal 2 Geothermal · 55 MW
- Aidlin Geothermal Power Plant Geothermal · 25 MW
- Keysight - Santa Rosa Natural gas · 4.5 MW
- Laguna Water Reclamation Facility Biomass · 4.4 MW
- Ellis Creek Solar Solar · 4 MW
- Sonoma Central Landfill Phase I Landfill gas · 3.2 MW
- Sonoma Central Landfill Phase II Landfill gas · 3.2 MW
- Dissigno Healdsburg FPV, LLC Solar · 3 MW
- Warm Springs Hydro Project Hydro · 2.7 MW
- Bodega Avenue Solar LLC Solar · 2 MW
- Sonoma Central Landfill Phase III Landfill gas · 1.6 MW
- Cloverdale Solar I Solar · 1.5 MW
- Windsor Floating Solar Solar · 1.5 MW
- Beringer Solar · 1.4 MW
- Sutter Santa Rosa Solar Solar · 1.3 MW
- ASTI Solar · 1.2 MW
- Santa Rosa Junior College Petaluma Solar Solar · 1.2 MW
- Cloverdale Solar Center Solar · 1 MW
- Stage Gulch Solar Solar · 1 MW
- Lavio Solar Solar · 1 MW
Stanislaus County 19 plants
- Proxima Solar · 352 MW
- Walnut Energy Center Natural gas · 300.6 MW
- Almond Power Plant Natural gas · 223.5 MW
- Woodland Natural gas · 199 MW
- McClure Oil · 142.4 MW
- Walnut Natural gas · 49.8 MW
- ERock MID Claribel Generation Station Natural gas · 48 MW
- Enchanted Rock Turlock Irrigation Distri Natural gas · 46.8 MW
- Central 40 Solar · 40 MW
- Paulsell Solar · 35 MW
- Axium Modesto Solar Solar · 25 MW
- Frontier Solar LLC Solar · 20 MW
- Frankenheimer Power Plant Hydro · 5.3 MW
- La Grange Hydro · 4.5 MW
- Turlock Lake Hydro · 3.3 MW
- Woodward Power Plant Hydro · 2.8 MW
- Amazon - Patterson PV Solar · 2.5 MW
- Robert O Schulz Solar Farm Solar · 1.6 MW
- Hickman Hydro · 1 MW
Sutter County 7 plants
- Sutter Energy Center Natural gas · 636 MW
- Greenleaf 1 Natural gas · 69.8 MW
- Yuba City Cogen Partners Natural gas · 49.9 MW
- Greenleaf 2 Power Plant Natural gas · 49.5 MW
- Yuba City Energy Center Natural gas · 47.3 MW
- Feather River Energy Center Natural gas · 47 MW
- Tierra Buena Energy Storage Battery storage · 5 MW
Tehama County 6 plants
- Red Bluff Natural gas · 46.4 MW
- Sierra Pacific Industries (2042-RD) Solar · 8.4 MW
- South Hydro · 6.7 MW
- Black Butte Hydro · 6.1 MW
- Ponderosa Bailey Creek Hydro · 1.1 MW
- Foundation Wal-Mart Red Bluff Wind · 1 MW
Trinity County 4 plants
- Trinity Hydro · 140 MW
- Big Creek Water Works Hydro · 5 MW
- Gosselin Hydro Plant Hydro · 2 MW
- Three Forks Water Power Project Hydro · 1.3 MW
Tulare County 60 plants
- Rexford Solar Farm Solar · 540 MW
- Deer Creek Hybrid Solar · 102.8 MW
- Bottleneck Energy Storage Battery storage · 80 MW
- Shirk Energy Storage Battery storage · 80 MW
- Angela Solar Project Solar · 80 MW
- Delano Energy Center Natural gas · 60.5 MW
- Luciana Solar · 55.8 MW
- Alpaugh 50 Solar · 50 MW
- Atwell Island Solar · 20.2 MW
- Terminus Hydroelectric Project Hydro · 20.1 MW
- Alpaugh North Solar · 20 MW
- White River Solar Solar · 20 MW
- Atwell Island West Solar Solar · 20 MW
- Nicolis Solar PV Plant Solar · 20 MW
- CED Ducor 1 Solar · 20 MW
- CED Ducor 2 Solar · 20 MW
- CED Ducor 4 Solar · 20 MW
- White River Solar 2 Solar · 19.8 MW
- CED Ducor 3 Solar · 15 MW
- Tropico Solar PV Plant Solar · 14 MW
- Alpaugh BESS Battery storage · 10 MW
- City of Tulare Water Facility Solar · 9.2 MW
- Tipton 1 - (CA) Solar · 5.2 MW
- Visalia - (CA) Solar · 5.2 MW
- Solar Photovoltaic Project #42 Solar · 5 MW
- Farmersville Solar · 4.5 MW
- Lindsay Solar Solar · 4 MW
- Double J Dairy Array Solar · 4 MW
- Kingsburg Solar Solar · 3.7 MW
- Visalia Solar Solar · 3.6 MW
- Kaweah Delta District Hospital Natural gas · 3.5 MW
- Exeter Solar Solar · 3.5 MW
- Ivanhoe Solar Solar · 3.5 MW
- Porterville Solar Solar · 3.5 MW
- Amazon Visalia (FAT2) Solar · 3.5 MW
- Tulare 1 and 2 Solar · 3 MW
- Porterville 6 and 7 Solar · 3 MW
- Visalia CSG LLC Solar · 3 MW
- Tulare CSG LLC Solar · 3 MW
- Tulare BioMAT Fuel Cell Biomass · 2.8 MW
- Central CA Fuel Cell 1, LLC Natural gas · 2.8 MW
- Tipton 2 - (CA) Solar · 2.8 MW
- 1875 West Street Solar Solar · 2 MW
