RE Maplewood
Solar power plant in Pecos County, Texas. 250 MW of nameplate capacity across 2 generators, operated by Onward Energy.
Also known as EIA plant 61346
Analyst: free account, 1 question a day.
Key facts
- Capacity
- 250 MWNameplate
- Generators
- 2 operatingEIA-860M, August 2026
- Operating since
- April 2021First generator online
- Operator
- Onward EnergyEIA operator ID 60453
- Grid
- ERCOTBalancing authority ERCO
- Price nodes
- 1 ERCOT nodeResource nodes with prices
- Location
- Pecos County, TX30.9766, −102.2578
- EIA plant ID
- 61346EIA plant page
Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.
How much power RE Maplewood produces
Free · EIA-923Net generation, 2025
526 GWh
526,415 MWh, final
Capacity factor, 2025
24.0%
2024: 25.5%
January to July 2026
284 GWh
Provisional
Range, 2022 to 2025
462.7–561.0
GWh a year. Low 2023, high 2024
| Year | Net generation, MWh | Capacity factor | Months reported |
|---|---|---|---|
| 2000 | Not reported | Not reported | 0 of 12 |
| 2001 | Not reported | Not reported | 0 of 12 |
| 2002 | Not reported | Not reported | 0 of 12 |
| 2003 | Not reported | Not reported | 0 of 12 |
| 2004 | Not reported | Not reported | 0 of 12 |
| 2005 | Not reported | Not reported | 0 of 12 |
| 2006 | Not reported | Not reported | 0 of 12 |
| 2007 | Not reported | Not reported | 0 of 12 |
| 2008 | Not reported | Not reported | 0 of 12 |
| 2009 | Not reported | Not reported | 0 of 12 |
| 2010 | Not reported | Not reported | 0 of 12 |
| 2011 | Not reported | Not reported | 0 of 12 |
| 2012 | Not reported | Not reported | 0 of 12 |
| 2013 | Not reported | Not reported | 0 of 12 |
| 2014 | Not reported | Not reported | 0 of 12 |
| 2015 | Not reported | Not reported | 0 of 12 |
| 2016 | Not reported | Not reported | 0 of 12 |
| 2017 | Not reported | Not reported | 0 of 12 |
| 2018 | Not reported | Not reported | 0 of 12 |
| 2019 | Not reported | Not reported | 0 of 12 |
| 2020 | Not reported | Not reported | 0 of 12 |
| 2021 | 263,846 | Not reported | 9 of 12 |
| 2022 | 538,908 | 24.6% | 12 of 12 |
| 2023 | 462,705 | 21.1% | 12 of 12 |
| 2024 | 561,007 | 25.5% | 12 of 12 |
| 2025 | 526,415 | 24.0% | 12 of 12 |
| 2026 (provisional, partial year) | 284,311 | 22.4% | 7 of 7 |
* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.
Power prices and basis
Free account · ERCOTEmissions
Free · EPA CAMPDNo EPA emissions units are linked to this plant.
Water use
Free · EIA-923 cooling, USGSNo EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.
Generators
Free · EIA-860M| Generator | Technology | Nameplate MW | Online since |
|---|---|---|---|
| PV1 | Solar Photovoltaic | 222.0 | October 2021 |
| PV2 | Solar Photovoltaic | 28.0 | April 2021 |
Ownership and offtake
ProOwnership and offtake are part of Pro
Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Onward Energy as the operator, which is not always the owner.
Modeled data
ProPro adds modeled values for this plant. Everything above stays free.
Modeled curtailment
A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.
Expected vs reported generation
Monthly modeled expected output and physical potential next to EIA-923 reported output.
300 analyst questions a month, plus MCP
Query RE Maplewood and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.
Power plants near RE Maplewood
More plants operated by Onward Energy
Questions about RE Maplewood
How much power does RE Maplewood produce?
RE Maplewood reported 526,415 MWh (526 GWh) of net generation in 2025, a 24.0% capacity factor on 250 MW of nameplate capacity. From January to July 2026 it reported 284 GWh, which is provisional.
Where is RE Maplewood?
RE Maplewood is in Pecos County, Texas, at 30.9766, −102.2578. It is in the Electric Reliability Council of Texas, Inc. balancing area (ERCO).
Who operates RE Maplewood?
EIA-860M for August 2026 lists Onward Energy as the operator (EIA operator ID 60453). The operator is not always the owner.
When did RE Maplewood start operating?
Its first generator began operating in April 2021, according to EIA-860M.
Does InfraMap have power prices for RE Maplewood?
Yes. InfraMap has ERCOT day-ahead and real-time prices at 1 price node linked to RE Maplewood, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.
Sources
- EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
- EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
- ERCOT day-ahead and real-time prices; node and hub assignments as of 2026-10-05
Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page