SolarOperatingCAISO

TA-High Desert LLC

Solar power plant in Los Angeles County, California. 20 MW of nameplate capacity across 1 generator, operated by TA-High Desert LLC.

Also known as TA-High Desert · TA-High Desert, LLC · EIA plant 58149

Analyst: free account, 1 question a day.

Central Antelope Dry Ranch B LLCSummer Solar LLCCentral Antelope Dry Ranch CRodeo Solar C2Rodeo Solar D2TA-High Desert500 m
Open in the map
6 plants within 1.5 km, from EIA coordinates.

Key facts

Capacity
20 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
March 2013First generator online
Operator
TA-High Desert LLCEIA operator ID 58112
Grid
CAISOBalancing authority CISO
Price nodes
1 CAISO nodeResource nodes with prices
Location
Los Angeles County, CA34.7089, −118.3047
EIA plant ID
58149EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power TA-High Desert produces

Free · EIA-923

Net generation, 2025

57.9 GWh

57,851 MWh, final

Capacity factor, 2025

33.0%

2024: 32.3%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2015 to 2025

45.4–57.9

GWh a year. Low 2023, high 2025

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
2011Not reportedNot reported0 of 12
2012Not reportedNot reported0 of 12
201344,395Not reported10 of 12
201457,73333.0%12 of 12
201557,21232.7%12 of 12
201655,87231.8%12 of 12
201755,25131.5%12 of 12
201856,15232.1%12 of 12
201949,82028.4%12 of 12
202049,73528.3%12 of 12
202151,07229.2%12 of 12
202247,35727.0%12 of 12
202345,36325.9%12 of 12
202456,82532.3%12 of 12
202557,85133.0%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account · CAISO

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
TAHDSolar Photovoltaic20.0March 2013

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists TA-High Desert LLC as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Modeled curtailment

A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.

Modeled

Expected vs reported generation

Monthly modeled expected output and physical potential next to EIA-923 reported output.

Analyst and MCP

300 analyst questions a month, plus MCP

Query TA-High Desert LLC and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near TA-High Desert

Questions about TA-High Desert

How much power does TA-High Desert LLC produce?

TA-High Desert LLC reported 57,851 MWh (57.9 GWh) of net generation in 2025, a 33.0% capacity factor on 20 MW of nameplate capacity.

Where is TA-High Desert LLC?

TA-High Desert LLC is in Los Angeles County, California, at 34.7089, −118.3047. It is in the California Independent System Operator balancing area (CISO).

Who operates TA-High Desert LLC?

EIA-860M for August 2026 lists TA-High Desert LLC as the operator (EIA operator ID 58112). The operator is not always the owner.

When did TA-High Desert LLC start operating?

Its first generator began operating in March 2013, according to EIA-860M.

Does InfraMap have power prices for TA-High Desert LLC?

Yes. InfraMap has CAISO day-ahead and real-time prices at 1 price node linked to TA-High Desert LLC, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • CAISO day-ahead and real-time prices; node and hub assignments as of 2026-10-05
  • Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)
  • Project names from the USGS U.S. Large-Scale Solar Photovoltaic Database

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page