SolarBattery storageOperatingCAISO

CA- US Foods- Livermore

Solar and battery storage project in Alameda County, California. 2.4 MW of nameplate capacity across 2 generators, operated by EDPRNA DG CA Livermore LLC.

Also known as EIA plant 68064

This project groups CA- US Foods- Livermore (EIA 68064). EIA reports them as separate plants.

Analyst: free account, 1 question a day.

Whitethorn Solar LLCAmeresco Vasco RoadSummit WindsGolden Hills WindAltamont Gas RecoveryLas Positas College2 km
Open in the map
6 plants within 8.1 km, from EIA coordinates.

Key facts

Capacity
2.4 MWSolar 1.2 · Battery storage 1.2
Generators
2 operatingEIA-860M, August 2026
Operating since
August 2024First generator online
Operator
EDPRNA DG CA Livermore LLCEIA operator ID 66574
Grid
CAISOBalancing authority CISO
Price nodes
None linkedNo verified ISO node
Location
Alameda County, CA37.7116, −121.7085
EIA plant ID
68064EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power CA- US Foods- Livermore produces

Free · EIA-923

Net generation, 2025

1.57 GWh

1,566 MWh, final

Capacity factor, 2025

21.8%

2024: Not reported

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2024 to 2025

0.6–1.6

GWh a year. Low 2024, high 2025

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
2011Not reportedNot reported0 of 12
2012Not reportedNot reported0 of 12
2013Not reportedNot reported0 of 12
2014Not reportedNot reported0 of 12
2015Not reportedNot reported0 of 12
2016Not reportedNot reported0 of 12
2017Not reportedNot reported0 of 12
2018Not reportedNot reported0 of 12
2019Not reportedNot reported0 of 12
2020Not reportedNot reported0 of 12
2021Not reportedNot reported0 of 12
2022Not reportedNot reported0 of 12
2023Not reportedNot reported0 of 12
2024636Not reported12 of 12
20251,56621.8%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
LBABatteries1.2August 2024
USFLSolar Photovoltaic1.2August 2024

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists EDPRNA DG CA Livermore LLC as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Modeled curtailment

A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.

Modeled

Expected vs reported generation

Monthly modeled expected output and physical potential next to EIA-923 reported output.

Analyst and MCP

300 analyst questions a month, plus MCP

Query CA- US Foods- Livermore and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near CA- US Foods- Livermore

Questions about CA- US Foods- Livermore

How much power does CA- US Foods- Livermore produce?

CA- US Foods- Livermore reported 1,566 MWh (1.57 GWh) of net generation in 2025, a 21.8% capacity factor on 2.4 MW of nameplate capacity.

Where is CA- US Foods- Livermore?

CA- US Foods- Livermore is in Alameda County, California, at 37.7116, −121.7085. It is in the California Independent System Operator balancing area (CISO).

Who operates CA- US Foods- Livermore?

EIA-860M for August 2026 lists EDPRNA DG CA Livermore LLC as the operator (EIA operator ID 66574). The operator is not always the owner.

Is CA- US Foods- Livermore a solar or a battery storage plant?

Both. Solar capacity totals 1.2 MW and battery storage capacity totals 1.2 MW.

When did CA- US Foods- Livermore start operating?

Its first generator began operating in August 2024, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page