HydroOperatingCAISO

Site 980 65

Hydro power plant in Madera County, California. 2.1 MW of nameplate capacity across 1 generator, operated by Madera-Chowchilla Power Auth.

Also known as EIA plant 50322

Analyst: free account, 1 question a day.

Borden Solar FarmPacific Ethanol Madera Solar ArrayFriant Hydro FacilitySite 980 6510 km
Open in the map
6 plants within 19 km, from EIA coordinates.

Key facts

Capacity
2.1 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
February 1985First generator online
Operator
Madera-Chowchilla Power AuthEIA operator ID 26287
Grid
CAISOBalancing authority CISO
Price nodes
2 CAISO nodesResource nodes with prices
Location
Madera County, CA37.0568, −119.8997
EIA plant ID
50322EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Site 980 65 produces

Free · EIA-923

Net generation, 2025

1.04 GWh

1,035 MWh, final

Capacity factor, 2025

5.6%

2024: 12.5%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2015 to 2025

0.0–7.4

GWh a year. Low 2015, high 2017

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
20014,027Not reported12 of 12
20022,785Not reported12 of 12
2003153Not reported12 of 12
20044,000Not reported12 of 12
20056,138Not reported12 of 12
20066,558Not reported12 of 12
20072,754Not reported12 of 12
20083,679Not reported12 of 12
20095,211Not reported12 of 12
20106,23233.9%12 of 12
20114,35423.7%12 of 12
20122,77415.0%12 of 12
20131,1066.0%12 of 12
201420.0%12 of 12
201500.0%12 of 12
20163,82820.8%12 of 12
20177,39940.2%12 of 12
20183,91521.3%12 of 12
20193,86021.0%12 of 12
20202,08511.3%12 of 12
20211160.6%12 of 12
20227093.9%12 of 12
20236,27734.1%12 of 12
20242,30812.5%12 of 12
20251,0355.6%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account · CAISO

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
GEN1Conventional Hydroelectric2.1February 1985

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Madera-Chowchilla Power Auth as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Site 980 65 and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Site 980 65

Questions about Site 980 65

How much power does Site 980 65 produce?

Site 980 65 reported 1,035 MWh (1.04 GWh) of net generation in 2025, a 5.6% capacity factor on 2.1 MW of nameplate capacity.

Where is Site 980 65?

Site 980 65 is in Madera County, California, at 37.0568, −119.8997. It is in the California Independent System Operator balancing area (CISO).

Who operates Site 980 65?

EIA-860M for August 2026 lists Madera-Chowchilla Power Auth as the operator (EIA operator ID 26287). The operator is not always the owner.

When did Site 980 65 start operating?

Its first generator began operating in February 1985, according to EIA-860M.

Does InfraMap have power prices for Site 980 65?

Yes. InfraMap has CAISO day-ahead and real-time prices at 2 price nodes linked to Site 980 65, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • CAISO day-ahead and real-time prices; node and hub assignments as of 2026-10-05

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page