Natural gasOperatingCAISO

Central CA Fuel Cell 1, LLC

Natural gas power plant in Tulare County, California. 2.8 MW of nameplate capacity across 1 generator, operated by Cordia.

Also known as EIA plant 63439

Analyst: free account, 1 question a day.

Tulare 1 and 2TWCGovernment Plaza SolarCentral CA Fuel Cell 15 km
Open in the map
6 plants within 12 km, from EIA coordinates.

Key facts

Capacity
2.8 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
May 2018First generator online
Operator
CordiaEIA operator ID 65297
Grid
CAISOBalancing authority CISO
Price nodes
None linkedNo verified ISO node
Location
Tulare County, CA36.1835, −119.3743
EIA plant ID
63439EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Central CA Fuel Cell 1 produces

Free · EIA-923

Net generation, 2025

13.2 GWh

13,227 MWh, final

Capacity factor, 2025

53.9%

2024: 70.6%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2019 to 2025

13.2–20.7

GWh a year. Low 2025, high 2021

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
2011Not reportedNot reported0 of 12
2012Not reportedNot reported0 of 12
2013Not reportedNot reported0 of 12
2014Not reportedNot reported0 of 12
2015Not reportedNot reported0 of 12
2016Not reportedNot reported0 of 12
2017Not reportedNot reported0 of 12
2018Not reportedNot reported0 of 12
201917,72172.2%12 of 12
202015,44862.8%12 of 12
202120,68284.3%12 of 12
202220,04581.7%12 of 12
202318,01573.4%12 of 12
202417,35670.6%12 of 12
202513,22753.9%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
CCFC1Other Natural Gas2.8May 2018

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Cordia as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Generation potential vs reported

Monthly potential at seasonal net capability, next to EIA-923 output. Shows how much of the plant's capability was used.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Central CA Fuel Cell 1, LLC and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Central CA Fuel Cell 1

Questions about Central CA Fuel Cell 1

How much power does Central CA Fuel Cell 1, LLC produce?

Central CA Fuel Cell 1, LLC reported 13,227 MWh (13.2 GWh) of net generation in 2025, a 53.9% capacity factor on 2.8 MW of nameplate capacity.

Where is Central CA Fuel Cell 1, LLC?

Central CA Fuel Cell 1, LLC is in Tulare County, California, at 36.1835, −119.3743. It is in the California Independent System Operator balancing area (CISO).

Who operates Central CA Fuel Cell 1, LLC?

EIA-860M for August 2026 lists Cordia as the operator (EIA operator ID 65297). The operator is not always the owner.

When did Central CA Fuel Cell 1, LLC start operating?

Its first generator began operating in May 2018, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page