SolarOperatingIID

Seville 2

Solar power plant in Imperial County, California. 30 MW of nameplate capacity across 1 generator, operated by Deriva Energy.

Also known as Seville Solar Two · EIA plant 59723

Analyst: free account, 1 question a day.

Ocotillo WellsTitan Solar 1 (CA)Salton Sea Power Gen Co - Unit 1Seville 220 km
Open in the map
6 plants within 35 km, from EIA coordinates.

Key facts

Capacity
30 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
December 2015First generator online
Operator
Deriva EnergyEIA operator ID 65411
Grid
IIDBalancing authority IID
Price nodes
None linkedNo verified ISO node
Location
Imperial County, CA33.1101, −116.0059
EIA plant ID
59723EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Seville 2 produces

Free · EIA-923

Net generation, 2025

78.3 GWh

78,279 MWh, final

Capacity factor, 2025

29.8%

2024: 29.4%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2016 to 2025

77.5–98.7

GWh a year. Low 2024, high 2016

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
2011Not reportedNot reported0 of 12
2012Not reportedNot reported0 of 12
2013Not reportedNot reported0 of 12
2014Not reportedNot reported0 of 12
2015692Not reported1 of 12
201698,65937.4%12 of 12
201792,06435.0%12 of 12
201889,27334.0%12 of 12
201984,30032.1%12 of 12
202079,91730.3%12 of 12
202182,46731.4%12 of 12
202286,58232.9%12 of 12
202383,03931.6%12 of 12
202477,50029.4%12 of 12
202578,27929.8%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
SEV2Solar Photovoltaic30.0December 2015

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Deriva Energy as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Modeled curtailment

A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.

Modeled

Expected vs reported generation

Monthly modeled expected output and physical potential next to EIA-923 reported output.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Seville 2 and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Seville 2

More plants operated by Deriva Energy

Questions about Seville 2

How much power does Seville 2 produce?

Seville 2 reported 78,279 MWh (78.3 GWh) of net generation in 2025, a 29.8% capacity factor on 30 MW of nameplate capacity.

Where is Seville 2?

Seville 2 is in Imperial County, California, at 33.1101, −116.0059. It is in the Imperial Irrigation District balancing area (IID).

Who operates Seville 2?

EIA-860M for August 2026 lists Deriva Energy as the operator (EIA operator ID 65411). The operator is not always the owner.

When did Seville 2 start operating?

Its first generator began operating in December 2015, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page