Other fuelsOperatingTEC

Mosaic Co Bartow Facility

Other fuels power plant in Polk County, Florida. 81.9 MW of nameplate capacity across 2 generators, operated by Mosaic Company.

Also known as Mosaic Company Bartow Cogen · EIA plant 50633

Analyst: free account, 1 question a day.

Bonnie Mine SolarMulberry Cogeneration FacilityBartow Solar Energy LLCOrange Cogeneration FacilityPeace Creek SolarJamison Solar (FL)Mosaic Co Bartow Faci…5 km
Open in the map
6 plants within 12 km, from EIA coordinates.

Key facts

Capacity
81.9 MWNameplate
Generators
2 operatingEIA-860M, August 2026
Operating since
December 1985First generator online
Operator
Mosaic CompanyEIA operator ID 3102
Grid
TECBalancing authority TEC
Price nodes
None linkedNo verified ISO node
Location
Polk County, FL27.9080, −81.9185
EIA plant ID
50633EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Mosaic Co Bartow Facility produces

Free · EIA-923

Net generation, 2025

171 GWh

171,013 MWh, final

Capacity factor, 2025

23.8%

2024: 22.9%

January to July 2026

110 GWh

Provisional

Range, 2015 to 2025

125.3–408.0

GWh a year. Low 2023, high 2019

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000497,027Not reported12 of 12
2001412,365Not reported12 of 12
2002125,203Not reported12 of 12
2003Not reportedNot reported0 of 12
2004453,761Not reported12 of 12
2005481,950Not reported12 of 12
2006412,142Not reported12 of 12
2007445,353Not reported12 of 12
2008383,370Not reported12 of 12
2009379,607Not reported12 of 12
2010406,28656.6%12 of 12
2011473,45466.0%12 of 12
2012433,50860.3%12 of 12
2013401,37655.9%12 of 12
2014181,50737.7%8 of 12
2015310,611Not reported12 of 12
2016353,52349.1%12 of 12
2017298,19241.6%12 of 12
2018351,76249.0%12 of 12
2019408,02256.9%12 of 12
2020343,17047.7%12 of 12
2021280,56039.1%12 of 12
2022201,82928.1%12 of 12
2023125,25517.5%12 of 12
2024165,06822.9%12 of 12
2025171,01323.8%12 of 12
2026 (provisional, partial year)110,42926.5%7 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
GEN1All Other36.9December 1985
GEN2All Other45.0August 1992

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Mosaic Company as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Generation potential vs reported

Monthly potential at seasonal net capability, next to EIA-923 output. Shows how much of the plant's capability was used.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Mosaic Co Bartow Facility and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Mosaic Co Bartow Facility

More plants operated by Mosaic Company

Questions about Mosaic Co Bartow Facility

How much power does Mosaic Co Bartow Facility produce?

Mosaic Co Bartow Facility reported 171,013 MWh (171 GWh) of net generation in 2025, a 23.8% capacity factor on 81.9 MW of nameplate capacity. From January to July 2026 it reported 110 GWh, which is provisional.

Where is Mosaic Co Bartow Facility?

Mosaic Co Bartow Facility is in Polk County, Florida, at 27.9080, −81.9185. It is in the Tampa Electric Company balancing area (TEC).

Who operates Mosaic Co Bartow Facility?

EIA-860M for August 2026 lists Mosaic Company as the operator (EIA operator ID 3102). The operator is not always the owner.

When did Mosaic Co Bartow Facility start operating?

Its first generator began operating in December 1985, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page