Municipal solid wasteOperatingMISO

Red Wing

Municipal solid waste power plant in Goodhue County, Minnesota. 23 MW of nameplate capacity across 2 generators, operated by Northern States Power Co - Minnesota.

Also known as Red Wing Steam Plant · Red Wing Generation Station · EIA plant 1926

Analyst: free account, 1 question a day.

Red Wing Community SolarNovel Stumpf 1 Solar CSGTrimbelle (Pierce Pepin)Foreman's Hill Community SolarRed Wing5 km
Open in the map
6 plants within 12 km, from EIA coordinates.

Key facts

Capacity
23 MWNameplate
Generators
2 operatingEIA-860M, August 2026
Operating since
October 1949First generator online
Operator
Northern States Power Co - MinnesotaEIA operator ID 13781
Grid
MISOBalancing authority MISO
Price nodes
2 MISO nodesResource nodes with prices
Location
Goodhue County, MN44.5692, −92.5169
EIA plant ID
1926EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Red Wing produces

Free · EIA-923

Net generation, 2025

125 GWh

125,450 MWh, final

Capacity factor, 2025

62.3%

2024: 61.0%

January to July 2026

66.1 GWh

Provisional

Range, 2015 to 2025

107.8–145.2

GWh a year. Low 2017, high 2020

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000111,775Not reported12 of 12
2001112,231Not reported12 of 12
2002116,878Not reported12 of 12
2003111,315Not reported12 of 12
2004113,280Not reported12 of 12
2005110,316Not reported12 of 12
200697,593Not reported12 of 12
2007103,964Not reported12 of 12
200899,907Not reported12 of 12
200997,045Not reported12 of 12
20108,48849.6%1 of 12
201118,25653.3%2 of 12
201262,31852.8%7 of 12
2013111,04955.1%12 of 12
2014109,52854.4%12 of 12
2015117,83058.5%12 of 12
2016128,13963.4%12 of 12
2017107,79253.5%12 of 12
2018121,33960.2%12 of 12
2019137,00468.0%12 of 12
2020145,16571.9%12 of 12
2021132,08665.6%12 of 12
2022124,53461.8%12 of 12
2023134,57766.8%12 of 12
2024123,21361.0%12 of 12
2025125,45062.3%12 of 12
2026 (provisional, partial year)66,08956.5%7 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account · MISO

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
1Municipal Solid Waste11.5October 1949
2Municipal Solid Waste11.5November 1949

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Northern States Power Co - Minnesota as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Generation potential vs reported

Monthly potential at seasonal net capability, next to EIA-923 output. Shows how much of the plant's capability was used.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Red Wing and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Red Wing

More plants operated by Northern States Power Co - Minnesota

Questions about Red Wing

How much power does Red Wing produce?

Red Wing reported 125,450 MWh (125 GWh) of net generation in 2025, a 62.3% capacity factor on 23 MW of nameplate capacity. From January to July 2026 it reported 66.1 GWh, which is provisional.

Where is Red Wing?

Red Wing is in Goodhue County, Minnesota, at 44.5692, −92.5169. It is in the Midcontinent Independent Transmission System Operator, Inc.. balancing area (MISO).

Who operates Red Wing?

EIA-860M for August 2026 lists Northern States Power Co - Minnesota as the operator (EIA operator ID 13781). The operator is not always the owner.

When did Red Wing start operating?

Its first generator began operating in October 1949, according to EIA-860M.

Does InfraMap have power prices for Red Wing?

Yes. InfraMap has MISO day-ahead and real-time prices at 2 price nodes linked to Red Wing, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • MISO day-ahead and real-time prices; node and hub assignments as of 2026-10-05
  • Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page