WindOperatingCAISO

Brookfield Tehachapi 1

Wind power plant in Kern County, California. 102 MW of nameplate capacity across 1 generator, operated by Coram California Development, L.P..

Also known as Brookfield Tehachapi 1 (CCDLP) · Brookfield Tehachapi 2 · EIA plant 57962

Analyst: free account, 1 question a day.

Alta Wind VIIIPinyon Pine IISEPV Mojave WestBrookfield Tehachapi 12 km
Open in the map
6 plants within 4.4 km, from EIA coordinates.

Key facts

Capacity
102 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
March 2012First generator online
Operator
Coram California Development, L.P.EIA operator ID 60081
Grid
CAISOBalancing authority CISO
Price nodes
1 CAISO nodeResource nodes with prices
Location
Kern County, CA35.0083, −118.2414
EIA plant ID
57962EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Brookfield Tehachapi 1 produces

Free · EIA-923

Net generation, 2025

164 GWh

164,452 MWh, final

Capacity factor, 2025

18.4%

2024: 30.9%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2015 to 2025

164.5–286.4

GWh a year. Low 2025, high 2016

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
2011Not reportedNot reported0 of 12
2012184,39127.4%9 of 12
2013277,66631.1%12 of 12
2014280,83431.4%12 of 12
2015237,35026.6%12 of 12
2016286,42832.0%12 of 12
2017254,83128.5%12 of 12
2018275,14930.8%12 of 12
2019246,95727.6%12 of 12
2020250,63728.0%12 of 12
2021274,37230.7%12 of 12
2022261,13929.2%12 of 12
2023220,35824.7%12 of 12
2024276,86730.9%12 of 12
2025164,45218.4%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account · CAISO

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
BT1Onshore Wind Turbine102.0March 2012

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Coram California Development, L.P. as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Modeled curtailment

A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.

Modeled

Expected vs reported generation

Monthly modeled expected output and physical potential next to EIA-923 reported output.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Brookfield Tehachapi 1 and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Brookfield Tehachapi 1

Questions about Brookfield Tehachapi 1

How much power does Brookfield Tehachapi 1 produce?

Brookfield Tehachapi 1 reported 164,452 MWh (164 GWh) of net generation in 2025, a 18.4% capacity factor on 102 MW of nameplate capacity.

Where is Brookfield Tehachapi 1?

Brookfield Tehachapi 1 is in Kern County, California, at 35.0083, −118.2414. It is in the California Independent System Operator balancing area (CISO).

Who operates Brookfield Tehachapi 1?

EIA-860M for August 2026 lists Coram California Development, L.P. as the operator (EIA operator ID 60081). The operator is not always the owner.

When did Brookfield Tehachapi 1 start operating?

Its first generator began operating in March 2012, according to EIA-860M.

Does InfraMap have power prices for Brookfield Tehachapi 1?

Yes. InfraMap has CAISO day-ahead and real-time prices at 1 price node linked to Brookfield Tehachapi 1, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • CAISO day-ahead and real-time prices; node and hub assignments as of 2026-10-05
  • Project names from the USGS U.S. Wind Turbine Database

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page