Key facts

Capacity
14 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
April 1989First generator online
Operator
Wheelabrator Environmental SystemsEIA operator ID 20541
Grid
ISO-NEBalancing authority ISNE
Price nodes
1 ISONE nodeResource nodes with prices
Location
Merrimack County, NH43.2866, −71.5769
EIA plant ID
50873EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Wheelabrator Concord Facility produces

Free · EIA-923

Net generation, 2025

94.5 GWh

94,458 MWh, final

Capacity factor, 2025

77.0%

2024: 75.8%

January to July 2026

52.9 GWh

Provisional

Range, 2015 to 2025

90.7–101.5

GWh a year. Low 2022, high 2015

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001105,476Not reported12 of 12
2002105,028Not reported12 of 12
2003103,653Not reported12 of 12
2004105,112Not reported12 of 12
2005100,282Not reported12 of 12
2006102,942Not reported12 of 12
2007100,940Not reported12 of 12
2008101,948Not reported12 of 12
2009103,110Not reported12 of 12
2010101,73883.0%12 of 12
2011101,12282.5%12 of 12
2012102,99883.8%12 of 12
2013102,43883.5%12 of 12
2014101,30482.6%12 of 12
2015101,47282.7%12 of 12
2016100,00281.3%12 of 12
201799,35881.0%12 of 12
201897,30079.3%12 of 12
201999,34481.0%12 of 12
2020101,05282.2%12 of 12
2021100,57682.0%12 of 12
202290,65073.9%12 of 12
202392,89075.7%12 of 12
202493,17075.8%12 of 12
202594,45877.0%12 of 12
2026 (provisional, partial year)52,94874.3%7 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account · ISONE

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
GEN1Municipal Solid Waste14.0April 1989

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Wheelabrator Environmental Systems as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Generation potential vs reported

Monthly potential at seasonal net capability, next to EIA-923 output. Shows how much of the plant's capability was used.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Wheelabrator Concord Facility and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Wheelabrator Concord Facility

More plants operated by Wheelabrator Environmental Systems

Questions about Wheelabrator Concord Facility

How much power does Wheelabrator Concord Facility produce?

Wheelabrator Concord Facility reported 94,458 MWh (94.5 GWh) of net generation in 2025, a 77.0% capacity factor on 14 MW of nameplate capacity. From January to July 2026 it reported 52.9 GWh, which is provisional.

Where is Wheelabrator Concord Facility?

Wheelabrator Concord Facility is in Merrimack County, New Hampshire, at 43.2866, −71.5769. It is in the ISO New England Inc. balancing area (ISNE).

Who operates Wheelabrator Concord Facility?

EIA-860M for August 2026 lists Wheelabrator Environmental Systems as the operator (EIA operator ID 20541). The operator is not always the owner.

When did Wheelabrator Concord Facility start operating?

Its first generator began operating in April 1989, according to EIA-860M.

Does InfraMap have power prices for Wheelabrator Concord Facility?

Yes. InfraMap has ISONE day-ahead and real-time prices at 1 price node linked to Wheelabrator Concord Facility, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • ISONE day-ahead and real-time prices; node and hub assignments as of 2026-10-05

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page