Key facts

Capacity
280 MWNameplate
Generators
2 operatingEIA-860M, August 2026
Operating since
December 2014First generator online
Operator
Mojave Solar LLCEIA operator ID 56660
Grid
CAISOBalancing authority CISO
Price nodes
1 CAISO nodeResource nodes with prices
Location
San Bernardino County, CA35.0177, −117.3391
EIA plant ID
57331EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Mojave Solar Project produces

Free · EIA-923

Net generation, 2025

590 GWh

590,420 MWh, final

Capacity factor, 2025

24.1%

2024: 25.6%

January to July 2026

354 GWh

Provisional

Range, 2015 to 2025

503.6–629.1

GWh a year. Low 2015, high 2024

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
2011Not reportedNot reported0 of 12
2012Not reportedNot reported0 of 12
2013Not reportedNot reported0 of 12
2014Not reportedNot reported0 of 12
2015503,57620.5%12 of 12
2016624,90725.4%12 of 12
2017594,03024.2%12 of 12
2018605,18024.7%12 of 12
2019514,48421.0%12 of 12
2020558,41422.7%12 of 12
2021587,97724.0%12 of 12
2022595,70224.3%12 of 12
2023612,40225.0%12 of 12
2024629,10125.6%12 of 12
2025590,42024.1%12 of 12
2026 (provisional, partial year)354,43724.9%7 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account · CAISO

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

Withdrawal, 2024

474

million gallons

Consumption, 2024

474

million gallons

Source

On-site wells with water rights

Ground, Fresh. Induced-draft tower

Watershed stress

Very low/none · 0.178

USGS SUI, HUC12 Schweitzer Well-Harper Lake

24 of 24 cooling months report withdrawal. Groundwater user; SUI describes surface water and is context only. Blank volumes are unreported, not zero.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
MSP1Solar Thermal without Energy Storage140.0December 2014
MSP2Solar Thermal without Energy Storage140.0December 2014

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Mojave Solar LLC as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Modeled curtailment

A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.

Modeled

Expected vs reported generation

Monthly modeled expected output and physical potential next to EIA-923 reported output.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Mojave Solar Project and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Mojave Solar Project

Questions about Mojave Solar Project

How much power does Mojave Solar Project produce?

Mojave Solar Project reported 590,420 MWh (590 GWh) of net generation in 2025, a 24.1% capacity factor on 280 MW of nameplate capacity. From January to July 2026 it reported 354 GWh, which is provisional.

Where is Mojave Solar Project?

Mojave Solar Project is in San Bernardino County, California, at 35.0177, −117.3391. It is in the California Independent System Operator balancing area (CISO).

Who operates Mojave Solar Project?

EIA-860M for August 2026 lists Mojave Solar LLC as the operator (EIA operator ID 56660). The operator is not always the owner.

When did Mojave Solar Project start operating?

Its first generator began operating in December 2014, according to EIA-860M.

Does InfraMap have power prices for Mojave Solar Project?

Yes. InfraMap has CAISO day-ahead and real-time prices at 1 price node linked to Mojave Solar Project, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • CAISO day-ahead and real-time prices; node and hub assignments as of 2026-10-05
  • EIA-923 cooling water 2024 and the USGS surface water supply and use index, Water years 2010-2020 (Oct 2009 to Sep 2020), mean of monthly values

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page