Natural gasOperatingCAISO

CCCSD Wastewater Treatment Plnt

Natural gas power plant in Contra Costa County, California. 3.5 MW of nameplate capacity across 1 generator, operated by Central Contra Costa Sanitary District.

Also known as EIA plant 57573

Analyst: free account, 1 question a day.

Marathon Bay Area CogenMartinez RefiningMartinez Sulfuric Aci…Valero Refinery Cogeneration Unit 1Ameresco Keller CanyonCCCSD Wastewater Trea…5 km
Open in the map
6 plants within 12 km, from EIA coordinates.

Key facts

Capacity
3.5 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
December 1995First generator online
Operator
Central Contra Costa Sanitary DistrictEIA operator ID 56914
Grid
CAISOBalancing authority CISO
Price nodes
None linkedNo verified ISO node
Location
Contra Costa County, CA37.9978, −122.0697
EIA plant ID
57573EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power CCCSD Wastewater Treatment Plnt produces

Free · EIA-923

Net generation, 2025

20.0 GWh

19,998 MWh, final. 11 of 12 months reported

Capacity factor, 2025

71.3%

2024: 60.5%

January to July 2026

11.1 GWh

Provisional

Range, 2015 to 2024

18.6–22.2

GWh a year. Low 2024, high 2021

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
201023,63477.1%12 of 12
201123,37276.2%12 of 12
201211,49537.4%12 of 12
201317,19156.1%12 of 12
201418,81161.4%12 of 12
201521,81571.2%12 of 12
201619,35162.9%12 of 12
201719,24862.8%12 of 12
201821,79071.1%12 of 12
201921,54470.3%12 of 12
202020,43566.5%12 of 12
202122,18572.4%12 of 12
202221,20969.2%12 of 12
202321,70970.8%12 of 12
202418,61360.5%12 of 12
202519,99871.3%11 of 12
2026 (provisional, partial year)11,13162.5%7 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
S188Natural Gas Fired Combustion Turbine3.5December 1995

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Central Contra Costa Sanitary District as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Generation potential vs reported

Monthly potential at seasonal net capability, next to EIA-923 output. Shows how much of the plant's capability was used.

Analyst and MCP

300 analyst questions a month, plus MCP

Query CCCSD Wastewater Treatment Plnt and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near CCCSD Wastewater Treatment Plnt

Questions about CCCSD Wastewater Treatment Plnt

How much power does CCCSD Wastewater Treatment Plnt produce?

CCCSD Wastewater Treatment Plnt reported 19,998 MWh (20.0 GWh) of net generation in 2025, a 71.3% capacity factor on 3.5 MW of nameplate capacity. From January to July 2026 it reported 11.1 GWh, which is provisional. 11 of 12 months were reported for 2025.

Where is CCCSD Wastewater Treatment Plnt?

CCCSD Wastewater Treatment Plnt is in Contra Costa County, California, at 37.9978, −122.0697. It is in the California Independent System Operator balancing area (CISO).

Who operates CCCSD Wastewater Treatment Plnt?

EIA-860M for August 2026 lists Central Contra Costa Sanitary District as the operator (EIA operator ID 56914). The operator is not always the owner.

When did CCCSD Wastewater Treatment Plnt start operating?

Its first generator began operating in December 1995, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page