Lone Valley Solar Park I LLC
Solar power plant in San Bernardino County, California. 10 MW of nameplate capacity across 1 generator, operated by Lone Valley Solar Park I LLC.
Also known as Lone Valley Solar Park I, LLC · EIA plant 58417
Analyst: free account, 1 question a day.
Key facts
- Capacity
- 10 MWNameplate
- Generators
- 1 operatingEIA-860M, August 2026
- Operating since
- December 2014First generator online
- Operator
- Lone Valley Solar Park I LLCEIA operator ID 58413
- Grid
- CAISOBalancing authority CISO
- Price nodes
- 1 CAISO nodeResource nodes with prices
- Location
- San Bernardino County, CA34.3981, −116.8655
- EIA plant ID
- 58417EIA plant page
Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.
How much power Lone Valley Solar Park I produces
Free · EIA-923Net generation, 2025
24.2 GWh
24,233 MWh, final
Capacity factor, 2025
27.7%
2024: 26.9%
January to July 2026
Not reported
Provisional. 0 of 7 months reported
Range, 2015 to 2025
22.6–25.1
GWh a year. Low 2021, high 2015
| Year | Net generation, MWh | Capacity factor | Months reported |
|---|---|---|---|
| 2000 | Not reported | Not reported | 0 of 12 |
| 2001 | Not reported | Not reported | 0 of 12 |
| 2002 | Not reported | Not reported | 0 of 12 |
| 2003 | Not reported | Not reported | 0 of 12 |
| 2004 | Not reported | Not reported | 0 of 12 |
| 2005 | Not reported | Not reported | 0 of 12 |
| 2006 | Not reported | Not reported | 0 of 12 |
| 2007 | Not reported | Not reported | 0 of 12 |
| 2008 | Not reported | Not reported | 0 of 12 |
| 2009 | Not reported | Not reported | 0 of 12 |
| 2010 | Not reported | Not reported | 0 of 12 |
| 2011 | Not reported | Not reported | 0 of 12 |
| 2012 | Not reported | Not reported | 0 of 12 |
| 2013 | Not reported | Not reported | 0 of 12 |
| 2014 | 2,068 | Not reported | 1 of 12 |
| 2015 | 25,071 | 28.6% | 12 of 12 |
| 2016 | 22,954 | 26.1% | 12 of 12 |
| 2017 | 23,826 | 27.2% | 12 of 12 |
| 2018 | 24,116 | 27.5% | 12 of 12 |
| 2019 | 23,814 | 27.2% | 12 of 12 |
| 2020 | 22,966 | 26.1% | 12 of 12 |
| 2021 | 22,642 | 25.8% | 12 of 12 |
| 2022 | 23,572 | 26.9% | 12 of 12 |
| 2023 | 23,773 | 27.1% | 12 of 12 |
| 2024 | 23,630 | 26.9% | 12 of 12 |
| 2025 | 24,233 | 27.7% | 12 of 12 |
| 2026 (provisional, partial year) | Not reported | Not reported | 0 of 7 |
* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.
Power prices and basis
Free account · CAISOEmissions
Free · EPA CAMPDNo EPA emissions units are linked to this plant.
Water use
Free · EIA-923 cooling, USGSNo EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.
Generators
Free · EIA-860M| Generator | Technology | Nameplate MW | Online since |
|---|---|---|---|
| CP1 | Solar Photovoltaic | 10.0 | December 2014 |
Ownership and offtake
ProOwnership and offtake are part of Pro
Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Lone Valley Solar Park I LLC as the operator, which is not always the owner.
Modeled data
ProPro adds modeled values for this plant. Everything above stays free.
Modeled curtailment
A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.
Expected vs reported generation
Monthly modeled expected output and physical potential next to EIA-923 reported output.
300 analyst questions a month, plus MCP
Query Lone Valley Solar Park I LLC and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.
Power plants near Lone Valley Solar Park I
Questions about Lone Valley Solar Park I
How much power does Lone Valley Solar Park I LLC produce?
Lone Valley Solar Park I LLC reported 24,233 MWh (24.2 GWh) of net generation in 2025, a 27.7% capacity factor on 10 MW of nameplate capacity.
Where is Lone Valley Solar Park I LLC?
Lone Valley Solar Park I LLC is in San Bernardino County, California, at 34.3981, −116.8655. It is in the California Independent System Operator balancing area (CISO).
Who operates Lone Valley Solar Park I LLC?
EIA-860M for August 2026 lists Lone Valley Solar Park I LLC as the operator (EIA operator ID 58413). The operator is not always the owner.
When did Lone Valley Solar Park I LLC start operating?
Its first generator began operating in December 2014, according to EIA-860M.
Does InfraMap have power prices for Lone Valley Solar Park I LLC?
Yes. InfraMap has CAISO day-ahead and real-time prices at 1 price node linked to Lone Valley Solar Park I LLC, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.
Sources
- EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
- EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
- CAISO day-ahead and real-time prices; node and hub assignments as of 2026-10-05
- Project names from the USGS U.S. Large-Scale Solar Photovoltaic Database
Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page