OilOperatingPJM

Easton

Oil power plant in Talbot County, Maryland. 31.1 MW of nameplate capacity across 9 generators, operated by Easton Utilities Comm.

Also known as Easton Power Plant · EIA plant 1580

Analyst: free account, 1 question a day.

MEBAWye Mills VNEM CSGChesapeake CollegeUMCES Ground MountMustang OneEaston10 km
Open in the map
6 plants within 24 km, from EIA coordinates.

Key facts

Capacity
31.1 MWNameplate
Generators
9 operatingEIA-860M, August 2026
Operating since
November 1954First generator online
Operator
Easton Utilities CommEIA operator ID 5625
Grid
PJMBalancing authority PJM
Price nodes
1 PJM nodeResource nodes with prices
Location
Talbot County, MD38.7786, −76.0769
EIA plant ID
1580EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Easton produces

Free · EIA-923

Net generation, 2025

2.70 GWh

2,704 MWh, final

Capacity factor, 2025

1.0%

2024: -0.4%

January to July 2026

3.84 GWh

Provisional

Range, 2015 to 2025

−1.1–5.0

GWh a year. Low 2016, high 2015

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
20000Not reported12 of 12
200118,041Not reported6 of 12
200215,163Not reported12 of 12
200326,296Not reported12 of 12
200413,606Not reported12 of 12
200516,839Not reported12 of 12
20064,698Not reported12 of 12
200710,370Not reported12 of 12
20082,172Not reported12 of 12
2009808Not reported12 of 12
20109920.3%12 of 12
20112,8131.0%12 of 12
20122,0870.7%12 of 12
20138,4902.9%12 of 12
20144,9611.7%12 of 12
20154,9711.7%12 of 12
2016−1,085-0.4%12 of 12
20176750.2%12 of 12
20182350.1%12 of 12
2019−50-0.0%12 of 12
2020−184-0.1%12 of 12
20211460.0%12 of 12
20224,2751.5%12 of 12
2023−963-0.3%12 of 12
2024−1,055-0.4%12 of 12
20252,7041.0%12 of 12
2026 (provisional, partial year)3,8442.4%7 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account · PJM

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
7Petroleum Liquids2.5November 1954
9Petroleum Liquids3.0December 1961
10Petroleum Liquids3.5May 1966
11Petroleum Liquids3.8June 1968
12Petroleum Liquids4.1July 1970
13Petroleum Liquids5.6July 1973
14Petroleum Liquids5.6July 1973
101Petroleum Liquids1.5December 1995
102Petroleum Liquids1.5December 1995

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Easton Utilities Comm as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Generation potential vs reported

Monthly potential at seasonal net capability, next to EIA-923 output. Shows how much of the plant's capability was used.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Easton and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Easton

More plants operated by Easton Utilities Comm

Questions about Easton

How much power does Easton produce?

Easton reported 2,704 MWh (2.70 GWh) of net generation in 2025, a 1.0% capacity factor on 31.1 MW of nameplate capacity. From January to July 2026 it reported 3.84 GWh, which is provisional.

Where is Easton?

Easton is in Talbot County, Maryland, at 38.7786, −76.0769. It is in the PJM Interconnection, LLC balancing area (PJM).

Who operates Easton?

EIA-860M for August 2026 lists Easton Utilities Comm as the operator (EIA operator ID 5625). The operator is not always the owner.

When did Easton start operating?

Its first generator began operating in November 1954, according to EIA-860M.

Does InfraMap have power prices for Easton?

Yes. InfraMap has PJM day-ahead and real-time prices at 1 price node linked to Easton, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • PJM day-ahead and real-time prices; node and hub assignments as of 2026-10-05
  • Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)