Natural gasOperatingCAISO

Energy Center

Natural gas power plant in San Bernardino County, California. 0.9 MW of nameplate capacity across 3 generators, operated by University of Redlands.

Also known as EIA plant 58168

Analyst: free account, 1 question a day.

Chambers 4 - Redland LGB4Redlands Community HospitalLoma Linda University CogenIGS KSBDKohls San Bernardino Solar FacilityEnergy Center5 km
Open in the map
6 plants within 10 km, from EIA coordinates.

Key facts

Capacity
0.9 MWNameplate
Generators
3 operatingEIA-860M, August 2026
Operating since
May 2019First generator online
Operator
University of RedlandsEIA operator ID 58105
Grid
CAISOBalancing authority CISO
Price nodes
None linkedNo verified ISO node
Location
San Bernardino County, CA34.0631, −117.1639
EIA plant ID
58168EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Energy Center produces

Free · EIA-923

Net generation, 2025

4.36 GWh

4,360 MWh, final

Capacity factor, 2025

55.3%

2024: 18.8%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2015 to 2025

1.5–9.9

GWh a year. Low 2024, high 2015

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
2011Not reportedNot reported0 of 12
20127,27255.2%12 of 12
20139,88475.2%12 of 12
20149,88475.2%12 of 12
20159,94775.7%12 of 12
20167,26255.1%12 of 12
20176,93852.8%12 of 12
20182,91522.2%12 of 12
2019557Not reported2 of 12
20206,48582.0%12 of 12
20216,47482.1%12 of 12
20224,53357.5%12 of 12
20234,74760.2%12 of 12
20241,48618.8%12 of 12
20254,36055.3%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
TURB1Natural Gas Fired Combustion Turbine0.3May 2019
TURB2Natural Gas Fired Combustion Turbine0.3May 2019
TURB3Natural Gas Fired Combustion Turbine0.3May 2019

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists University of Redlands as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Generation potential vs reported

Monthly potential at seasonal net capability, next to EIA-923 output. Shows how much of the plant's capability was used.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Energy Center and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Energy Center

Questions about Energy Center

How much power does Energy Center produce?

Energy Center reported 4,360 MWh (4.36 GWh) of net generation in 2025, a 55.3% capacity factor on 0.9 MW of nameplate capacity.

Where is Energy Center?

Energy Center is in San Bernardino County, California, at 34.0631, −117.1639. It is in the California Independent System Operator balancing area (CISO).

Who operates Energy Center?

EIA-860M for August 2026 lists University of Redlands as the operator (EIA operator ID 58105). The operator is not always the owner.

When did Energy Center start operating?

Its first generator began operating in May 2019, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page