Natural gasSolarOperatingCAISO

CSUF Trigeneration

Natural gas and solar power plant in Orange County, California. 8.9 MW of nameplate capacity across 7 generators, operated by California State University at Fullerton.

Also known as EIA plant 58169

Analyst: free account, 1 question a day.

Canyon Power PlantKaiser East La Palma Ave. Fuel CellAT&T AnaheimValley ViewCSUF Trigeneration2 km
Open in the map
6 plants within 5.7 km, from EIA coordinates.

Key facts

Capacity
8.9 MWNatural gas 4.6 · Solar 4.3
Generators
7 operatingEIA-860M, August 2026
Operating since
October 2010First generator online
Operator
California State University at FullertonEIA operator ID 58104
Grid
CAISOBalancing authority CISO
Price nodes
None linkedNo verified ISO node
Location
Orange County, CA33.8806, −117.8866
EIA plant ID
58169EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power CSUF Trigeneration produces

Free · EIA-923

Net generation, 2025

36.7 GWh

36,664 MWh, final

Capacity factor, 2025

47.0%

2024: 50.3%

January to July 2026

19.2 GWh

Provisional

Range, 2015 to 2025

31.2–39.7

GWh a year. Low 2015, high 2022

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
2011Not reportedNot reported0 of 12
201231,355Not reported12 of 12
201328,50959.2%12 of 12
201431,33465.0%12 of 12
201531,24064.8%12 of 12
201632,163Not reported12 of 12
201731,78342.7%12 of 12
201834,22346.0%12 of 12
201933,94845.6%12 of 12
202032,711Not reported12 of 12
202136,13046.3%12 of 12
202239,73951.0%12 of 12
202337,36547.9%12 of 12
202436,12150.3%11 of 12
202536,66447.0%12 of 12
2026 (provisional, partial year)19,21242.4%7 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
1Natural Gas Fired Combustion Turbine4.6October 2010
CPACSolar Photovoltaic0.3January 2012
KHSSolar Photovoltaic0.3January 2012
NPSSolar Photovoltaic2.0December 2016
PS4Solar Photovoltaic0.3January 2012
PS5Solar Photovoltaic0.4July 2020
SCPSSolar Photovoltaic1.0December 2016

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists California State University at Fullerton as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Generation potential vs reported

Monthly potential at seasonal net capability, next to EIA-923 output. Shows how much of the plant's capability was used.

Analyst and MCP

300 analyst questions a month, plus MCP

Query CSUF Trigeneration and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near CSUF Trigeneration

Questions about CSUF Trigeneration

How much power does CSUF Trigeneration produce?

CSUF Trigeneration reported 36,664 MWh (36.7 GWh) of net generation in 2025, a 47.0% capacity factor on 8.9 MW of nameplate capacity. From January to July 2026 it reported 19.2 GWh, which is provisional.

Where is CSUF Trigeneration?

CSUF Trigeneration is in Orange County, California, at 33.8806, −117.8866. It is in the California Independent System Operator balancing area (CISO).

Who operates CSUF Trigeneration?

EIA-860M for August 2026 lists California State University at Fullerton as the operator (EIA operator ID 58104). The operator is not always the owner.

Is CSUF Trigeneration a natural gas or a solar plant?

Both. Natural gas capacity totals 4.6 MW and solar capacity totals 4.3 MW.

When did CSUF Trigeneration start operating?

Its first generator began operating in October 2010, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page