Key facts

Capacity
1.8 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
April 1986First generator online
Operator
Pacific Gas & Electric Co.EIA operator ID 14328
Grid
CAISOBalancing authority CISO
Price nodes
1 CAISO nodeResource nodes with prices
Location
Butte County, CA39.8935, −121.5934
EIA plant ID
714EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Toadtown produces

Free · EIA-923

Net generation, 2025

1.78 GWh

1,779 MWh, final

Capacity factor, 2025

11.3%

2024: 14.9%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2015 to 2025

1.0–4.3

GWh a year. Low 2021, high 2019

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
20006,114Not reported12 of 12
20014,739Not reported12 of 12
20025,832Not reported12 of 12
20036,524Not reported12 of 12
20045,192Not reported12 of 12
20055,735Not reported12 of 12
20065,742Not reported12 of 12
20074,024Not reported12 of 12
20083,483Not reported12 of 12
20093,312Not reported12 of 12
20105,32833.8%12 of 12
20115,85237.1%12 of 12
20123,40421.5%12 of 12
20133,90324.8%12 of 12
20141,5429.8%12 of 12
20151,87511.9%12 of 12
20163,21620.3%12 of 12
20173,29420.9%12 of 12
20183,53422.4%12 of 12
20194,33227.5%12 of 12
20201,97812.5%12 of 12
20211,0206.5%12 of 12
20223,25220.6%12 of 12
20232,51916.0%12 of 12
20242,35014.9%12 of 12
20251,77911.3%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account · CAISO

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
1Conventional Hydroelectric1.8April 1986

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Pacific Gas & Electric Co. as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Toadtown and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Toadtown

More plants operated by Pacific Gas & Electric Co.

Questions about Toadtown

How much power does Toadtown produce?

Toadtown reported 1,779 MWh (1.78 GWh) of net generation in 2025, a 11.3% capacity factor on 1.8 MW of nameplate capacity.

Where is Toadtown?

Toadtown is in Butte County, California, at 39.8935, −121.5934. It is in the California Independent System Operator balancing area (CISO).

Who operates Toadtown?

EIA-860M for August 2026 lists Pacific Gas & Electric Co. as the operator (EIA operator ID 14328). The operator is not always the owner.

When did Toadtown start operating?

Its first generator began operating in April 1986, according to EIA-860M.

Does InfraMap have power prices for Toadtown?

Yes. InfraMap has CAISO day-ahead and real-time prices at 1 price node linked to Toadtown, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)