Municipal solid wasteOperatingTEC

Hillsborough County Resource Recovery

Municipal solid waste power plant in Hillsborough County, Florida. 47 MW of nameplate capacity across 2 generators, operated by Hillsborough County - (FL).

Also known as EIA plant 50858

Analyst: free account, 1 question a day.

Bayside Battery StorageMosaic Co Tampa Facility5 km
Open in the map
5 plants within 14 km, from EIA coordinates.

Key facts

Capacity
47 MWNameplate
Generators
2 operatingEIA-860M, August 2026
Operating since
April 1987First generator online
Operator
Hillsborough County - (FL)EIA operator ID 8633
Grid
TECBalancing authority TEC
Price nodes
None linkedNo verified ISO node
Location
Hillsborough County, FL27.9549, −82.3405
EIA plant ID
50858EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Hillsborough County Resource Recovery produces

Free · EIA-923

Net generation, 2025

201 GWh

201,072 MWh, final

Capacity factor, 2025

48.8%

2024: 41.9%

January to July 2026

111 GWh

Provisional

Range, 2015 to 2025

173.1–273.3

GWh a year. Low 2024, high 2015

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001199,971Not reported12 of 12
2002186,941Not reported11 of 12
2003216,868Not reported12 of 12
2004186,729Not reported12 of 12
2005193,683Not reported12 of 12
2006197,478Not reported12 of 12
2007191,639Not reported12 of 12
2008194,770Not reported12 of 12
2009222,502Not reported12 of 12
2010288,27170.0%12 of 12
2011289,81470.4%12 of 12
2012299,39172.5%12 of 12
2013309,64675.2%12 of 12
2014282,84068.7%12 of 12
2015273,26866.4%12 of 12
2016272,93566.1%12 of 12
2017265,86664.6%12 of 12
2018246,62959.9%12 of 12
2019208,30054.8%11 of 12
2020206,48450.0%12 of 12
2021239,23058.1%12 of 12
2022237,18057.6%12 of 12
2023214,67052.1%12 of 12
2024173,07941.9%12 of 12
2025201,07248.8%12 of 12
2026 (provisional, partial year)111,04246.4%7 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
GEN1Municipal Solid Waste29.0April 1987
GEN2Municipal Solid Waste18.0June 2009

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Hillsborough County - (FL) as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Generation potential vs reported

Monthly potential at seasonal net capability, next to EIA-923 output. Shows how much of the plant's capability was used.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Hillsborough County Resource Recovery and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Hillsborough County Resource Recovery

Questions about Hillsborough County Resource Recovery

How much power does Hillsborough County Resource Recovery produce?

Hillsborough County Resource Recovery reported 201,072 MWh (201 GWh) of net generation in 2025, a 48.8% capacity factor on 47 MW of nameplate capacity. From January to July 2026 it reported 111 GWh, which is provisional.

Where is Hillsborough County Resource Recovery?

Hillsborough County Resource Recovery is in Hillsborough County, Florida, at 27.9549, −82.3405. It is in the Tampa Electric Company balancing area (TEC).

Who operates Hillsborough County Resource Recovery?

EIA-860M for August 2026 lists Hillsborough County - (FL) as the operator (EIA operator ID 8633). The operator is not always the owner.

When did Hillsborough County Resource Recovery start operating?

Its first generator began operating in April 1987, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page