Battery storageOperatingCAISO

San Jacinto Grid, LLC

Battery storage project in Riverside County, California. 65 MW of nameplate capacity across 1 generator, operated by San Jacinto Grid, LLC.

Also known as San Jacinto Grid · EIA plant 65657

Analyst: free account, 1 question a day.

Beaumont BESS5 km
Open in the map
6 plants within 15 km, from EIA coordinates.

Key facts

Capacity
65 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
October 2025First generator online
Operator
San Jacinto Grid, LLCEIA operator ID 64936
Grid
CAISOBalancing authority CISO
Price nodes
1 CAISO nodeResource nodes with prices
Location
Riverside County, CA33.9230, −116.8735
EIA plant ID
65657EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power San Jacinto Grid produces

Free · EIA-923

Net generation, 2025

−2.38 GWh

−2,379 MWh, final. 3 of 12 months reported

Battery discharge, 2025

9.31 GWh

Charge 11.7 GWh

January to July 2026

−3.06 GWh

Provisional

Annual net generation, GWh
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
2011Not reportedNot reported0 of 12
2012Not reportedNot reported0 of 12
2013Not reportedNot reported0 of 12
2014Not reportedNot reported0 of 12
2015Not reportedNot reported0 of 12
2016Not reportedNot reported0 of 12
2017Not reportedNot reported0 of 12
2018Not reportedNot reported0 of 12
2019Not reportedNot reported0 of 12
2020Not reportedNot reported0 of 12
2021Not reportedNot reported0 of 12
2022Not reportedNot reported0 of 12
2023Not reportedNot reported0 of 12
2024Not reportedNot reported0 of 12
2025−2,379Not reported3 of 12
2026 (provisional, partial year)−3,055Not reported7 of 7

* 2026 covers January to July and is provisional. Battery plants can report negative net generation, when charging uses more energy than they discharge.

Power prices and basis

Free account · CAISO

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
HESJGBatteries65.0October 2025

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists San Jacinto Grid, LLC as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Analyst and MCP

300 analyst questions a month, plus MCP

Query San Jacinto Grid, LLC and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near San Jacinto Grid

Questions about San Jacinto Grid

How much power does San Jacinto Grid, LLC produce?

San Jacinto Grid, LLC reported −2,379 MWh (−2.38 GWh) of net generation in 2025. From January to July 2026 it reported −3.06 GWh, which is provisional. 3 of 12 months were reported for 2025.

Where is San Jacinto Grid, LLC?

San Jacinto Grid, LLC is in Riverside County, California, at 33.9230, −116.8735. It is in the California Independent System Operator balancing area (CISO).

Who operates San Jacinto Grid, LLC?

EIA-860M for August 2026 lists San Jacinto Grid, LLC as the operator (EIA operator ID 64936). The operator is not always the owner.

When did San Jacinto Grid, LLC start operating?

Its first generator began operating in October 2025, according to EIA-860M.

Does InfraMap have power prices for San Jacinto Grid, LLC?

Yes. InfraMap has CAISO day-ahead and real-time prices at 1 price node linked to San Jacinto Grid, LLC, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • CAISO day-ahead and real-time prices; node and hub assignments as of 2026-10-05
  • Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)