HEBT Irvine 1
Battery storage project in Orange County, California. 5.5 MW of nameplate capacity across 2 generators, operated by Electrodes.
Also known as EIA plant 61722
Analyst: free account, 1 question a day.
Key facts
- Capacity
- 5.5 MWNameplate
- Generators
- 2 operatingEIA-860M, August 2026
- Operating since
- May 2018First generator online
- Operator
- ElectrodesEIA operator ID 61344
- Grid
- CAISOBalancing authority CISO
- Price nodes
- None linkedNo verified ISO node
- Location
- Orange County, CA33.7135, −117.8521
- EIA plant ID
- 61722EIA plant page
Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.
How much power HEBT Irvine 1 produces
Free · EIA-923Net generation, 2025
−919 MWh
−919 MWh, final
Battery discharge, 2025
4.55 GWh
Charge 5.48 GWh
January to July 2026
Not reported
Provisional. 0 of 7 months reported
Range, 2019 to 2025
−2.7–−0.1
GWh a year. Low 2020, high 2019
| Year | Net generation, MWh | Capacity factor | Months reported |
|---|---|---|---|
| 2000 | Not reported | Not reported | 0 of 12 |
| 2001 | Not reported | Not reported | 0 of 12 |
| 2002 | Not reported | Not reported | 0 of 12 |
| 2003 | Not reported | Not reported | 0 of 12 |
| 2004 | Not reported | Not reported | 0 of 12 |
| 2005 | Not reported | Not reported | 0 of 12 |
| 2006 | Not reported | Not reported | 0 of 12 |
| 2007 | Not reported | Not reported | 0 of 12 |
| 2008 | Not reported | Not reported | 0 of 12 |
| 2009 | Not reported | Not reported | 0 of 12 |
| 2010 | Not reported | Not reported | 0 of 12 |
| 2011 | Not reported | Not reported | 0 of 12 |
| 2012 | Not reported | Not reported | 0 of 12 |
| 2013 | Not reported | Not reported | 0 of 12 |
| 2014 | Not reported | Not reported | 0 of 12 |
| 2015 | Not reported | Not reported | 0 of 12 |
| 2016 | Not reported | Not reported | 0 of 12 |
| 2017 | Not reported | Not reported | 0 of 12 |
| 2018 | 0 | Not reported | 8 of 12 |
| 2019 | −106 | Not reported | 12 of 12 |
| 2020 | −2,725 | Not reported | 12 of 12 |
| 2021 | −535 | Not reported | 12 of 12 |
| 2022 | −532 | Not reported | 12 of 12 |
| 2023 | −316 | Not reported | 12 of 12 |
| 2024 | −207 | Not reported | 12 of 12 |
| 2025 | −919 | Not reported | 12 of 12 |
| 2026 (provisional, partial year) | Not reported | Not reported | 0 of 7 |
* 2026 covers January to July and is provisional. Battery plants can report negative net generation, when charging uses more energy than they discharge.
Power prices and basis
Free accountNo verified ISO price node is linked to this plant, or its price history could not load.
Emissions
Free · EPA CAMPDNo EPA emissions units are linked to this plant.
Water use
Free · EIA-923 cooling, USGSNo EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.
Generators
Free · EIA-860M| Generator | Technology | Nameplate MW | Online since |
|---|---|---|---|
| IRV01 | Batteries | 1.0 | May 2018 |
| IRV1W | Batteries | 4.5 | May 2018 |
Ownership and offtake
ProOwnership and offtake are part of Pro
Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Electrodes as the operator, which is not always the owner.
Modeled data
ProPro adds modeled values for this plant. Everything above stays free.
300 analyst questions a month, plus MCP
Query HEBT Irvine 1 and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.
Power plants near HEBT Irvine 1
More plants operated by Electrodes
Questions about HEBT Irvine 1
How much power does HEBT Irvine 1 produce?
HEBT Irvine 1 reported −919 MWh (−919 MWh) of net generation in 2025.
Where is HEBT Irvine 1?
HEBT Irvine 1 is in Orange County, California, at 33.7135, −117.8521. It is in the California Independent System Operator balancing area (CISO).
Who operates HEBT Irvine 1?
EIA-860M for August 2026 lists Electrodes as the operator (EIA operator ID 61344). The operator is not always the owner.
When did HEBT Irvine 1 start operating?
Its first generator began operating in May 2018, according to EIA-860M.
Sources
- EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
- EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page