WindOperatingCAISO

Painted Hills Wind Park

Wind power plant in Riverside County, California. 46.8 MW of nameplate capacity across 1 generator, operated by Terra-Gen Operating Co-Wind.

Also known as Painted Hills Repower · EIA plant 50533

Analyst: free account, 1 question a day.

Whitewater Hill Wind PartnersNorth Palm Springs 1AMountain View IIIAM Wind RepowerPainted Hills Wind Park2 km
Open in the map
6 plants within 4.1 km, from EIA coordinates.

Key facts

Capacity
46.8 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
April 2021First generator online
Operator
Terra-Gen Operating Co-WindEIA operator ID 2770
Grid
CAISOBalancing authority CISO
Price nodes
1 CAISO nodeResource nodes with prices
Location
Riverside County, CA33.9369, −116.6183
EIA plant ID
50533EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Painted Hills Wind Park produces

Free · EIA-923

Net generation, 2025

168 GWh

168,163 MWh, final

Capacity factor, 2025

41.0%

2024: 42.7%

January to July 2026

111 GWh

Provisional

Range, 2015 to 2025

29.9–177.3

GWh a year. Low 2018, high 2023

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
200134,144Not reported12 of 12
200240,138Not reported12 of 12
200331,472Not reported12 of 12
200428,171Not reported12 of 12
200534,483Not reported12 of 12
200634,652Not reported12 of 12
200737,056Not reported12 of 12
200833,602Not reported12 of 12
200936,333Not reported12 of 12
201034,73120.9%12 of 12
201137,86722.8%12 of 12
201230,47318.3%12 of 12
201332,42019.5%12 of 12
201432,33319.4%12 of 12
201531,80619.1%12 of 12
201632,83319.7%12 of 12
201731,82219.1%12 of 12
201829,90818.0%12 of 12
201930,876Not reported11 of 12
2020Not reportedNot reported0 of 12
2021117,697Not reported9 of 12
2022140,42734.3%12 of 12
2023177,25843.2%12 of 12
2024175,43642.7%12 of 12
2025168,16341.0%12 of 12
2026 (provisional, partial year)111,22046.7%7 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account · CAISO

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
PHWOnshore Wind Turbine46.8April 2021

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Terra-Gen Operating Co-Wind as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Modeled curtailment

A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.

Modeled

Expected vs reported generation

Monthly modeled expected output and physical potential next to EIA-923 reported output.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Painted Hills Wind Park and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Painted Hills Wind Park

More plants operated by Terra-Gen Operating Co-Wind

Questions about Painted Hills Wind Park

How much power does Painted Hills Wind Park produce?

Painted Hills Wind Park reported 168,163 MWh (168 GWh) of net generation in 2025, a 41.0% capacity factor on 46.8 MW of nameplate capacity. From January to July 2026 it reported 111 GWh, which is provisional.

Where is Painted Hills Wind Park?

Painted Hills Wind Park is in Riverside County, California, at 33.9369, −116.6183. It is in the California Independent System Operator balancing area (CISO).

Who operates Painted Hills Wind Park?

EIA-860M for August 2026 lists Terra-Gen Operating Co-Wind as the operator (EIA operator ID 2770). The operator is not always the owner.

When did Painted Hills Wind Park start operating?

Its first generator began operating in April 2021, according to EIA-860M.

Does InfraMap have power prices for Painted Hills Wind Park?

Yes. InfraMap has CAISO day-ahead and real-time prices at 1 price node linked to Painted Hills Wind Park, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • CAISO day-ahead and real-time prices; node and hub assignments as of 2026-10-05
  • Project names from the USGS U.S. Wind Turbine Database

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page