WindOperatingCAISO

Sky River Wind Energy Center

Wind power plant in Kern County, California. 60.2 MW of nameplate capacity across 1 generator, operated by Sky River Wind LLC.

Also known as Sky River Repower · EIA plant 50536

Analyst: free account, 1 question a day.

Pine Tree Solar ProjectPine Tree Wind Power ProjectNorth Sky River Energy LLCRE Barren Ridge 1Tehachapi Wind Resource II85 BSky River10 km
Open in the map
6 plants within 19 km, from EIA coordinates.

Key facts

Capacity
60.2 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
September 2021First generator online
Operator
Sky River Wind LLCEIA operator ID 64156
Grid
CAISOBalancing authority CISO
Price nodes
2 CAISO nodesResource nodes with prices
Location
Kern County, CA35.2608, −118.2469
EIA plant ID
50536EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Sky River produces

Free · EIA-923

Net generation, 2025

211 GWh

211,467 MWh, final

Capacity factor, 2025

40.1%

2024: 46.3%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2015 to 2025

37.0–245.0

GWh a year. Low 2020, high 2024

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000237,974Not reported12 of 12
2001201,280Not reported12 of 12
2002214,711Not reported12 of 12
2003212,264Not reported12 of 12
2004200,025Not reported12 of 12
2005213,102Not reported12 of 12
2006188,321Not reported12 of 12
2007193,931Not reported12 of 12
2008181,787Not reported12 of 12
2009165,445Not reported12 of 12
2010172,82925.7%12 of 12
2011170,37925.3%12 of 12
2012110,27916.3%12 of 12
2013162,67724.1%12 of 12
2014172,09025.5%12 of 12
2015130,55719.4%12 of 12
2016136,62620.2%12 of 12
2017138,30220.5%12 of 12
2018121,86018.1%12 of 12
201999,86114.8%12 of 12
202036,984Not reported12 of 12
202141,805Not reported4 of 12
2022183,82734.9%12 of 12
2023201,64338.2%12 of 12
2024244,98946.3%12 of 12
2025211,46740.1%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account · CAISO

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
SRW1Onshore Wind Turbine60.2September 2021

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Sky River Wind LLC as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Modeled curtailment

A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.

Modeled

Expected vs reported generation

Monthly modeled expected output and physical potential next to EIA-923 reported output.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Sky River Wind Energy Center and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Sky River

Questions about Sky River

How much power does Sky River Wind Energy Center produce?

Sky River Wind Energy Center reported 211,467 MWh (211 GWh) of net generation in 2025, a 40.1% capacity factor on 60.2 MW of nameplate capacity.

Where is Sky River Wind Energy Center?

Sky River Wind Energy Center is in Kern County, California, at 35.2608, −118.2469. It is in the California Independent System Operator balancing area (CISO).

Who operates Sky River Wind Energy Center?

EIA-860M for August 2026 lists Sky River Wind LLC as the operator (EIA operator ID 64156). The operator is not always the owner.

When did Sky River Wind Energy Center start operating?

Its first generator began operating in September 2021, according to EIA-860M.

Does InfraMap have power prices for Sky River Wind Energy Center?

Yes. InfraMap has CAISO day-ahead and real-time prices at 2 price nodes linked to Sky River Wind Energy Center, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • CAISO day-ahead and real-time prices; node and hub assignments as of 2026-10-05
  • Project names from the USGS U.S. Wind Turbine Database

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page