SolarBattery storageOperatingLDWP

Hecate Energy Beacon Solar 1

Solar and battery storage project in Kern County, California. 76 MW of nameplate capacity across 2 generators, operated by AES Distributed Energy.

Also known as EIA plant 59315

This project groups Hecate Energy Beacon Solar 1 (EIA 59315) and Beacon BESS 1 (EIA 61431). EIA reports them as separate plants.

Analyst: free account, 1 question a day.

Beacon Solar Plant Site 2Hecate Energy Beacon…Beacon Solar Plant Site 5Hecate Energy Beacon Solar 12 km
Open in the map
5 plants within 4.0 km, from EIA coordinates.

Key facts

Capacity
76 MWSolar 56.0 · Battery storage 20.0
Generators
2 operatingEIA-860M, August 2026
Operating since
April 2017First generator online
Operator
AES Distributed EnergyEIA operator ID 61012
Grid
LDWPBalancing authority LDWP
Price nodes
None linkedNo verified ISO node
Location
Kern County, CA35.2694, −118.0144
EIA plant ID
59315EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Hecate Energy Beacon Solar 1 produces

Free · EIA-923

Net generation, 2025

126 GWh

125,735 MWh, final

Capacity factor, 2025

26.2%

2024: 26.1%

January to July 2026

76.1 GWh

Provisional

Range, 2019 to 2025

125.7–140.4

GWh a year. Low 2025, high 2022

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
2011Not reportedNot reported0 of 12
2012Not reportedNot reported0 of 12
2013Not reportedNot reported0 of 12
2014Not reportedNot reported0 of 12
2015Not reportedNot reported0 of 12
2016Not reportedNot reported0 of 12
2017Not reportedNot reported0 of 12
201824,718Not reported3 of 12
2019136,93928.1%12 of 12
2020138,62228.3%12 of 12
2021139,59328.7%12 of 12
2022140,38528.9%12 of 12
2023133,67627.5%12 of 12
2024125,95026.1%12 of 12
2025125,73526.2%12 of 12
2026 (provisional, partial year)76,06427.2%7 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
BEAC1 EIA 59315Solar Photovoltaic56.0April 2017
BCNB1 EIA 61431Batteries20.0October 2018

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists AES Distributed Energy as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Modeled curtailment

A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.

Modeled

Expected vs reported generation

Monthly modeled expected output and physical potential next to EIA-923 reported output.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Hecate Energy Beacon Solar 1 and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Hecate Energy Beacon Solar 1

More plants operated by AES Distributed Energy

Questions about Hecate Energy Beacon Solar 1

How much power does Hecate Energy Beacon Solar 1 produce?

Hecate Energy Beacon Solar 1 reported 125,735 MWh (126 GWh) of net generation in 2025, a 26.2% capacity factor on 76 MW of nameplate capacity. From January to July 2026 it reported 76.1 GWh, which is provisional.

Where is Hecate Energy Beacon Solar 1?

Hecate Energy Beacon Solar 1 is in Kern County, California, at 35.2694, −118.0144. It is in the Los Angeles Department of Water and Power balancing area (LDWP).

Who operates Hecate Energy Beacon Solar 1?

EIA-860M for August 2026 lists AES Distributed Energy as the operator (EIA operator ID 61012). The operator is not always the owner.

Is Hecate Energy Beacon Solar 1 a solar or a battery storage plant?

Both. Solar capacity totals 56 MW and battery storage capacity totals 20 MW.

When did Hecate Energy Beacon Solar 1 start operating?

Its first generator began operating in April 2017, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page