WindOperatingCAISO

Mojave 16/17/18

Wind power plant in Kern County, California. 88.5 MW of nameplate capacity across 1 generator, operated by Terra-Gen Operating Co-Wind.

Also known as Mojave 16, 17 & 18 (Desertwind III PPC Trust) · EIA plant 50821

Analyst: free account, 1 question a day.

Sagebrush ESSSagebrush Solar 2 ESS 59TPC Windfarms LLCMojave 3/4/5Mojave 16/17/18 BESSMojave 16/17/18500 m
Open in the map
6 plants within 1.0 km, from EIA coordinates.

Key facts

Capacity
88.5 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
December 1989First generator online
Operator
Terra-Gen Operating Co-WindEIA operator ID 2770
Grid
CAISOBalancing authority CISO
Price nodes
1 CAISO nodeResource nodes with prices
Location
Kern County, CA35.0450, −118.2642
EIA plant ID
50821EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Mojave 16/17/18 produces

Free · EIA-923

Net generation, 2025

66.3 GWh

66,295 MWh, final

Capacity factor, 2025

8.6%

2024: 9.5%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2015 to 2025

27.2–98.0

GWh a year. Low 2015, high 2020

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
200152,746Not reported12 of 12
200262,199Not reported12 of 12
200353,455Not reported12 of 12
200449,402Not reported12 of 12
200544,792Not reported12 of 12
200645,773Not reported12 of 12
200753,539Not reported12 of 12
200845,540Not reported12 of 12
200945,706Not reported12 of 12
201046,28717.6%12 of 12
201141,30015.7%12 of 12
201228,67010.9%12 of 12
201344,08916.8%12 of 12
201435,49313.5%12 of 12
201527,24510.4%12 of 12
201636,90014.0%12 of 12
201734,23813.0%12 of 12
201862,516Not reported12 of 12
201952,08912.4%12 of 12
202097,991Not reported12 of 12
202194,83612.2%12 of 12
202276,1929.8%12 of 12
202353,9367.0%12 of 12
202473,9099.5%12 of 12
202566,2958.6%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account · CAISO

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
GEN1Onshore Wind Turbine88.5December 1989

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Terra-Gen Operating Co-Wind as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Modeled curtailment

A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.

Modeled

Expected vs reported generation

Monthly modeled expected output and physical potential next to EIA-923 reported output.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Mojave 16/17/18 and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Mojave 16/17/18

More plants operated by Terra-Gen Operating Co-Wind

Questions about Mojave 16/17/18

How much power does Mojave 16/17/18 produce?

Mojave 16/17/18 reported 66,295 MWh (66.3 GWh) of net generation in 2025, a 8.6% capacity factor on 88.5 MW of nameplate capacity.

Where is Mojave 16/17/18?

Mojave 16/17/18 is in Kern County, California, at 35.0450, −118.2642. It is in the California Independent System Operator balancing area (CISO).

Who operates Mojave 16/17/18?

EIA-860M for August 2026 lists Terra-Gen Operating Co-Wind as the operator (EIA operator ID 2770). The operator is not always the owner.

When did Mojave 16/17/18 start operating?

Its first generator began operating in December 1989, according to EIA-860M.

Does InfraMap have power prices for Mojave 16/17/18?

Yes. InfraMap has CAISO day-ahead and real-time prices at 1 price node linked to Mojave 16/17/18, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • CAISO day-ahead and real-time prices; node and hub assignments as of 2026-10-05
  • Project names from the USGS U.S. Wind Turbine Database

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page