SolarBattery storageOperatingCAISO

North Juvenile Detention Center Solar

Solar and battery storage project in Tulare County, California. 1.4 MW of nameplate capacity across 2 generators, operated by SoCore Energy LLC.

Also known as EIA plant 68266

This project groups North Juvenile Detention Center Solar (EIA 68266). EIA reports them as separate plants.

Analyst: free account, 1 question a day.

Bob Wiley Detention CenterElkhorn DairyPOM Juice SolarPOM Beverage SolarIvanhoe SolarNorth Juvenile Detent…5 km
Open in the map
6 plants within 10 km, from EIA coordinates.

Key facts

Capacity
1.4 MWSolar 1.1 · Battery storage 0.3
Generators
2 operatingEIA-860M, August 2026
Operating since
November 2019First generator online
Operator
SoCore Energy LLCEIA operator ID 60520
Grid
CAISOBalancing authority CISO
Price nodes
None linkedNo verified ISO node
Location
Tulare County, CA36.4610, −119.3200
EIA plant ID
68266EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power North Juvenile Detention Center Solar produces

Free · EIA-923

Net generation, 2025

2.31 GWh

2,311 MWh, final

Capacity factor, 2025

24.2%

2024: 20.3%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2024 to 2025

2.0–2.3

GWh a year. Low 2024, high 2025

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
2011Not reportedNot reported0 of 12
2012Not reportedNot reported0 of 12
2013Not reportedNot reported0 of 12
2014Not reportedNot reported0 of 12
2015Not reportedNot reported0 of 12
2016Not reportedNot reported0 of 12
2017Not reportedNot reported0 of 12
2018Not reportedNot reported0 of 12
2019Not reportedNot reported0 of 12
2020Not reportedNot reported0 of 12
2021Not reportedNot reported0 of 12
2022Not reportedNot reported0 of 12
2023Not reportedNot reported0 of 12
20241,95120.3%12 of 12
20252,31124.2%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
BA1Batteries0.3November 2019
PV1Solar Photovoltaic1.1November 2019

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists SoCore Energy LLC as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Modeled curtailment

A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.

Modeled

Expected vs reported generation

Monthly modeled expected output and physical potential next to EIA-923 reported output.

Analyst and MCP

300 analyst questions a month, plus MCP

Query North Juvenile Detention Center Solar and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near North Juvenile Detention Center Solar

More plants operated by SoCore Energy LLC

Questions about North Juvenile Detention Center Solar

How much power does North Juvenile Detention Center Solar produce?

North Juvenile Detention Center Solar reported 2,311 MWh (2.31 GWh) of net generation in 2025, a 24.2% capacity factor on 1.4 MW of nameplate capacity.

Where is North Juvenile Detention Center Solar?

North Juvenile Detention Center Solar is in Tulare County, California, at 36.4610, −119.3200. It is in the California Independent System Operator balancing area (CISO).

Who operates North Juvenile Detention Center Solar?

EIA-860M for August 2026 lists SoCore Energy LLC as the operator (EIA operator ID 60520). The operator is not always the owner.

Is North Juvenile Detention Center Solar a solar or a battery storage plant?

Both. Solar capacity totals 1.1 MW and battery storage capacity totals 0.3 MW.

When did North Juvenile Detention Center Solar start operating?

Its first generator began operating in November 2019, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page