Natural gasOperatingCAISO

San Jose Cogeneration

Natural gas power plant in Santa Clara County, California. 6 MW of nameplate capacity across 1 generator, operated by San Jose State University Fclts Dev &Ops.

Also known as EIA plant 10548

Analyst: free account, 1 question a day.

CSU San Jose State UniversityKellogg's - San JoseSCC - San JoseMicro Santa ClaraSan Jose Cogeneration2 km
Open in the map
6 plants within 5.7 km, from EIA coordinates.

Key facts

Capacity
6 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
December 1984First generator online
Operator
San Jose State University Fclts Dev &OpsEIA operator ID 16732
Grid
CAISOBalancing authority CISO
Price nodes
None linkedNo verified ISO node
Location
Santa Clara County, CA37.3361, −121.8783
EIA plant ID
10548EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power San Jose Cogeneration produces

Free · EIA-923

Net generation, 2025

35.1 GWh

35,106 MWh, final

Capacity factor, 2025

66.8%

2024: 65.7%

January to July 2026

19.6 GWh

Provisional

Range, 2015 to 2025

24.2–37.8

GWh a year. Low 2022, high 2015

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
200113,025Not reported12 of 12
200236,108Not reported12 of 12
200339,564Not reported12 of 12
200438,394Not reported12 of 12
200531,769Not reported12 of 12
200637,389Not reported12 of 12
20073,537Not reported1 of 12
200823,508Not reported12 of 12
200937,683Not reported12 of 12
201036,11168.7%12 of 12
201133,69464.1%12 of 12
201239,64775.2%12 of 12
201335,12466.8%12 of 12
201436,22968.9%12 of 12
201537,83972.0%12 of 12
201634,69965.8%12 of 12
201736,57969.6%12 of 12
201830,77058.5%12 of 12
201933,35663.5%12 of 12
202031,65660.1%12 of 12
202125,67048.8%12 of 12
202224,16546.0%12 of 12
202326,23049.9%12 of 12
202434,63665.7%12 of 12
202535,10666.8%12 of 12
2026 (provisional, partial year)19,59664.2%7 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
GEN1Natural Gas Fired Combustion Turbine6.0December 1984

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists San Jose State University Fclts Dev &Ops as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Generation potential vs reported

Monthly potential at seasonal net capability, next to EIA-923 output. Shows how much of the plant's capability was used.

Analyst and MCP

300 analyst questions a month, plus MCP

Query San Jose Cogeneration and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near San Jose Cogeneration

Questions about San Jose Cogeneration

How much power does San Jose Cogeneration produce?

San Jose Cogeneration reported 35,106 MWh (35.1 GWh) of net generation in 2025, a 66.8% capacity factor on 6 MW of nameplate capacity. From January to July 2026 it reported 19.6 GWh, which is provisional.

Where is San Jose Cogeneration?

San Jose Cogeneration is in Santa Clara County, California, at 37.3361, −121.8783. It is in the California Independent System Operator balancing area (CISO).

Who operates San Jose Cogeneration?

EIA-860M for August 2026 lists San Jose State University Fclts Dev &Ops as the operator (EIA operator ID 16732). The operator is not always the owner.

When did San Jose Cogeneration start operating?

Its first generator began operating in December 1984, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page