HydroOperatingISO-NE

North Gorham

Hydro power plant in Cumberland County, Maine. 2.2 MW of nameplate capacity across 2 generators, operated by Brookfield White Pine Hydro LLC.

Also known as North Gorham Power Plant · EIA plant 1501

Analyst: free account, 1 question a day.

Roosevelt TrailStandishShakerCross Town Energy StorageDynamic - Gray SolarS D Warren WestbrookNorth Gorham5 km
Open in the map
6 plants within 15 km, from EIA coordinates.

Key facts

Capacity
2.2 MWNameplate
Generators
2 operatingEIA-860M, August 2026
Operating since
January 1925First generator online
Operator
Brookfield White Pine Hydro LLCEIA operator ID 39006
Grid
ISO-NEBalancing authority ISNE
Price nodes
1 ISONE nodeResource nodes with prices
Location
Cumberland County, ME43.8025, −70.4499
EIA plant ID
1501EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power North Gorham produces

Free · EIA-923

Net generation, 2025

6.46 GWh

6,456 MWh, final

Capacity factor, 2025

33.5%

2024: 34.1%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2015 to 2025

6.5–12.2

GWh a year. Low 2025, high 2019

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
20018,807Not reported12 of 12
20026,315Not reported12 of 12
20039,017Not reported12 of 12
20049,756Not reported12 of 12
200511,908Not reported12 of 12
200612,350Not reported12 of 12
200710,328Not reported12 of 12
200811,224Not reported12 of 12
200913,924Not reported12 of 12
201011,46159.5%12 of 12
201110,82756.2%12 of 12
20127,79340.3%12 of 12
20138,81345.7%12 of 12
201410,40454.0%12 of 12
20158,27342.9%12 of 12
20169,71250.3%12 of 12
201710,38353.9%12 of 12
201810,29153.4%12 of 12
201912,15263.1%12 of 12
202010,01451.8%12 of 12
20217,01236.4%12 of 12
20228,62444.7%12 of 12
20239,40448.8%12 of 12
20246,59334.1%12 of 12
20256,45633.5%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account · ISONE

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
1Conventional Hydroelectric1.1January 1925
2Conventional Hydroelectric1.1January 1925

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Brookfield White Pine Hydro LLC as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Analyst and MCP

300 analyst questions a month, plus MCP

Query North Gorham and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near North Gorham

More plants operated by Brookfield White Pine Hydro LLC

Questions about North Gorham

How much power does North Gorham produce?

North Gorham reported 6,456 MWh (6.46 GWh) of net generation in 2025, a 33.5% capacity factor on 2.2 MW of nameplate capacity.

Where is North Gorham?

North Gorham is in Cumberland County, Maine, at 43.8025, −70.4499. It is in the ISO New England Inc. balancing area (ISNE).

Who operates North Gorham?

EIA-860M for August 2026 lists Brookfield White Pine Hydro LLC as the operator (EIA operator ID 39006). The operator is not always the owner.

When did North Gorham start operating?

Its first generator began operating in January 1925, according to EIA-860M.

Does InfraMap have power prices for North Gorham?

Yes. InfraMap has ISONE day-ahead and real-time prices at 1 price node linked to North Gorham, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • ISONE day-ahead and real-time prices; node and hub assignments as of 2026-10-05
  • Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page