HydroOperatingCAISO

Friant Hydro Facility

Hydro power plant in Fresno County, California. 37.5 MW of nameplate capacity across 4 generators, operated by Friant Power Authority.

Also known as EIA plant 50393

Analyst: free account, 1 question a day.

Clovis North High SchoolSCCCD - Clovis Commun…Kerckhoff 2Site 980 65Saint Agnes Medical CenterClovis High SchoolFriant Hydro Facility10 km
Open in the map
6 plants within 20 km, from EIA coordinates.

Key facts

Capacity
37.5 MWNameplate
Generators
4 operatingEIA-860M, August 2026
Operating since
April 1985First generator online
Operator
Friant Power AuthorityEIA operator ID 25438
Grid
CAISOBalancing authority CISO
Price nodes
1 CAISO nodeResource nodes with prices
Location
Fresno County, CA36.9977, −119.7035
EIA plant ID
50393EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Friant Hydro Facility produces

Free · EIA-923

Net generation, 2025

73.5 GWh

73,499 MWh, final

Capacity factor, 2025

22.4%

2024: 18.2%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2015 to 2025

6.9–178.9

GWh a year. Low 2015, high 2019

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
200160,744Not reported12 of 12
200271,281Not reported12 of 12
200388,193Not reported12 of 12
200462,891Not reported12 of 12
2005127,235Not reported12 of 12
2006115,232Not reported12 of 12
200734,425Not reported12 of 12
200848,974Not reported12 of 12
200981,409Not reported12 of 12
201076,03928.4%12 of 12
2011117,83444.0%12 of 12
201255,98520.8%12 of 12
201349,73618.6%12 of 12
201413,6225.1%12 of 12
20156,8912.6%12 of 12
201638,41214.3%12 of 12
2017166,258Not reported12 of 12
2018125,90238.3%12 of 12
2019178,91554.5%12 of 12
202071,28821.6%12 of 12
202140,26312.3%12 of 12
202273,37922.3%12 of 12
2023106,18732.3%12 of 12
202459,84118.2%12 of 12
202573,49922.4%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account · CAISO

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
FR1Conventional Hydroelectric18.4January 1986
M1Conventional Hydroelectric9.8July 1985
RO1Conventional Hydroelectric2.4April 1985
RO2Conventional Hydroelectric6.9June 2017

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Friant Power Authority as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Friant Hydro Facility and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Friant Hydro Facility

Questions about Friant Hydro Facility

How much power does Friant Hydro Facility produce?

Friant Hydro Facility reported 73,499 MWh (73.5 GWh) of net generation in 2025, a 22.4% capacity factor on 37.5 MW of nameplate capacity.

Where is Friant Hydro Facility?

Friant Hydro Facility is in Fresno County, California, at 36.9977, −119.7035. It is in the California Independent System Operator balancing area (CISO).

Who operates Friant Hydro Facility?

EIA-860M for August 2026 lists Friant Power Authority as the operator (EIA operator ID 25438). The operator is not always the owner.

When did Friant Hydro Facility start operating?

Its first generator began operating in April 1985, according to EIA-860M.

Does InfraMap have power prices for Friant Hydro Facility?

Yes. InfraMap has CAISO day-ahead and real-time prices at 1 price node linked to Friant Hydro Facility, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • CAISO day-ahead and real-time prices; node and hub assignments as of 2026-10-05

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page