Municipal solid wasteOperatingFPC

Covanta Lake County Energy

Municipal solid waste power plant in Lake County, Florida. 15.5 MW of nameplate capacity across 1 generator, operated by Covanta Lake Inc.

Also known as Covanta Lake County Waste-to-Energy · EIA plant 50629

Analyst: free account, 1 question a day.

Cutrale Citrus Juices USA IHalf Moon Solar PlantRattler Solar PlantCovanta Lake County Energy20 km
Open in the map
6 plants within 41 km, from EIA coordinates.

Key facts

Capacity
15.5 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
September 1990First generator online
Operator
Covanta Lake IncEIA operator ID 4482
Grid
FPCBalancing authority FPC
Price nodes
None linkedNo verified ISO node
Location
Lake County, FL28.7402, −81.8892
EIA plant ID
50629EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Covanta Lake County Energy produces

Free · EIA-923

Net generation, 2025

87.1 GWh

87,096 MWh, final

Capacity factor, 2025

64.1%

2024: 61.1%

January to July 2026

47.4 GWh

Provisional

Range, 2015 to 2025

67.3–87.1

GWh a year. Low 2017, high 2025

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
200132,016Not reported5 of 12
200290,114Not reported12 of 12
200382,185Not reported12 of 12
200484,079Not reported12 of 12
200586,068Not reported12 of 12
200687,577Not reported12 of 12
200788,407Not reported12 of 12
200884,327Not reported12 of 12
200979,738Not reported12 of 12
201080,48059.3%12 of 12
201190,31966.5%12 of 12
201287,55764.3%12 of 12
201380,62259.4%12 of 12
201471,11052.4%12 of 12
201580,61659.4%12 of 12
201681,27759.7%12 of 12
201767,25049.5%12 of 12
201886,63363.8%12 of 12
201977,29356.9%12 of 12
202077,77157.1%12 of 12
202183,24761.3%12 of 12
202281,23659.8%12 of 12
202382,41960.7%12 of 12
202483,20661.1%12 of 12
202587,09664.1%12 of 12
2026 (provisional, partial year)47,38360.1%7 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
GEN1Municipal Solid Waste15.5September 1990

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Covanta Lake Inc as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Generation potential vs reported

Monthly potential at seasonal net capability, next to EIA-923 output. Shows how much of the plant's capability was used.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Covanta Lake County Energy and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Covanta Lake County Energy

Questions about Covanta Lake County Energy

How much power does Covanta Lake County Energy produce?

Covanta Lake County Energy reported 87,096 MWh (87.1 GWh) of net generation in 2025, a 64.1% capacity factor on 15.5 MW of nameplate capacity. From January to July 2026 it reported 47.4 GWh, which is provisional.

Where is Covanta Lake County Energy?

Covanta Lake County Energy is in Lake County, Florida, at 28.7402, −81.8892. It is in the Progress Energy Florida balancing area (FPC).

Who operates Covanta Lake County Energy?

EIA-860M for August 2026 lists Covanta Lake Inc as the operator (EIA operator ID 4482). The operator is not always the owner.

When did Covanta Lake County Energy start operating?

Its first generator began operating in September 1990, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page