SolarOperatingCAISO

Giffen Solar Park

Solar power plant in Fresno County, California. 20 MW of nameplate capacity across 1 generator, operated by Giffen Solar Park, LLC.

Also known as EIA plant 59522

Analyst: free account, 1 question a day.

GiffenAspiration GGreat Valley Solar Portfolio Holdings, LScarlet Solar (CA)RE Adams East, LLCGiffen Solar Park5 km
Open in the map
6 plants within 8.4 km, from EIA coordinates.

Key facts

Capacity
20 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
June 2017First generator online
Operator
Giffen Solar Park, LLCEIA operator ID 59257
Grid
CAISOBalancing authority CISO
Price nodes
1 CAISO nodeResource nodes with prices
Location
Fresno County, CA36.5447, −120.3161
EIA plant ID
59522EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Giffen Solar Park produces

Free · EIA-923

Net generation, 2025

19.6 GWh

19,635 MWh, final

Capacity factor, 2025

11.2%

2024: 11.0%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2018 to 2025

19.3–37.0

GWh a year. Low 2024, high 2018

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
2011Not reportedNot reported0 of 12
2012Not reportedNot reported0 of 12
2013Not reportedNot reported0 of 12
2014Not reportedNot reported0 of 12
2015Not reportedNot reported0 of 12
2016Not reportedNot reported0 of 12
201729,133Not reported7 of 12
201836,96021.1%12 of 12
201931,78718.1%12 of 12
202030,10217.1%12 of 12
202130,75917.6%12 of 12
202228,12916.1%12 of 12
202321,92512.5%12 of 12
202419,32611.0%12 of 12
202519,63511.2%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account · CAISO

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
FRGSPSolar Photovoltaic20.0June 2017

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Giffen Solar Park, LLC as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Modeled curtailment

A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.

Modeled

Expected vs reported generation

Monthly modeled expected output and physical potential next to EIA-923 reported output.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Giffen Solar Park and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Giffen Solar Park

Questions about Giffen Solar Park

How much power does Giffen Solar Park produce?

Giffen Solar Park reported 19,635 MWh (19.6 GWh) of net generation in 2025, a 11.2% capacity factor on 20 MW of nameplate capacity.

Where is Giffen Solar Park?

Giffen Solar Park is in Fresno County, California, at 36.5447, −120.3161. It is in the California Independent System Operator balancing area (CISO).

Who operates Giffen Solar Park?

EIA-860M for August 2026 lists Giffen Solar Park, LLC as the operator (EIA operator ID 59257). The operator is not always the owner.

When did Giffen Solar Park start operating?

Its first generator began operating in June 2017, according to EIA-860M.

Does InfraMap have power prices for Giffen Solar Park?

Yes. InfraMap has CAISO day-ahead and real-time prices at 1 price node linked to Giffen Solar Park, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • CAISO day-ahead and real-time prices; node and hub assignments as of 2026-10-05

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page