Natural gasOperatingERCOT

Leon Creek

Natural gas power plant in Bexar County, Texas. 229.6 MW of nameplate capacity across 4 generators, operated by City of San Antonio - (TX).

Also known as Leon Creek Power Plant · EIA plant 3609

Analyst: free account, 1 question a day.

Nelson Gardens Landfill Gas to EnergyCommerce ESSBexar ESSHEB_CPS00085Leon Creek5 km
Open in the map
6 plants within 15 km, from EIA coordinates.

Key facts

Capacity
229.6 MWNameplate
Generators
4 operatingEIA-860M, August 2026
Operating since
June 2004First generator online
Operator
City of San Antonio - (TX)EIA operator ID 16604
Grid
ERCOTBalancing authority ERCO
Price nodes
2 ERCOT nodesResource nodes with prices
Location
Bexar County, TX29.3525, −98.5761
EIA plant ID
3609EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Leon Creek produces

Free · EIA-923

Net generation, 2025

386 GWh

385,732 MWh, final

Capacity factor, 2025

19.2%

2024: 11.3%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2015 to 2025

33.0–385.7

GWh a year. Low 2015, high 2025

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
200090,621Not reported12 of 12
200131,862Not reported12 of 12
2002−1,577Not reported12 of 12
2003−1,513Not reported12 of 12
2004144,703Not reported7 of 12
2005275,816Not reported12 of 12
2006127,181Not reported12 of 12
2007111,466Not reported12 of 12
2008157,377Not reported12 of 12
2009125,538Not reported12 of 12
201034,4280.9%12 of 12
2011156,9504.3%12 of 12
201294,1192.6%12 of 12
201335,793Not reported6 of 12
201462,1683.1%12 of 12
201533,0351.6%12 of 12
201664,7533.2%12 of 12
201797,5254.8%12 of 12
2018201,10210.0%12 of 12
2019165,1108.2%12 of 12
2020121,2246.0%12 of 12
202180,3554.0%12 of 12
2022145,3457.2%12 of 12
2023223,19711.1%12 of 12
2024227,52911.3%12 of 12
2025385,73219.2%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account · ERCOT

Emissions

Free · EPA CAMPD

CO₂, 2025

233,252

US short tons. 2024: 139,373

SO₂, 2025

1

US short tons

NOx, 2025

35

US short tons

CO₂ per MWh, calculated

0.60 t

About 1,209 lb per MWh

4 of 4 EPA units reported CO₂ in 2025 (3, 4, CGT1, CGT2, CGT3, CGT4), matched to EIA plant 3609 through the EPA–EIA crosswalk. The per-MWh rate is EPA CO₂ divided by EIA-923 net generation. The two reporting boundaries can differ.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
CGT1Natural Gas Fired Combustion Turbine57.4June 2004
CGT2Natural Gas Fired Combustion Turbine57.4June 2004
CGT3Natural Gas Fired Combustion Turbine57.4June 2004
CGT4Natural Gas Fired Combustion Turbine57.4June 2004

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists City of San Antonio - (TX) as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Generation potential vs reported

Monthly potential at seasonal net capability, next to EIA-923 output. Shows how much of the plant's capability was used.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Leon Creek and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Leon Creek

More plants operated by City of San Antonio - (TX)

Questions about Leon Creek

How much power does Leon Creek produce?

Leon Creek reported 385,732 MWh (386 GWh) of net generation in 2025, a 19.2% capacity factor on 229.6 MW of nameplate capacity.

Where is Leon Creek?

Leon Creek is in Bexar County, Texas, at 29.3525, −98.5761. It is in the Electric Reliability Council of Texas, Inc. balancing area (ERCO).

Who operates Leon Creek?

EIA-860M for August 2026 lists City of San Antonio - (TX) as the operator (EIA operator ID 16604). The operator is not always the owner.

When did Leon Creek start operating?

Its first generator began operating in June 2004, according to EIA-860M.

Does InfraMap have power prices for Leon Creek?

Yes. InfraMap has ERCOT day-ahead and real-time prices at 2 price nodes linked to Leon Creek, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • EPA CAMPD annual emissions through the EPA–EIA crosswalk, 1995 to 2025
  • ERCOT day-ahead and real-time prices; node and hub assignments as of 2026-10-05
  • Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page