SEPV 1
Solar power plant in Los Angeles County, California. 2 MW of nameplate capacity across 1 generator, operated by CVI CleanCapital Solar 1 LLC.
Also known as EIA plant 58073
Analyst: free account, 1 question a day.
Key facts
- Capacity
- 2 MWNameplate
- Generators
- 1 operatingEIA-860M, August 2026
- Operating since
- May 2012First generator online
- Operator
- CVI CleanCapital Solar 1 LLCEIA operator ID 65432
- Grid
- CAISOBalancing authority CISO
- Price nodes
- 1 CAISO nodeResource nodes with prices
- Location
- Los Angeles County, CA34.6189, −117.9394
- EIA plant ID
- 58073EIA plant page
Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.
How much power SEPV 1 produces
Free · EIA-923Net generation, 2025
2.51 GWh
2,514 MWh, final
Capacity factor, 2025
14.3%
2024: 15.4%
January to July 2026
Not reported
Provisional. 0 of 7 months reported
Range, 2015 to 2025
2.5–5.3
GWh a year. Low 2025, high 2016
| Year | Net generation, MWh | Capacity factor | Months reported |
|---|---|---|---|
| 2000 | Not reported | Not reported | 0 of 12 |
| 2001 | Not reported | Not reported | 0 of 12 |
| 2002 | Not reported | Not reported | 0 of 12 |
| 2003 | Not reported | Not reported | 0 of 12 |
| 2004 | Not reported | Not reported | 0 of 12 |
| 2005 | Not reported | Not reported | 0 of 12 |
| 2006 | Not reported | Not reported | 0 of 12 |
| 2007 | Not reported | Not reported | 0 of 12 |
| 2008 | Not reported | Not reported | 0 of 12 |
| 2009 | Not reported | Not reported | 0 of 12 |
| 2010 | Not reported | Not reported | 0 of 12 |
| 2011 | Not reported | Not reported | 0 of 12 |
| 2012 | 3,504 | Not reported | 8 of 12 |
| 2013 | 5,398 | 30.8% | 12 of 12 |
| 2014 | Not reported | Not reported | 0 of 12 |
| 2015 | 5,180 | 29.6% | 12 of 12 |
| 2016 | 5,329 | 30.3% | 12 of 12 |
| 2017 | 4,947 | 28.2% | 12 of 12 |
| 2018 | 5,307 | 30.3% | 12 of 12 |
| 2019 | 4,823 | 27.5% | 12 of 12 |
| 2020 | 4,275 | 24.3% | 12 of 12 |
| 2021 | 2,903 | 16.6% | 12 of 12 |
| 2022 | 3,261 | 18.6% | 12 of 12 |
| 2023 | 2,973 | 17.0% | 12 of 12 |
| 2024 | 2,700 | 15.4% | 12 of 12 |
| 2025 | 2,514 | 14.3% | 12 of 12 |
| 2026 (provisional, partial year) | Not reported | Not reported | 0 of 7 |
* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.
Power prices and basis
Free account · CAISOEmissions
Free · EPA CAMPDNo EPA emissions units are linked to this plant.
Water use
Free · EIA-923 cooling, USGSNo EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.
Generators
Free · EIA-860M| Generator | Technology | Nameplate MW | Online since |
|---|---|---|---|
| SEPV | Solar Photovoltaic | 2.0 | May 2012 |
Ownership and offtake
ProOwnership and offtake are part of Pro
Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists CVI CleanCapital Solar 1 LLC as the operator, which is not always the owner.
Modeled data
ProPro adds modeled values for this plant. Everything above stays free.
Modeled curtailment
A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.
Expected vs reported generation
Monthly modeled expected output and physical potential next to EIA-923 reported output.
300 analyst questions a month, plus MCP
Query SEPV 1 and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.
Power plants near SEPV 1
More plants operated by CVI CleanCapital Solar 1 LLC
Questions about SEPV 1
How much power does SEPV 1 produce?
SEPV 1 reported 2,514 MWh (2.51 GWh) of net generation in 2025, a 14.3% capacity factor on 2 MW of nameplate capacity.
Where is SEPV 1?
SEPV 1 is in Los Angeles County, California, at 34.6189, −117.9394. It is in the California Independent System Operator balancing area (CISO).
Who operates SEPV 1?
EIA-860M for August 2026 lists CVI CleanCapital Solar 1 LLC as the operator (EIA operator ID 65432). The operator is not always the owner.
When did SEPV 1 start operating?
Its first generator began operating in May 2012, according to EIA-860M.
Does InfraMap have power prices for SEPV 1?
Yes. InfraMap has CAISO day-ahead and real-time prices at 1 price node linked to SEPV 1, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.
Sources
- EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
- EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
- CAISO day-ahead and real-time prices; node and hub assignments as of 2026-10-05
Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page