SolarOperatingCAISO

CA Flats Solar 150, LLC

Solar power plant in San Luis Obispo County, California. 150 MW of nameplate capacity across 1 generator, operated by Arevon Energy, Inc..

Also known as CA Flats Solar 150 · EIA plant 60034

Analyst: free account, 1 question a day.

Meridian VineyardsVintner SolarAtascadero State HospitalCA Flats Solar 15010 km
Open in the map
6 plants within 27 km, from EIA coordinates.

Key facts

Capacity
150 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
February 2019First generator online
Operator
Arevon Energy, Inc.EIA operator ID 61230
Grid
CAISOBalancing authority CISO
Price nodes
1 CAISO nodeResource nodes with prices
Location
San Luis Obispo County, CA35.6156, −120.4044
EIA plant ID
60034EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power CA Flats Solar 150 produces

Free · EIA-923

Net generation, 2025

305 GWh

305,407 MWh, final

Capacity factor, 2025

23.2%

2024: 24.7%

January to July 2026

152 GWh

Provisional

Range, 2020 to 2025

304.9–381.6

GWh a year. Low 2023, high 2021

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
2011Not reportedNot reported0 of 12
2012Not reportedNot reported0 of 12
2013Not reportedNot reported0 of 12
2014Not reportedNot reported0 of 12
2015Not reportedNot reported0 of 12
2016Not reportedNot reported0 of 12
2017Not reportedNot reported0 of 12
2018Not reportedNot reported0 of 12
2019320,888Not reported11 of 12
2020370,05928.1%12 of 12
2021381,60129.0%12 of 12
2022344,02026.2%12 of 12
2023304,85223.2%12 of 12
2024325,59424.7%12 of 12
2025305,40723.2%12 of 12
2026 (provisional, partial year)152,33720.0%7 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account · CAISO

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
GEN01Solar Photovoltaic150.0February 2019

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Arevon Energy, Inc. as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Modeled curtailment

A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.

Modeled

Expected vs reported generation

Monthly modeled expected output and physical potential next to EIA-923 reported output.

Analyst and MCP

300 analyst questions a month, plus MCP

Query CA Flats Solar 150, LLC and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near CA Flats Solar 150

More plants operated by Arevon Energy, Inc.

Questions about CA Flats Solar 150

How much power does CA Flats Solar 150, LLC produce?

CA Flats Solar 150, LLC reported 305,407 MWh (305 GWh) of net generation in 2025, a 23.2% capacity factor on 150 MW of nameplate capacity. From January to July 2026 it reported 152 GWh, which is provisional.

Where is CA Flats Solar 150, LLC?

CA Flats Solar 150, LLC is in San Luis Obispo County, California, at 35.6156, −120.4044. It is in the California Independent System Operator balancing area (CISO).

Who operates CA Flats Solar 150, LLC?

EIA-860M for August 2026 lists Arevon Energy, Inc. as the operator (EIA operator ID 61230). The operator is not always the owner.

When did CA Flats Solar 150, LLC start operating?

Its first generator began operating in February 2019, according to EIA-860M.

Does InfraMap have power prices for CA Flats Solar 150, LLC?

Yes. InfraMap has CAISO day-ahead and real-time prices at 1 price node linked to CA Flats Solar 150, LLC, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • CAISO day-ahead and real-time prices; node and hub assignments as of 2026-10-05
  • Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page