AES ES Alamitos, LLC
Battery storage project in Los Angeles County, California. 100 MW of nameplate capacity across 1 generator, operated by AES ES Alamitos, LLC.
Also known as EIA plant 61204
Analyst: free account, 1 question a day.
Key facts
- Capacity
- 100 MWNameplate
- Generators
- 1 operatingEIA-860M, August 2026
- Operating since
- January 2021First generator online
- Operator
- AES ES Alamitos, LLCEIA operator ID 62160
- Grid
- CAISOBalancing authority CISO
- Price nodes
- 1 CAISO nodeResource nodes with prices
- Location
- Los Angeles County, CA33.7702, −118.0997
- EIA plant ID
- 61204EIA plant page
Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.
How much power AES ES Alamitos produces
Free · EIA-923Net generation, 2025
−13.5 GWh
−13,483 MWh, final
Battery discharge, 2025
94.9 GWh
Charge 108 GWh
January to July 2026
−8.61 GWh
Provisional
Range, 2021 to 2025
−17.6–−13.5
GWh a year. Low 2021, high 2025
| Year | Net generation, MWh | Capacity factor | Months reported |
|---|---|---|---|
| 2000 | Not reported | Not reported | 0 of 12 |
| 2001 | Not reported | Not reported | 0 of 12 |
| 2002 | Not reported | Not reported | 0 of 12 |
| 2003 | Not reported | Not reported | 0 of 12 |
| 2004 | Not reported | Not reported | 0 of 12 |
| 2005 | Not reported | Not reported | 0 of 12 |
| 2006 | Not reported | Not reported | 0 of 12 |
| 2007 | Not reported | Not reported | 0 of 12 |
| 2008 | Not reported | Not reported | 0 of 12 |
| 2009 | Not reported | Not reported | 0 of 12 |
| 2010 | Not reported | Not reported | 0 of 12 |
| 2011 | Not reported | Not reported | 0 of 12 |
| 2012 | Not reported | Not reported | 0 of 12 |
| 2013 | Not reported | Not reported | 0 of 12 |
| 2014 | Not reported | Not reported | 0 of 12 |
| 2015 | Not reported | Not reported | 0 of 12 |
| 2016 | Not reported | Not reported | 0 of 12 |
| 2017 | Not reported | Not reported | 0 of 12 |
| 2018 | Not reported | Not reported | 0 of 12 |
| 2019 | Not reported | Not reported | 0 of 12 |
| 2020 | Not reported | Not reported | 0 of 12 |
| 2021 | −17,622 | Not reported | 12 of 12 |
| 2022 | −15,513 | Not reported | 12 of 12 |
| 2023 | −14,091 | Not reported | 12 of 12 |
| 2024 | −13,859 | Not reported | 12 of 12 |
| 2025 | −13,483 | Not reported | 12 of 12 |
| 2026 (provisional, partial year) | −8,607 | Not reported | 7 of 7 |
* 2026 covers January to July and is provisional. Battery plants can report negative net generation, when charging uses more energy than they discharge.
Power prices and basis
Free account · CAISOEmissions
Free · EPA CAMPDNo EPA emissions units are linked to this plant.
Water use
Free · EIA-923 cooling, USGSNo EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.
Generators
Free · EIA-860M| Generator | Technology | Nameplate MW | Online since |
|---|---|---|---|
| ALMTS | Batteries | 100.0 | January 2021 |
Ownership and offtake
ProOwnership and offtake are part of Pro
Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists AES ES Alamitos, LLC as the operator, which is not always the owner.
Modeled data
ProPro adds modeled values for this plant. Everything above stays free.
300 analyst questions a month, plus MCP
Query AES ES Alamitos, LLC and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.
Power plants near AES ES Alamitos
Questions about AES ES Alamitos
How much power does AES ES Alamitos, LLC produce?
AES ES Alamitos, LLC reported −13,483 MWh (−13.5 GWh) of net generation in 2025. From January to July 2026 it reported −8.61 GWh, which is provisional.
Where is AES ES Alamitos, LLC?
AES ES Alamitos, LLC is in Los Angeles County, California, at 33.7702, −118.0997. It is in the California Independent System Operator balancing area (CISO).
Who operates AES ES Alamitos, LLC?
EIA-860M for August 2026 lists AES ES Alamitos, LLC as the operator (EIA operator ID 62160). The operator is not always the owner.
When did AES ES Alamitos, LLC start operating?
Its first generator began operating in January 2021, according to EIA-860M.
Does InfraMap have power prices for AES ES Alamitos, LLC?
Yes. InfraMap has CAISO day-ahead and real-time prices at 1 price node linked to AES ES Alamitos, LLC, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.
Sources
- EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
- EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
- CAISO day-ahead and real-time prices; node and hub assignments as of 2026-10-05
Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page