Calistoga Resilency Center
Other fuels and battery storage project in Napa County, California. 19.3 MW of nameplate capacity across 2 generators, operated by Calistoga Resiliency Center, LLC.
Also known as EIA plant 69358
This project groups Calistoga Resilency Center (EIA 69358). EIA reports them as separate plants.
Analyst: free account, 1 question a day.
Key facts
- Capacity
- 19.3 MWOther fuels 8.0 · Battery storage 11.3
- Generators
- 2 operatingEIA-860M, August 2026
- Operating since
- August 2025First generator online
- Operator
- Calistoga Resiliency Center, LLCEIA operator ID 67450
- Grid
- CAISOBalancing authority CISO
- Price nodes
- 1 CAISO nodeResource nodes with prices
- Location
- Napa County, CA38.5770, −122.5700
- EIA plant ID
- 69358EIA plant page
Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.
How much power Calistoga Resilency Center produces
Free · EIA-923Net generation, 2025
−183 MWh
−183 MWh, final. 5 of 12 months reported
Capacity factor, 2025
Not reported
2024: Not reported
January to July 2026
Not reported
Provisional. 0 of 7 months reported
| Year | Net generation, MWh | Capacity factor | Months reported |
|---|---|---|---|
| 2000 | Not reported | Not reported | 0 of 12 |
| 2001 | Not reported | Not reported | 0 of 12 |
| 2002 | Not reported | Not reported | 0 of 12 |
| 2003 | Not reported | Not reported | 0 of 12 |
| 2004 | Not reported | Not reported | 0 of 12 |
| 2005 | Not reported | Not reported | 0 of 12 |
| 2006 | Not reported | Not reported | 0 of 12 |
| 2007 | Not reported | Not reported | 0 of 12 |
| 2008 | Not reported | Not reported | 0 of 12 |
| 2009 | Not reported | Not reported | 0 of 12 |
| 2010 | Not reported | Not reported | 0 of 12 |
| 2011 | Not reported | Not reported | 0 of 12 |
| 2012 | Not reported | Not reported | 0 of 12 |
| 2013 | Not reported | Not reported | 0 of 12 |
| 2014 | Not reported | Not reported | 0 of 12 |
| 2015 | Not reported | Not reported | 0 of 12 |
| 2016 | Not reported | Not reported | 0 of 12 |
| 2017 | Not reported | Not reported | 0 of 12 |
| 2018 | Not reported | Not reported | 0 of 12 |
| 2019 | Not reported | Not reported | 0 of 12 |
| 2020 | Not reported | Not reported | 0 of 12 |
| 2021 | Not reported | Not reported | 0 of 12 |
| 2022 | Not reported | Not reported | 0 of 12 |
| 2023 | Not reported | Not reported | 0 of 12 |
| 2024 | Not reported | Not reported | 0 of 12 |
| 2025 | −183 | Not reported | 5 of 12 |
| 2026 (provisional, partial year) | Not reported | Not reported | 0 of 7 |
* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.
Power prices and basis
Free account · CAISOEmissions
Free · EPA CAMPDNo EPA emissions units are linked to this plant.
Water use
Free · EIA-923 cooling, USGSNo EIA cooling-water record for this plant in 2024.
Generators
Free · EIA-860M| Generator | Technology | Nameplate MW | Online since |
|---|---|---|---|
| CRCBA | Batteries | 11.3 | August 2025 |
| CRCFC | All Other | 8.0 | August 2025 |
Ownership and offtake
ProOwnership and offtake are part of Pro
Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Calistoga Resiliency Center, LLC as the operator, which is not always the owner.
Modeled data
ProPro adds modeled values for this plant. Everything above stays free.
Generation potential vs reported
Monthly potential at seasonal net capability, next to EIA-923 output. Shows how much of the plant's capability was used.
300 analyst questions a month, plus MCP
Query Calistoga Resilency Center and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.
Power plants near Calistoga Resilency Center
Questions about Calistoga Resilency Center
How much power does Calistoga Resilency Center produce?
Calistoga Resilency Center reported −183 MWh (−183 MWh) of net generation in 2025. 5 of 12 months were reported for 2025.
Where is Calistoga Resilency Center?
Calistoga Resilency Center is in Napa County, California, at 38.5770, −122.5700. It is in the California Independent System Operator balancing area (CISO).
Who operates Calistoga Resilency Center?
EIA-860M for August 2026 lists Calistoga Resiliency Center, LLC as the operator (EIA operator ID 67450). The operator is not always the owner.
Is Calistoga Resilency Center a other fuels or a battery storage plant?
Both. Other fuels capacity totals 8 MW and battery storage capacity totals 11.3 MW.
When did Calistoga Resilency Center start operating?
Its first generator began operating in August 2025, according to EIA-860M.
Does InfraMap have power prices for Calistoga Resilency Center?
Yes. InfraMap has CAISO day-ahead and real-time prices at 1 price node linked to Calistoga Resilency Center, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.
Sources
- EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
- EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
- CAISO day-ahead and real-time prices; node and hub assignments as of 2026-10-05
Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page