Battery storageOperatingCAISO

Crimson

Battery storage project in Riverside County, California. 350 MW of nameplate capacity across 2 generators, operated by RE Crimson LLC.

Also known as EIA plant 65140

Analyst: free account, 1 question a day.

Desert QuartziteSolar Blythe LLCCrimson5 km
Open in the map
6 plants within 9.6 km, from EIA coordinates.

Key facts

Capacity
350 MWNameplate
Generators
2 operatingEIA-860M, August 2026
Operating since
October 2022First generator online
Operator
RE Crimson LLCEIA operator ID 64513
Grid
CAISOBalancing authority CISO
Price nodes
2 CAISO nodesResource nodes with prices
Location
Riverside County, CA33.5735, −114.8145
EIA plant ID
65140EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Crimson produces

Free · EIA-923

Net generation, 2025

−66.0 GWh

−66,012 MWh, final

Battery discharge, 2025

498 GWh

Charge 564 GWh

January to July 2026

−36.7 GWh

Provisional

Range, 2023 to 2025

−66.0–−55.4

GWh a year. Low 2025, high 2024

Annual net generation, GWh
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
2011Not reportedNot reported0 of 12
2012Not reportedNot reported0 of 12
2013Not reportedNot reported0 of 12
2014Not reportedNot reported0 of 12
2015Not reportedNot reported0 of 12
2016Not reportedNot reported0 of 12
2017Not reportedNot reported0 of 12
2018Not reportedNot reported0 of 12
2019Not reportedNot reported0 of 12
2020Not reportedNot reported0 of 12
2021Not reportedNot reported0 of 12
2022−15,287Not reported3 of 12
2023−60,188Not reported12 of 12
2024−55,373Not reported12 of 12
2025−66,012Not reported12 of 12
2026 (provisional, partial year)−36,736Not reported7 of 7

* 2026 covers January to July and is provisional. Battery plants can report negative net generation, when charging uses more energy than they discharge.

Power prices and basis

Free account · CAISO

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
SWSH1Batteries200.0October 2022
SWSH2Batteries150.0October 2022

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists RE Crimson LLC as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Crimson and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Crimson

Questions about Crimson

How much power does Crimson produce?

Crimson reported −66,012 MWh (−66.0 GWh) of net generation in 2025. From January to July 2026 it reported −36.7 GWh, which is provisional.

Where is Crimson?

Crimson is in Riverside County, California, at 33.5735, −114.8145. It is in the California Independent System Operator balancing area (CISO).

Who operates Crimson?

EIA-860M for August 2026 lists RE Crimson LLC as the operator (EIA operator ID 64513). The operator is not always the owner.

When did Crimson start operating?

Its first generator began operating in October 2022, according to EIA-860M.

Does InfraMap have power prices for Crimson?

Yes. InfraMap has CAISO day-ahead and real-time prices at 2 price nodes linked to Crimson, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • CAISO day-ahead and real-time prices; node and hub assignments as of 2026-10-05

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page