HydroOperatingTVA

Old Hickory

Hydro power plant in Sumner County, Tennessee. 103.7 MW of nameplate capacity across 4 generators, operated by USCE-Nashville District.

Also known as Old Hickory Power Plant · EIA plant 3426

Analyst: free account, 1 question a day.

Music City Community SolarOpryland USAJ P PriestOld Hickory10 km
Open in the map
5 plants within 23 km, from EIA coordinates.

Key facts

Capacity
103.7 MWNameplate
Generators
4 operatingEIA-860M, August 2026
Operating since
April 1957First generator online
Operator
USCE-Nashville DistrictEIA operator ID 19462
Grid
TVABalancing authority TVA
Price nodes
None linkedNo verified ISO node
Location
Sumner County, TN36.2972, −86.6556
EIA plant ID
3426EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Old Hickory produces

Free · EIA-923

Net generation, 2025

325 GWh

324,741 MWh, final

Capacity factor, 2025

35.7%

2024: 47.9%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2015 to 2025

324.7–515.7

GWh a year. Low 2025, high 2021

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000338,948Not reported12 of 12
2001362,726Not reported12 of 12
2002495,485Not reported12 of 12
2003652,387Not reported12 of 12
2004682,392Not reported12 of 12
2005453,551Not reported12 of 12
2006407,848Not reported12 of 12
2007250,279Not reported12 of 12
2008537,428Not reported12 of 12
2009530,044Not reported12 of 12
2010412,77845.4%12 of 12
2011485,82853.5%12 of 12
2012416,98845.8%12 of 12
2013548,23360.4%12 of 12
2014489,93553.9%12 of 12
2015483,68253.2%12 of 12
2016390,69242.9%12 of 12
2017484,85253.4%12 of 12
2018453,88050.0%12 of 12
2019377,45541.6%12 of 12
2020512,09056.2%12 of 12
2021515,65456.8%12 of 12
2022483,31553.2%12 of 12
2023368,68240.6%12 of 12
2024436,55547.9%12 of 12
2025324,74135.7%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
1Conventional Hydroelectric28.7April 1957
2Conventional Hydroelectric25.0July 1957
3Conventional Hydroelectric25.0September 1957
4Conventional Hydroelectric25.0December 1957

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists USCE-Nashville District as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Old Hickory and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Old Hickory

More plants operated by USCE-Nashville District

Questions about Old Hickory

How much power does Old Hickory produce?

Old Hickory reported 324,741 MWh (325 GWh) of net generation in 2025, a 35.7% capacity factor on 103.7 MW of nameplate capacity.

Where is Old Hickory?

Old Hickory is in Sumner County, Tennessee, at 36.2972, −86.6556. It is in the Tennessee Valley Authority balancing area (TVA).

Who operates Old Hickory?

EIA-860M for August 2026 lists USCE-Nashville District as the operator (EIA operator ID 19462). The operator is not always the owner.

When did Old Hickory start operating?

Its first generator began operating in April 1957, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page