SolarOperatingCAISO

RE Kent South, LLC

Solar power plant in Kings County, California. 20 MW of nameplate capacity across 1 generator, operated by Onward Energy.

Also known as RE Kent South · EIA plant 58991

Analyst: free account, 1 question a day.

Henrietta D Energy Storage LLCRE Mustang LLCWestside Solar Power PV1Slate HybridMustang TwoHenrietta PeakerRE Kent South500 m
Open in the map
6 plants within 1.5 km, from EIA coordinates.

Key facts

Capacity
20 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
December 2014First generator online
Operator
Onward EnergyEIA operator ID 60453
Grid
CAISOBalancing authority CISO
Price nodes
1 CAISO nodeResource nodes with prices
Location
Kings County, CA36.2261, −119.9053
EIA plant ID
58991EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power RE Kent South produces

Free · EIA-923

Net generation, 2025

35.7 GWh

35,670 MWh, final

Capacity factor, 2025

20.4%

2024: 25.2%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2015 to 2025

35.7–53.8

GWh a year. Low 2025, high 2015

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
2011Not reportedNot reported0 of 12
2012Not reportedNot reported0 of 12
2013Not reportedNot reported0 of 12
20141,298Not reported1 of 12
201553,78030.7%12 of 12
201653,47830.4%12 of 12
201753,16030.3%12 of 12
201851,99029.7%12 of 12
201951,42029.3%12 of 12
202048,23627.5%12 of 12
202148,84627.9%12 of 12
202249,26728.1%12 of 12
202340,63223.2%12 of 12
202444,26525.2%12 of 12
202535,67020.4%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account · CAISO

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
1Solar Photovoltaic20.0December 2014

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Onward Energy as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Modeled curtailment

A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.

Modeled

Expected vs reported generation

Monthly modeled expected output and physical potential next to EIA-923 reported output.

Analyst and MCP

300 analyst questions a month, plus MCP

Query RE Kent South, LLC and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near RE Kent South

More plants operated by Onward Energy

Questions about RE Kent South

How much power does RE Kent South, LLC produce?

RE Kent South, LLC reported 35,670 MWh (35.7 GWh) of net generation in 2025, a 20.4% capacity factor on 20 MW of nameplate capacity.

Where is RE Kent South, LLC?

RE Kent South, LLC is in Kings County, California, at 36.2261, −119.9053. It is in the California Independent System Operator balancing area (CISO).

Who operates RE Kent South, LLC?

EIA-860M for August 2026 lists Onward Energy as the operator (EIA operator ID 60453). The operator is not always the owner.

When did RE Kent South, LLC start operating?

Its first generator began operating in December 2014, according to EIA-860M.

Does InfraMap have power prices for RE Kent South, LLC?

Yes. InfraMap has CAISO day-ahead and real-time prices at 1 price node linked to RE Kent South, LLC, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • CAISO day-ahead and real-time prices; node and hub assignments as of 2026-10-05
  • Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page