Key facts

Capacity
3.2 MWNameplate
Generators
4 operatingEIA-860M, August 2026
Operating since
November 2008First generator online
Operator
Encina Joint Powers AuthorityEIA operator ID 5901
Grid
CAISOBalancing authority CISO
Price nodes
None linkedNo verified ISO node
Location
San Diego County, CA33.1165, −117.3215
EIA plant ID
10026EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Encina Water Pollution Control produces

Free · EIA-923

Net generation, 2025

14.3 GWh

14,281 MWh, final

Capacity factor, 2025

50.9%

2024: 50.4%

January to July 2026

8.23 GWh

Provisional

Range, 2015 to 2025

12.9–15.0

GWh a year. Low 2016, high 2018

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
20014,857Not reported12 of 12
20026,960Not reported12 of 12
20038,024Not reported12 of 12
20047,524Not reported12 of 12
20056,562Not reported12 of 12
20065,259Not reported12 of 12
20075,999Not reported12 of 12
20082,325Not reported12 of 12
200911,188Not reported12 of 12
201011,79642.1%12 of 12
201112,20043.5%12 of 12
2012−3,466-12.3%12 of 12
201313,16447.0%12 of 12
201413,16747.0%12 of 12
201513,49248.1%12 of 12
201612,88545.8%12 of 12
201713,83349.3%12 of 12
201814,98853.5%12 of 12
201914,52251.8%12 of 12
202014,59551.9%12 of 12
202114,49951.7%12 of 12
202214,37851.3%12 of 12
202314,35651.2%12 of 12
202414,17150.4%12 of 12
202514,28150.9%12 of 12
2026 (provisional, partial year)8,23450.6%7 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
EG10Other Waste Biomass0.8November 2008
EG20Other Waste Biomass0.8November 2008
EG30Other Waste Biomass0.8January 2009
EG40Other Waste Biomass0.8April 2009

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Encina Joint Powers Authority as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Generation potential vs reported

Monthly potential at seasonal net capability, next to EIA-923 output. Shows how much of the plant's capability was used.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Encina Water Pollution Control and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Encina Water Pollution Control

Questions about Encina Water Pollution Control

How much power does Encina Water Pollution Control produce?

Encina Water Pollution Control reported 14,281 MWh (14.3 GWh) of net generation in 2025, a 50.9% capacity factor on 3.2 MW of nameplate capacity. From January to July 2026 it reported 8.23 GWh, which is provisional.

Where is Encina Water Pollution Control?

Encina Water Pollution Control is in San Diego County, California, at 33.1165, −117.3215. It is in the California Independent System Operator balancing area (CISO).

Who operates Encina Water Pollution Control?

EIA-860M for August 2026 lists Encina Joint Powers Authority as the operator (EIA operator ID 5901). The operator is not always the owner.

When did Encina Water Pollution Control start operating?

Its first generator began operating in November 2008, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page