Maverick Solar 6, LLC
Solar and battery storage project in Riverside County, California. 150 MW of nameplate capacity across 2 generators, operated by Maverick Solar 6, LLC.
Also known as EIA plant 64105
This project groups Maverick Solar 6, LLC (EIA 64105). EIA reports them as separate plants.
Analyst: free account, 1 question a day.
Key facts
- Capacity
- 150 MWSolar 100.0 · Battery storage 50.0
- Generators
- 2 operatingEIA-860M, August 2026
- Operating since
- November 2021First generator online
- Operator
- Maverick Solar 6, LLCEIA operator ID 63733
- Grid
- CAISOBalancing authority CISO
- Price nodes
- 2 CAISO nodesResource nodes with prices
- Location
- Riverside County, CA33.7000, −115.3800
- EIA plant ID
- 64105EIA plant page
Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.
How much power Maverick Solar 6 produces
Free · EIA-923Net generation, 2025
258 GWh
257,676 MWh, final
Capacity factor, 2025
30.3%
2024: 29.6%
January to July 2026
128 GWh
Provisional
Range, 2023 to 2025
253.0–276.1
GWh a year. Low 2024, high 2023
| Year | Net generation, MWh | Capacity factor | Months reported |
|---|---|---|---|
| 2000 | Not reported | Not reported | 0 of 12 |
| 2001 | Not reported | Not reported | 0 of 12 |
| 2002 | Not reported | Not reported | 0 of 12 |
| 2003 | Not reported | Not reported | 0 of 12 |
| 2004 | Not reported | Not reported | 0 of 12 |
| 2005 | Not reported | Not reported | 0 of 12 |
| 2006 | Not reported | Not reported | 0 of 12 |
| 2007 | Not reported | Not reported | 0 of 12 |
| 2008 | Not reported | Not reported | 0 of 12 |
| 2009 | Not reported | Not reported | 0 of 12 |
| 2010 | Not reported | Not reported | 0 of 12 |
| 2011 | Not reported | Not reported | 0 of 12 |
| 2012 | Not reported | Not reported | 0 of 12 |
| 2013 | Not reported | Not reported | 0 of 12 |
| 2014 | Not reported | Not reported | 0 of 12 |
| 2015 | Not reported | Not reported | 0 of 12 |
| 2016 | Not reported | Not reported | 0 of 12 |
| 2017 | Not reported | Not reported | 0 of 12 |
| 2018 | Not reported | Not reported | 0 of 12 |
| 2019 | Not reported | Not reported | 0 of 12 |
| 2020 | Not reported | Not reported | 0 of 12 |
| 2021 | 113,562 | 19.7% | 6 of 12 |
| 2022 | 176,462 | Not reported | 7 of 12 |
| 2023 | 276,098 | 31.8% | 12 of 12 |
| 2024 | 253,003 | 29.6% | 12 of 12 |
| 2025 | 257,676 | 30.3% | 12 of 12 |
| 2026 (provisional, partial year) | 127,891 | 25.7% | 7 of 7 |
* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.
Power prices and basis
Free account · CAISOEmissions
Free · EPA CAMPDNo EPA emissions units are linked to this plant.
Water use
Free · EIA-923 cooling, USGSNo EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.
Generators
Free · EIA-860M| Generator | Technology | Nameplate MW | Online since |
|---|---|---|---|
| MAV03 | Solar Photovoltaic | 100.0 | November 2021 |
| MAV04 | Batteries | 50.0 | June 2022 |
Ownership and offtake
ProOwnership and offtake are part of Pro
Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Maverick Solar 6, LLC as the operator, which is not always the owner.
Modeled data
ProPro adds modeled values for this plant. Everything above stays free.
Modeled curtailment
A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.
Expected vs reported generation
Monthly modeled expected output and physical potential next to EIA-923 reported output.
300 analyst questions a month, plus MCP
Query Maverick Solar 6, LLC and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.
Power plants near Maverick Solar 6
Questions about Maverick Solar 6
How much power does Maverick Solar 6, LLC produce?
Maverick Solar 6, LLC reported 257,676 MWh (258 GWh) of net generation in 2025, a 30.3% capacity factor on 150 MW of nameplate capacity. From January to July 2026 it reported 128 GWh, which is provisional.
Where is Maverick Solar 6, LLC?
Maverick Solar 6, LLC is in Riverside County, California, at 33.7000, −115.3800. It is in the California Independent System Operator balancing area (CISO).
Who operates Maverick Solar 6, LLC?
EIA-860M for August 2026 lists Maverick Solar 6, LLC as the operator (EIA operator ID 63733). The operator is not always the owner.
Is Maverick Solar 6, LLC a solar or a battery storage plant?
Both. Solar capacity totals 100 MW and battery storage capacity totals 50 MW.
When did Maverick Solar 6, LLC start operating?
Its first generator began operating in November 2021, according to EIA-860M.
Does InfraMap have power prices for Maverick Solar 6, LLC?
Yes. InfraMap has CAISO day-ahead and real-time prices at 2 price nodes linked to Maverick Solar 6, LLC, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.
Sources
- EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
- EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
- CAISO day-ahead and real-time prices; node and hub assignments as of 2026-10-05
Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page