SolarBattery storageOperatingCAISO

CA Manteca 730 Spreckels Ave

Solar and battery storage project in San Joaquin County, California. 3 MW of nameplate capacity across 2 generators, operated by Catalyze Manteca 730 Spreckels Avenue Microgrid LLC.

Also known as EIA plant 66509

This project groups CA Manteca 730 Spreckels Ave (EIA 66509). EIA reports them as separate plants.

Analyst: free account, 1 question a day.

Tesoro RV & Boat StorageManteca Land PVLathrop 4 - SLCVA204AltaGas Ripon Energy Inc.Ameresco ForwardCA Manteca 730 Spreckels Ave5 km
Open in the map
6 plants within 11 km, from EIA coordinates.

Key facts

Capacity
3 MWSolar 1.5 · Battery storage 1.5
Generators
2 operatingEIA-860M, August 2026
Operating since
September 2024First generator online
Operator
Catalyze Manteca 730 Spreckels Avenue Microgrid LLCEIA operator ID 65514
Grid
CAISOBalancing authority CISO
Price nodes
None linkedNo verified ISO node
Location
San Joaquin County, CA37.7887, −121.1945
EIA plant ID
66509EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power CA Manteca 730 Spreckels Ave produces

Free · EIA-923

Net generation, 2025

100 MWh

100 MWh, final

Capacity factor, 2025

0.8%

2024: Not reported

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2024 to 2025

100.0–323.0

MWh a year. Low 2025, high 2024

Annual net generation, MWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
2011Not reportedNot reported0 of 12
2012Not reportedNot reported0 of 12
2013Not reportedNot reported0 of 12
2014Not reportedNot reported0 of 12
2015Not reportedNot reported0 of 12
2016Not reportedNot reported0 of 12
2017Not reportedNot reported0 of 12
2018Not reportedNot reported0 of 12
2019Not reportedNot reported0 of 12
2020Not reportedNot reported0 of 12
2021Not reportedNot reported0 of 12
2022Not reportedNot reported0 of 12
2023Not reportedNot reported0 of 12
2024323Not reported12 of 12
20251000.8%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
18259Solar Photovoltaic1.5September 2024
B8259Batteries1.5September 2024

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Catalyze Manteca 730 Spreckels Avenue Microgrid LLC as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Modeled curtailment

A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.

Modeled

Expected vs reported generation

Monthly modeled expected output and physical potential next to EIA-923 reported output.

Analyst and MCP

300 analyst questions a month, plus MCP

Query CA Manteca 730 Spreckels Ave and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near CA Manteca 730 Spreckels Ave

Questions about CA Manteca 730 Spreckels Ave

How much power does CA Manteca 730 Spreckels Ave produce?

CA Manteca 730 Spreckels Ave reported 100 MWh (100 MWh) of net generation in 2025, a 0.8% capacity factor on 3 MW of nameplate capacity.

Where is CA Manteca 730 Spreckels Ave?

CA Manteca 730 Spreckels Ave is in San Joaquin County, California, at 37.7887, −121.1945. It is in the California Independent System Operator balancing area (CISO).

Who operates CA Manteca 730 Spreckels Ave?

EIA-860M for August 2026 lists Catalyze Manteca 730 Spreckels Avenue Microgrid LLC as the operator (EIA operator ID 65514). The operator is not always the owner.

Is CA Manteca 730 Spreckels Ave a solar or a battery storage plant?

Both. Solar capacity totals 1.5 MW and battery storage capacity totals 1.5 MW.

When did CA Manteca 730 Spreckels Ave start operating?

Its first generator began operating in September 2024, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page