- Kaweah 2 Hydro · 1.8 MW
- Bob Wiley Detention Center Solar · 1.8 MW
- Agriculture Capital - Legacy Packing Solar · 1.6 MW
- Civic Center East Solar · 1.5 MW
- North Juvenile Detention Center Solar Solar · 1.4 MW
- Pivot Energy PPA 22 Solar · 1.3 MW
- Case Vander Eyk, Jr Dairy Solar Solar · 1.2 MW
- TWC Solar · 1.2 MW
- South County Detention Center Solar Solar · 1.1 MW
- Government Plaza Solar Solar · 1.1 MW
- Dinuba Wastewater Treatment Plant Solar · 1 MW
- Castle Rock Vineyards Solar · 1 MW
- RE-VFO LLC Solar · 1 MW
- FTF-PackingShed Solar · 1 MW
- Elkhorn Dairy Solar · 1 MW
- Tulare Akers Professional Center Solar · 1 MW
- Blue Moon Farms Solar · 1 MW
Tuolumne County 20 plants
- New Melones Hydro · 300 MW
- Dion R Holm Hydro · 180.2 MW
- Don Pedro Hydro · 170.8 MW
- R C Kirkwood Hydro · 132.8 MW
- Moccasin Hydro · 103.6 MW
- Stanislaus Hydro · 81.9 MW
- Donnells Hydro · 72 MW
- Tulloch Hydro · 29.9 MW
- Pacific-Ultrapower Chinese Station Wood biomass · 25 MW
- Sand Bar Power Plant Hydro · 16.2 MW
- Beardsley Hydro · 10 MW
- Sierra Energy Storage, LLC Battery storage · 10 MW
- Sierra Pacific Sonora Wood biomass · 7.5 MW
- Spring Gap Hydro · 6 MW
- Spicer Meadow Project Hydro · 5.9 MW
- Upper Dawson Hydro · 4.4 MW
- Sierra Pacific Chinese Camp Solar · 3.6 MW
- Moccasin Low Head Hydro Project Hydro · 2.9 MW
- Phoenix Hydro · 1.6 MW
- Sonora 1 Solar · 1.5 MW
Ventura County 24 plants
- Ormond Beach Natural gas · 1,612 MW
- Saticoy Battery storage · 100 MW
- Oxnard Natural gas · 68.7 MW
- McGrath Peaker Natural gas · 49.8 MW
- E F Oxnard Energy Facility Natural gas · 48.5 MW
- CSUCI Site Authority Natural gas · 31.1 MW
- Santa Paula Energy Storage LLC Battery storage · 30 MW
- Oxnard Paper Mill Natural gas · 29 MW
- Black Walnut Energy Storage LLC Battery storage · 15 MW
- Glass House Camarillo Cultivation Natural gas · 13.2 MW
- IGS OXR1 Solar · 4.8 MW
- California State Univ at Channel Islands Solar · 3.7 MW
- CA OXNARD 2600 Sakioka Dr Solar · 3.2 MW
- Ventura Solar Solar · 2.9 MW
- CA - Ventura Co CCD - Moorpark College Solar · 2.6 MW
- CA-Ventura County CCD-Ventura College Solar · 2.5 MW
- Acorn I Energy Storage LLC Battery storage · 2 MW
- RP Minnesota Solar Solar · 1.8 MW
- Oxnard Wastewater Treatment Plant Biomass · 1.5 MW
- CA-Ventura Co CCD-Oxnard College Canopy Solar · 1.5 MW
- Santa Felicia Dam Hydro · 1.3 MW
- Bayer Oxnard - Meter# 4719 Solar · 1.3 MW
- Springville Hydroelectric Hydro · 1 MW
- SunEdison Procter & Gamble Oxnard Solar · 1 MW
Yolo County 13 plants
- Woodland Biomass Power Ltd Wood biomass · 28 MW
- UC Davis South Campus Solar · 13 MW
- MM Yolo Power Landfill gas · 3.6 MW
- Putah Creek Solar Farm North Solar · 3 MW
- Target Woodland Solar Project Solar · 2.3 MW
- Grassland 3&4 Solar Project Solar · 2 MW
- Grassland 1&2 Solar Project Solar · 2 MW
- Putah Creek Solar Farm Solar · 2 MW
- West Village Solar - Array 2 Community S Solar · 1.3 MW
- West Village Solar - Array 1Community So Solar · 1.2 MW
- Walgreens Woodland Distribution Center Solar · 1 MW
- Yolo County Solar Project Solar · 1 MW
- Foundation Cemex Madison Wind · 1 MW
Yuba County 4 plants
- Colgate Hydro · 315 MW
- Narrows 2 Hydro · 46.7 MW
- G2 Energy Ostrom Road LLC Landfill gas · 3.5 MW
- Deadwood Creek Hydro · 2 MW
Questions about power plants in California
How many power plants are in California?
EIA-860M for August 2026 lists 1,838 operating power projects in California, with 107,415 MW of nameplate capacity including batteries.
What is the largest power plant in California?
Diablo Canyon in San Luis Obispo County, with 2,323 MW of nameplate capacity. The next largest is Dynegy Moss Landing Power Plant Hybrid, with 1,848 MW.
How much of California's capacity is solar?
25,487 MW, about 24% of nameplate capacity. 971 projects have solar as their primary fuel.
Source: EIA-860M August 2026, published 2026-09-24. Page updated 2026-10-04. Data sources