TES Filer City Station
Coal power plant in Manistee County, Michigan. 70 MW of nameplate capacity across 1 generator, operated by TES Filer City Station LP.
Also known as EIA plant 50835
Analyst: free account, 1 question a day.
Key facts
- Capacity
- 70 MWNameplate
- Generators
- 1 operatingEIA-860M, August 2026
- Operating since
- May 1990First generator online
- Operator
- TES Filer City Station LPEIA operator ID 18414
- Grid
- MISOBalancing authority MISO
- Price nodes
- 1 MISO nodeResource nodes with prices
- Location
- Manistee County, MI44.2173, −86.2891
- EIA plant ID
- 50835EIA plant page
Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.
How much power TES Filer City Station produces
Free · EIA-923Net generation, 2025
351 GWh
351,278 MWh, final
Capacity factor, 2025
57.3%
2024: 37.4%
January to July 2026
150 GWh
Provisional
Range, 2015 to 2025
230.2–510.4
GWh a year. Low 2024, high 2020
| Year | Net generation, MWh | Capacity factor | Months reported |
|---|---|---|---|
| 2000 | 492,153 | Not reported | 12 of 12 |
| 2001 | 146,448 | Not reported | 5 of 12 |
| 2002 | 268,902 | Not reported | 12 of 12 |
| 2003 | 458,857 | Not reported | 12 of 12 |
| 2004 | 44,078 | Not reported | 1 of 12 |
| 2005 | 448,582 | Not reported | 12 of 12 |
| 2006 | 490,179 | Not reported | 12 of 12 |
| 2007 | 484,115 | Not reported | 12 of 12 |
| 2008 | 482,382 | Not reported | 12 of 12 |
| 2009 | 501,694 | Not reported | 12 of 12 |
| 2010 | 493,743 | 80.5% | 12 of 12 |
| 2011 | 454,695 | 74.2% | 12 of 12 |
| 2012 | 492,294 | 80.1% | 12 of 12 |
| 2013 | 454,367 | 74.1% | 12 of 12 |
| 2014 | 413,088 | 80.9% | 10 of 12 |
| 2015 | 505,019 | 82.4% | 12 of 12 |
| 2016 | 124,880 | 81.7% | 3 of 12 |
| 2017 | 168,217 | 82.8% | 4 of 12 |
| 2018 | 123,576 | 81.7% | 3 of 12 |
| 2019 | 452,985 | 73.9% | 12 of 12 |
| 2020 | 510,430 | 83.0% | 12 of 12 |
| 2021 | 488,833 | 79.7% | 12 of 12 |
| 2022 | 498,457 | 81.3% | 12 of 12 |
| 2023 | 317,740 | 51.8% | 12 of 12 |
| 2024 | 230,199 | 37.4% | 12 of 12 |
| 2025 | 351,278 | 57.3% | 12 of 12 |
| 2026 (provisional, partial year) | 150,331 | 42.2% | 7 of 7 |
* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.
Power prices and basis
Free account · MISOEmissions
Free · EPA CAMPDCO₂, 2025
Not reported
US short tons. 2024: Not reported
SO₂, 2025
135
US short tons
NOx, 2025
869
US short tons
0 of 2 EPA units reported CO₂ in 2025 (1, 2), matched to EIA plant 50835 through the EPA–EIA crosswalk.
Water use
Free · EIA-923 cooling, USGSNo EIA cooling-water record for this plant in 2024.
Generators
Free · EIA-860M| Generator | Technology | Nameplate MW | Online since |
|---|---|---|---|
| GEN1 | Conventional Steam Coal | 70.0 | May 1990 |
Ownership and offtake
ProOwnership and offtake are part of Pro
Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists TES Filer City Station LP as the operator, which is not always the owner.
Modeled data
ProPro adds modeled values for this plant. Everything above stays free.
Generation potential vs reported
Monthly potential at seasonal net capability, next to EIA-923 output. Shows how much of the plant's capability was used.
300 analyst questions a month, plus MCP
Query TES Filer City Station and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.
Power plants near TES Filer City Station
Questions about TES Filer City Station
How much power does TES Filer City Station produce?
TES Filer City Station reported 351,278 MWh (351 GWh) of net generation in 2025, a 57.3% capacity factor on 70 MW of nameplate capacity. From January to July 2026 it reported 150 GWh, which is provisional.
Where is TES Filer City Station?
TES Filer City Station is in Manistee County, Michigan, at 44.2173, −86.2891. It is in the Midcontinent Independent Transmission System Operator, Inc.. balancing area (MISO).
Who operates TES Filer City Station?
EIA-860M for August 2026 lists TES Filer City Station LP as the operator (EIA operator ID 18414). The operator is not always the owner.
When did TES Filer City Station start operating?
Its first generator began operating in May 1990, according to EIA-860M.
Does InfraMap have power prices for TES Filer City Station?
Yes. InfraMap has MISO day-ahead and real-time prices at 1 price node linked to TES Filer City Station, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.
Sources
- EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
- EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
- EPA CAMPD annual emissions through the EPA–EIA crosswalk, 1995 to 2025
- MISO day-ahead and real-time prices; node and hub assignments as of 2026-10-05
Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page