Key facts

Capacity
7.5 MWNameplate
Generators
5 operatingEIA-860M, August 2026
Operating since
November 1962First generator online
Operator
City of La Crosse - (KS)EIA operator ID 10559
Grid
SPPBalancing authority SWPP
Price nodes
None linkedNo verified ISO node
Location
Rush County, KS38.5317, −99.3083
EIA plant ID
1297EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power La Crosse produces

Free · EIA-923

Net generation, 2025

9 MWh

9 MWh, final

Capacity factor, 2025

0.0%

2024: Not reported

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2015 to 2025

9.0–85.0

MWh a year. Low 2025, high 2022

Annual net generation, MWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
20000Not reported12 of 12
2001Not reportedNot reported0 of 12
200240Not reported12 of 12
2003142Not reported12 of 12
2004119Not reported12 of 12
2005148Not reported12 of 12
2006157Not reported12 of 12
200787Not reported12 of 12
2008−50Not reported12 of 12
200925Not reported12 of 12
2010650.1%12 of 12
2011500.1%12 of 12
2012330.1%12 of 12
2013120.0%12 of 12
2014230.0%12 of 12
2015190.0%12 of 12
2016140.0%12 of 12
2017290.1%12 of 12
2018160.0%12 of 12
2019420.1%12 of 12
2020250.1%12 of 12
2021790.2%12 of 12
2022850.2%12 of 12
2023240.0%12 of 12
202413Not reported12 of 12
202590.0%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
1Petroleum Liquids1.1November 1962
2Petroleum Liquids1.1December 1964
5Petroleum Liquids1.5January 1969
6Petroleum Liquids1.8December 1975
7Petroleum Liquids2.0February 2024

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists City of La Crosse - (KS) as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Generation potential vs reported

Monthly potential at seasonal net capability, next to EIA-923 output. Shows how much of the plant's capability was used.

Analyst and MCP

300 analyst questions a month, plus MCP

Query La Crosse and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near La Crosse

Questions about La Crosse

How much power does La Crosse produce?

La Crosse reported 9 MWh (9 MWh) of net generation in 2025, a 0.0% capacity factor on 7.5 MW of nameplate capacity.

Where is La Crosse?

La Crosse is in Rush County, Kansas, at 38.5317, −99.3083. It is in the Southwest Power Pool balancing area (SWPP).

Who operates La Crosse?

EIA-860M for August 2026 lists City of La Crosse - (KS) as the operator (EIA operator ID 10559). The operator is not always the owner.

When did La Crosse start operating?

Its first generator began operating in November 1962, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page