SolarOperatingCAISO

Vacaville Hospital

Solar power plant in Solano County, California. 1.5 MW of nameplate capacity across 1 generator, operated by KP Vacaville Solar, LLC.

Also known as EIA plant 63928

Analyst: free account, 1 question a day.

Genentech Vacaville Meter #1CalPeak Power Vaca Di…Mariani Packing Vacav…Vaca Dixon Solar StationCDCR (CA) - Solano State PrisonVacaville Hospital5 km
Open in the map
6 plants within 10 km, from EIA coordinates.

Key facts

Capacity
1.5 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
December 2019First generator online
Operator
KP Vacaville Solar, LLCEIA operator ID 64745
Grid
CAISOBalancing authority CISO
Price nodes
None linkedNo verified ISO node
Location
Solano County, CA38.3887, −121.9386
EIA plant ID
63928EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Vacaville Hospital produces

Free · EIA-923

Net generation, 2025

2.26 GWh

2,256 MWh, final

Capacity factor, 2025

17.2%

2024: 21.9%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2020 to 2025

2.3–3.2

GWh a year. Low 2025, high 2022

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
2011Not reportedNot reported0 of 12
2012Not reportedNot reported0 of 12
2013Not reportedNot reported0 of 12
2014Not reportedNot reported0 of 12
2015Not reportedNot reported0 of 12
2016Not reportedNot reported0 of 12
2017Not reportedNot reported0 of 12
2018Not reportedNot reported0 of 12
2019124Not reported1 of 12
20202,57719.6%12 of 12
20213,21324.5%12 of 12
20223,22224.5%12 of 12
20233,01923.0%12 of 12
20242,88521.9%12 of 12
20252,25617.2%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
6701Solar Photovoltaic1.5December 2019

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists KP Vacaville Solar, LLC as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Modeled curtailment

A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.

Modeled

Expected vs reported generation

Monthly modeled expected output and physical potential next to EIA-923 reported output.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Vacaville Hospital and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Vacaville Hospital

Questions about Vacaville Hospital

How much power does Vacaville Hospital produce?

Vacaville Hospital reported 2,256 MWh (2.26 GWh) of net generation in 2025, a 17.2% capacity factor on 1.5 MW of nameplate capacity.

Where is Vacaville Hospital?

Vacaville Hospital is in Solano County, California, at 38.3887, −121.9386. It is in the California Independent System Operator balancing area (CISO).

Who operates Vacaville Hospital?

EIA-860M for August 2026 lists KP Vacaville Solar, LLC as the operator (EIA operator ID 64745). The operator is not always the owner.

When did Vacaville Hospital start operating?

Its first generator began operating in December 2019, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page