Battery storageOperatingCAISO

DESI-2 Battery Storage Facility

Battery storage project in Orange County, California. 1.4 MW of nameplate capacity across 1 generator, operated by Southern California Edison Co.

Also known as EIA plant 62460

Analyst: free account, 1 question a day.

DATSPlant No 1 Orange CountyOCSDJohanna Energy Center, LLCHEBT Irvine 1DESI-2 Battery Storag…2 km
Open in the map
6 plants within 6.3 km, from EIA coordinates.

Key facts

Capacity
1.4 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
October 2019First generator online
Operator
Southern California Edison CoEIA operator ID 17609
Grid
CAISOBalancing authority CISO
Price nodes
1 CAISO nodeResource nodes with prices
Location
Orange County, CA33.7357, −117.9153
EIA plant ID
62460EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power DESI-2 Battery Storage Facility produces

Free · EIA-923

Net generation, 2025

0 MWh

0 MWh, final

Battery discharge, 2025

0 MWh

Charge 0 MWh

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2024 to 2025

0.0–0.0

MWh a year. Low 2024, high 2024

Annual net generation, MWh
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
2011Not reportedNot reported0 of 12
2012Not reportedNot reported0 of 12
2013Not reportedNot reported0 of 12
2014Not reportedNot reported0 of 12
2015Not reportedNot reported0 of 12
2016Not reportedNot reported0 of 12
2017Not reportedNot reported0 of 12
2018Not reportedNot reported0 of 12
2019Not reportedNot reported0 of 12
2020Not reportedNot reported0 of 12
2021Not reportedNot reported0 of 12
2022Not reportedNot reported0 of 12
2023Not reportedNot reported0 of 12
20240Not reported12 of 12
20250Not reported12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Battery plants can report negative net generation, when charging uses more energy than they discharge.

Power prices and basis

Free account · CAISO

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
DESI2Batteries1.4October 2019

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Southern California Edison Co as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Analyst and MCP

300 analyst questions a month, plus MCP

Query DESI-2 Battery Storage Facility and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near DESI-2 Battery Storage Facility

More plants operated by Southern California Edison Co

Questions about DESI-2 Battery Storage Facility

How much power does DESI-2 Battery Storage Facility produce?

DESI-2 Battery Storage Facility reported 0 MWh (0 MWh) of net generation in 2025.

Where is DESI-2 Battery Storage Facility?

DESI-2 Battery Storage Facility is in Orange County, California, at 33.7357, −117.9153. It is in the California Independent System Operator balancing area (CISO).

Who operates DESI-2 Battery Storage Facility?

EIA-860M for August 2026 lists Southern California Edison Co as the operator (EIA operator ID 17609). The operator is not always the owner.

When did DESI-2 Battery Storage Facility start operating?

Its first generator began operating in October 2019, according to EIA-860M.

Does InfraMap have power prices for DESI-2 Battery Storage Facility?

Yes. InfraMap has CAISO day-ahead and real-time prices at 1 price node linked to DESI-2 Battery Storage Facility, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • CAISO day-ahead and real-time prices; node and hub assignments as of 2026-10-05

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page