SolarOperatingCAISO

San Antonio West Solar Rooftop

Solar power plant in Riverside County, California. 1.5 MW of nameplate capacity across 1 generator, operated by SS San Antonio West LLC.

Also known as EIA plant 57904

Analyst: free account, 1 question a day.

CA Institute for WomenCamChino Leasing LLCKP Ontario Vineyard SolarNiagara Bottling Onta…Clearwater Power PlantSan Antonio West Sola…5 km
Open in the map
6 plants within 9.5 km, from EIA coordinates.

Key facts

Capacity
1.5 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
August 2012First generator online
Operator
SS San Antonio West LLCEIA operator ID 57273
Grid
CAISOBalancing authority CISO
Price nodes
1 CAISO nodeResource nodes with prices
Location
Riverside County, CA33.9656, −117.6591
EIA plant ID
57904EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power San Antonio West Solar Rooftop produces

Free · EIA-923

Net generation, 2025

2.25 GWh

2,252 MWh, final

Capacity factor, 2025

17.1%

2024: 12.9%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2015 to 2025

1.5–2.9

GWh a year. Low 2021, high 2015

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
2011Not reportedNot reported0 of 12
20121,403Not reported5 of 12
20133,21124.4%12 of 12
20143,05523.2%12 of 12
20152,94922.4%12 of 12
20162,65720.2%12 of 12
20172,86221.8%12 of 12
20182,82721.5%12 of 12
20191,73813.2%12 of 12
20202,44418.5%12 of 12
20211,52711.6%12 of 12
20221,54111.7%12 of 12
20231,57512.0%12 of 12
20241,70612.9%12 of 12
20252,25217.1%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account · CAISO

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
CHNOSolar Photovoltaic1.5August 2012

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists SS San Antonio West LLC as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Modeled curtailment

A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.

Modeled

Expected vs reported generation

Monthly modeled expected output and physical potential next to EIA-923 reported output.

Analyst and MCP

300 analyst questions a month, plus MCP

Query San Antonio West Solar Rooftop and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near San Antonio West Solar Rooftop

Questions about San Antonio West Solar Rooftop

How much power does San Antonio West Solar Rooftop produce?

San Antonio West Solar Rooftop reported 2,252 MWh (2.25 GWh) of net generation in 2025, a 17.1% capacity factor on 1.5 MW of nameplate capacity.

Where is San Antonio West Solar Rooftop?

San Antonio West Solar Rooftop is in Riverside County, California, at 33.9656, −117.6591. It is in the California Independent System Operator balancing area (CISO).

Who operates San Antonio West Solar Rooftop?

EIA-860M for August 2026 lists SS San Antonio West LLC as the operator (EIA operator ID 57273). The operator is not always the owner.

When did San Antonio West Solar Rooftop start operating?

Its first generator began operating in August 2012, according to EIA-860M.

Does InfraMap have power prices for San Antonio West Solar Rooftop?

Yes. InfraMap has CAISO day-ahead and real-time prices at 1 price node linked to San Antonio West Solar Rooftop, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • CAISO day-ahead and real-time prices; node and hub assignments as of 2026-10-05

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page