HydroOperatingMISO

Chalk Hill

Hydro power plant in Menominee County, Michigan. 7.8 MW of nameplate capacity across 3 generators, operated by Wisconsin Electric Power Co.

Also known as Chalk Hill Power Plant · EIA plant 1776

Analyst: free account, 1 question a day.

Grand RapidsNorway (MI)Little Quinnesec Falls Hydro ProjectBig Quinnesec 92Chalk Hill20 km
Open in the map
6 plants within 36 km, from EIA coordinates.

Key facts

Capacity
7.8 MWNameplate
Generators
3 operatingEIA-860M, August 2026
Operating since
May 1927First generator online
Operator
Wisconsin Electric Power CoEIA operator ID 20847
Grid
MISOBalancing authority MISO
Price nodes
1 MISO nodeResource nodes with prices
Location
Menominee County, MI45.5136, −87.8011
EIA plant ID
1776EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Chalk Hill produces

Free · EIA-923

Net generation, 2025

34.0 GWh

33,984 MWh, final

Capacity factor, 2025

49.7%

2024: 19.8%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2015 to 2025

13.6–43.3

GWh a year. Low 2024, high 2019

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
200032,419Not reported12 of 12
200131,510Not reported12 of 12
200237,698Not reported12 of 12
200330,583Not reported12 of 12
200432,054Not reported12 of 12
200527,405Not reported12 of 12
200627,906Not reported12 of 12
200722,558Not reported12 of 12
200823,761Not reported12 of 12
200921,013Not reported12 of 12
201026,27930.3%12 of 12
201124,70928.5%12 of 12
201219,881Not reported12 of 12
201326,77739.2%12 of 12
201437,22354.5%12 of 12
201533,49649.0%12 of 12
201638,40156.0%12 of 12
201740,04158.6%12 of 12
201838,61156.5%12 of 12
201943,28563.3%12 of 12
202041,35260.4%12 of 12
202132,47147.5%12 of 12
202233,04648.4%12 of 12
202330,23744.3%12 of 12
202413,57019.8%12 of 12
202533,98449.7%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account · MISO

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
1Conventional Hydroelectric2.6May 1927
2Conventional Hydroelectric2.6May 1927
3Conventional Hydroelectric2.6May 1927

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Wisconsin Electric Power Co as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Chalk Hill and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Chalk Hill

More plants operated by Wisconsin Electric Power Co

Questions about Chalk Hill

How much power does Chalk Hill produce?

Chalk Hill reported 33,984 MWh (34.0 GWh) of net generation in 2025, a 49.7% capacity factor on 7.8 MW of nameplate capacity.

Where is Chalk Hill?

Chalk Hill is in Menominee County, Michigan, at 45.5136, −87.8011. It is in the Midcontinent Independent Transmission System Operator, Inc.. balancing area (MISO).

Who operates Chalk Hill?

EIA-860M for August 2026 lists Wisconsin Electric Power Co as the operator (EIA operator ID 20847). The operator is not always the owner.

When did Chalk Hill start operating?

Its first generator began operating in May 1927, according to EIA-860M.

Does InfraMap have power prices for Chalk Hill?

Yes. InfraMap has MISO day-ahead and real-time prices at 1 price node linked to Chalk Hill, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • MISO day-ahead and real-time prices; node and hub assignments as of 2026-10-05
  • Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page