Berry NMW Cogens
Natural gas power plant in Kern County, California. 11.4 MW of nameplate capacity across 2 generators, operated by Berry Petroleum Co.
Also known as EIA plant 62176
Analyst: free account, 1 question a day.
Key facts
- Capacity
- 11.4 MWNameplate
- Generators
- 2 operatingEIA-860M, August 2026
- Operating since
- November 2017First generator online
- Operator
- Berry Petroleum CoEIA operator ID 1569
- Grid
- CAISOBalancing authority CISO
- Price nodes
- 1 CAISO nodeResource nodes with prices
- Location
- Kern County, CA35.3076, −119.6116
- EIA plant ID
- 62176EIA plant page
Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.
How much power Berry NMW Cogens produces
Free · EIA-923Net generation, 2025
75.7 GWh
75,656 MWh, final
Capacity factor, 2025
75.8%
2024: 75.3%
January to July 2026
Not reported
Provisional. 0 of 7 months reported
Range, 2018 to 2025
39.3–75.7
GWh a year. Low 2018, high 2025
| Year | Net generation, MWh | Capacity factor | Months reported |
|---|---|---|---|
| 2000 | Not reported | Not reported | 0 of 12 |
| 2001 | Not reported | Not reported | 0 of 12 |
| 2002 | Not reported | Not reported | 0 of 12 |
| 2003 | Not reported | Not reported | 0 of 12 |
| 2004 | Not reported | Not reported | 0 of 12 |
| 2005 | Not reported | Not reported | 0 of 12 |
| 2006 | Not reported | Not reported | 0 of 12 |
| 2007 | Not reported | Not reported | 0 of 12 |
| 2008 | Not reported | Not reported | 0 of 12 |
| 2009 | Not reported | Not reported | 0 of 12 |
| 2010 | Not reported | Not reported | 0 of 12 |
| 2011 | Not reported | Not reported | 0 of 12 |
| 2012 | Not reported | Not reported | 0 of 12 |
| 2013 | Not reported | Not reported | 0 of 12 |
| 2014 | Not reported | Not reported | 0 of 12 |
| 2015 | Not reported | Not reported | 0 of 12 |
| 2016 | Not reported | Not reported | 0 of 12 |
| 2017 | Not reported | Not reported | 0 of 12 |
| 2018 | 39,305 | 46.7% | 12 of 12 |
| 2019 | 48,229 | 57.3% | 12 of 12 |
| 2020 | 50,114 | 59.4% | 12 of 12 |
| 2021 | 61,479 | 73.1% | 12 of 12 |
| 2022 | 69,384 | 82.5% | 12 of 12 |
| 2023 | 71,742 | Not reported | 12 of 12 |
| 2024 | 75,434 | 75.3% | 12 of 12 |
| 2025 | 75,656 | 75.8% | 12 of 12 |
| 2026 (provisional, partial year) | Not reported | Not reported | 0 of 7 |
* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.
Power prices and basis
Free account · CAISOEmissions
Free · EPA CAMPDNo EPA emissions units are linked to this plant.
Water use
Free · EIA-923 cooling, USGSNo EIA cooling-water record for this plant in 2024.
Generators
Free · EIA-860M| Generator | Technology | Nameplate MW | Online since |
|---|---|---|---|
| 21Z | Natural Gas Fired Combustion Turbine | 5.7 | November 2017 |
| PF | Natural Gas Fired Combustion Turbine | 5.7 | November 2017 |
Ownership and offtake
ProOwnership and offtake are part of Pro
Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Berry Petroleum Co as the operator, which is not always the owner.
Modeled data
ProPro adds modeled values for this plant. Everything above stays free.
Generation potential vs reported
Monthly potential at seasonal net capability, next to EIA-923 output. Shows how much of the plant's capability was used.
300 analyst questions a month, plus MCP
Query Berry NMW Cogens and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.
Power plants near Berry NMW Cogens
More plants operated by Berry Petroleum Co
Questions about Berry NMW Cogens
How much power does Berry NMW Cogens produce?
Berry NMW Cogens reported 75,656 MWh (75.7 GWh) of net generation in 2025, a 75.8% capacity factor on 11.4 MW of nameplate capacity.
Where is Berry NMW Cogens?
Berry NMW Cogens is in Kern County, California, at 35.3076, −119.6116. It is in the California Independent System Operator balancing area (CISO).
Who operates Berry NMW Cogens?
EIA-860M for August 2026 lists Berry Petroleum Co as the operator (EIA operator ID 1569). The operator is not always the owner.
When did Berry NMW Cogens start operating?
Its first generator began operating in November 2017, according to EIA-860M.
Does InfraMap have power prices for Berry NMW Cogens?
Yes. InfraMap has CAISO day-ahead and real-time prices at 1 price node linked to Berry NMW Cogens, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.
Sources
- EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
- EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
- CAISO day-ahead and real-time prices; node and hub assignments as of 2026-10-05
Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page